Berg-Zimmer & Associates, Inc. v. Central Manufacturing Corp.

434 N.W.2d 834, 148 Wis. 2d 341, 1988 Wisc. App. LEXIS 1186
CourtCourt of Appeals of Wisconsin
DecidedDecember 21, 1988
Docket87-0822
StatusPublished
Cited by3 cases

This text of 434 N.W.2d 834 (Berg-Zimmer & Associates, Inc. v. Central Manufacturing Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berg-Zimmer & Associates, Inc. v. Central Manufacturing Corp., 434 N.W.2d 834, 148 Wis. 2d 341, 1988 Wisc. App. LEXIS 1186 (Wis. Ct. App. 1988).

Opinion

SULLIVAN, J.

Berg-Zimmer & Associates, Inc. (Berg-Zimmer) appeals from a judgment awarding it *344 $2,540 on its complaint for breach of contract and awarding Central Manufacturing Corporation (Central) $28,463.10 on its counterclaim. 1 We conclude that the trial court’s findings with respect to the $2,540 are not clearly erroneous and affirm. We also conclude that the trial court abused its discretion when it admitted documentary evidence that was hearsay. We reverse Central’s award and order its counterclaim remanded for further proceedings.

The facts are largely undisputed. The principal area of disagreement is the intent of the parties gleaned from their writings and conduct. On March 8, 1983, Berg-Zimmer, an engineering and consulting firm, entered into a contract with Central, a metal fabrication company, to provide shop drawings and designs for the Mitchell Field expansion project. Central was the fabricator subcontractor for Zalk Joseph, the primary structural steel fabricator for the project. Central contended in the trial court, as it does on appeal, that it agreed to pay a maximum of $7,680 for forty drawings, and that subsequently the contract was modified to provide for a maximum of $9,180 because Berg-Zimmer had completed eleven additional shop drawings. Berg-Zimmer has taken the position that the agreement provided a $17.50 charge per hour for work done on the drawings.

A bench trial was held from January 14 to 16,1987. Central filed a post-trial amended counterclaim on *345 January 22, 1987, which alleged negligence and breach of contract by Berg-Zimmer in that the shop drawings failed to conform to the specifications provided by Central. After reviewing the shop drawings, Central fabricated the steel pieces in conformity with the shop drawings. When Central’s erecting subcontractor, Sy-phax Steel Corporation (Syphax), attempted to place the steel plates, they did not fit and required refabrication. Syphax charged Central more than $28,000 for the additional work. Berg-Zimmer denied any negligence or breach of contract.

The trial court made the following findings:

(1) Central and Berg-Zimmer had agreed to contract for up to forty drawings at a maximum price of $7,680, and not at an hourly rate of $17.50;
(2) Both parties agreed to modify the contract to provide for a maximum payment of $9,180 for the additional eleven shop drawings;
(3) Central only had to pay for shop drawing revisions that the project architects approved, which totaled $360; and
(4) Berg-Zimmer had breached the contract and was negligent in its failure to prepare accurate shop drawings.

Construction of a written contract is normally a question of law and is therefore reviewed independently. Lambert v. Wrensch, 135 Wis. 2d 105, 115, 399 N.W.2d 369, 373-74 (1987). However, if an ambiguity exists which requires resort to extrinsic evidence for resolution, an issue of fact is presented. Id. at 115 n. 8, 399 N.W.2d at 374 n. 8. We affirm a trial court’s fact-findings unless they are clearly erroneous. Sec. *346 805.17(2), Stats; Noll v. Dimiceli’s, Inc., 115 Wis. 2d 641, 643, 340 N.W.2d 575, 577 (Ct. App. 1983). In this case, the trial court used extrinsic evidence to resolve the ambiguity concerning the price of the drawings and whether the parties agreed to a modification of the contract. We conclude that the contract was ambiguous and therefore an issue of fact is presented.

The parties agree that Berg-Zimmer hand-delivered an offer to Central on March 8,1983. Berg-Zimmer offered to do thirty-seven to forty drawings and designs at “$17.50 per hour base” and “Rework — $17.50 per hour." Michael Gagnon (Gagnon), a Berg-Zimmer salesperson, delivered it to George Gillis (Gillis), Central's production manager, in Gillis’ office. Due to budget constraints, Gillis agreed to pay a maximum of $7,680 for forty drawings. Gillis calculated thirty-two heavy sheet drawings at $200 each and eight light sheet drawings at $160 each. 2 Gillis then took the offer to Central’s president, Irvin Palmer (Palmer), who approved the offer. Gillis returned to Gagnon, who agreed to the $7,680 figure. Gillis and Gagnon then discussed the matter of corrections.

Berg-Zimmer presented evidence that the contract was for a flat $17.50 per hour. Specifically, Berg-Zim-mer’s invoices to Central were based on an hourly rate, and Central paid the invoices. However, on September 28, 1983, Central forwarded a debit memorandum to Berg-Zimmer stating its invoices exceeded the $7,680 contract price by $1,358.75.

We conclude that the evidence conflicted on the matter of the contract price. The trial court’s finding that the contract price was for $7,680 is supported by *347 credible evidence and is not clearly erroneous. See sec. 805.17(2), Stats.

The trial court also found that the parties modified the contract in November of 1983. Berg-Zimmer asserts that the fact that it continued sending invoices to Central after November at the hourly rate proves it never agreed to any modification.

It is without dispute that in November of 1983, Gillis, Palmer and Russell Berg (Berg), president of Berg-Zimmer, discussed a revised contract price because Berg-Zimmer had completed eleven additional shop drawings. The evidence clearly proves that the parties determined upon a new price of $9,180 as a result of compromise, and that it was arrived at by multiplying fifty-one drawings by $180, the price per drawing. 3

During the November meeting, Palmer wrote notes on the March 8,1983 document from Berg-Zimmer, and in the presence of Gillis and Berg, Palmer wrote “51 shts @ 180 =$9180.00, 11-17-83, IRV RUS GEO.” On December 8, 1983, Central forwarded a purchase order to Berg-Zimmer confirming the $9,180 price. Berg conceded in a deposition, and at trial, that the invoice was his “potential understanding.” Berg-Zimmer did not send additional invoices to Central after December 8, nor did it notify Central that it would not accept the modification. Based upon the November agreement, Berg-Zimmer’s failure to object to the December 8 purchase order, and all surrounding circumstances, the trial court found that Berg-Zimmer had accepted the *348 modification. We uphold the findings of the trial court in this conflicting fact scenario because they are not clearly erroneous and because it was the particular duty of the court to evaluate the credibility of witnesses. See sec. 805.17(2), Stats. A modified contract need not be supported by new consideration and may be manifested by the actions of the parties. See Smith v. Osborn, 66 Wis. 2d 264, 277, 223 N.W.2d 913

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Angela Lee Linsmeyer v. Jason Scott Linsmeyer
Court of Appeals of Wisconsin, 2020
PALISADES COLLECTION LLC v. Kalal
2010 WI App 38 (Court of Appeals of Wisconsin, 2010)
Leitzke v. Magazine Marketplace, Inc.
484 N.W.2d 364 (Court of Appeals of Wisconsin, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
434 N.W.2d 834, 148 Wis. 2d 341, 1988 Wisc. App. LEXIS 1186, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berg-zimmer-associates-inc-v-central-manufacturing-corp-wisctapp-1988.