Berenyi Inc v. Nucor Corporation

CourtDistrict Court, D. South Carolina
DecidedJuly 13, 2022
Docket2:20-cv-03170
StatusUnknown

This text of Berenyi Inc v. Nucor Corporation (Berenyi Inc v. Nucor Corporation) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Berenyi Inc v. Nucor Corporation, (D.S.C. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF SOUTH CAROLINA CHARLESTON DIVISION IN ADMIRALTY

BERENYI, INC., ) ) Plaintiff, ) ) vs. ) ) NUCOR CORPORATION, by and through its ) No. 2:20-cv-03170-DCN Berkeley Division; KINDER MORGAN ) BULK TERMINALS, LLC f/k/a/ KINDER ) ORDER MORGAN BULK TERMINALS, INC.; and ) KINDER MORGAN MID ATLANTIC ) MARINE SERVICES, LLC, ) ) Defendants. ) _______________________________________)

This matter is before the court on defendants Kinder Morgan Bulk Terminals, LLC f/k/a Kinder Morgan Bulk Terminals, Inc. (“Kinder Morgan Terminals”) and Kinder Morgan Mid Atlantic Marine Services, LLC’s (“Kinder Morgan MS”) (collectively, “Kinder Morgan” or the “Kinder Morgan defendants”) motion for summary judgment, ECF No. 45, and plaintiff Berenyi, Inc.’s (“Berenyi”) motion to amend the scheduling order to permit the filing of an amended complaint, ECF No. 63. For the reasons set forth below, the court denies Berenyi’s motion to amend and denies the Kinder Morgan defendants’ motion for summary judgment. I. BACKGROUND Defendant Nucor Corporation (“Nucor”) manufactures steel products in the United States. It owns and operates a steel facility in Berkeley County, South Carolina. The facility includes an inland port, or berth, on the Cooper River which Nucor uses to unload materials from barges for transport to the facility. In 2016, Nucor hired Berenyi as a contractor to design, excavate, and construct an extension to the berth. Berenyi devised a plan to drive sheet piling into the eastern end of the existing berth, thus forming a temporary sheet pile wall where the existing and expanded berth would join. The sheet pile wall was intended to prevent water from the Cooper River from flowing into the area behind the wall while it was being excavated to form the expanded berth.

While the berth extension project was ongoing, Nucor continued to use the berth to transport materials to its facility. As part of that work, Kinder Morgan Terminals had previously entered into an Independent Contractor Agreement with several Nucor entities, including Nucor’s Berkeley Division, to provide workmen and equipment for processing, warehousing, stevedoring, and other marine services. Kinder Morgan MS owned a fleet of barges that were used to deliver materials to Nucor’s port facility. Stevens Towing Co., Inc. (“Stevens Towing”) was hired to tow the barges to Nucor’s port, and both Kinder Morgan and Stevens Towing were responsible for tying up the barges to the berth.

On September 8, 2017, the Nucor facility was shut down due to the threat posed by Hurricane Irma. All but a few Nucor employees were released from their shifts, and similarly, Berenyi and Kinder Morgan employees were ordered to shut down operations and secure their equipment in preparation for the storm. As a result, the only individuals present at the facility on the night of September 8 were the maintenance and safety personnel who were shutting down the manufacturing plant. During the night, the temporary sheet pile wall collapsed, causing water to flood into the excavated area of the extended berth. A Nucor employee discovered the collapsed wall at approximately 5:30 a.m. on September 9. No one had witnessed the collapse. According to the complaint, a barge or barges owned by Kinder Morgan MS caused the collapse when the barge or barges allided with the sheet pile wall. On September 3, 2020, Berenyi filed suit against Nucor, the Kinder Morgan defendants, and Stevens Towing1 in this court, alleging causes of action for negligence and gross negligence. ECF No. 1, Compl. On February 14, 2022, the Kinder Morgan defendants filed their motion for

summary judgment. ECF No. 45. Berenyi responded in opposition on March 23, 2022, ECF No. 54, and the Kinder Morgan defendants replied on April 7, 2022, ECF No. 59. On May 11, 2022, Berenyi filed its motion styled as a motion to amend the scheduling order to permit the filing of an amended complaint.2 On May 25, 2022, the Kinder Morgan defendants responded in opposition. Berenyi did not file a reply, and the time to do so has now elapsed. On June 9, 2022, the court held a hearing on both motions. ECF No. 69. As such, both motions have been fully briefed and are now ripe for review. II. STANDARD A. Motion to Amend

“[A]fter the deadlines provided by a scheduling order have passed, the [Rule 16(b)] good cause standard must be satisfied to justify leave to amend the pleadings.” Nourison Rug Corp. v. Parvizian, 535 F.3d 295, 298 (4th Cir. 2008). Rule 16(b)’s good cause standard “focuses on the timeliness of the amendment and the reason for its tardy submission; the primary consideration is the diligence of the moving party.” Montgomery v. Anne Arundel Cnty., 182 F. App’x 156, 162 (4th Cir. 2006); see RFT

1 Stevens Towing was voluntarily dismissed from the action on March 30, 2022. ECF No. 56. 2 For ease of reference, the court simply refers to the motion as a motion to amend. Mgmt. Co., LLC v. Powell, 607 F. App’x 238, 242 (4th Cir. 2015). “In seeking leave to amend, the ‘movant must demonstrate that the reasons for the tardiness of his motion justify a departure from the rules set by the court in its scheduling order.’” Thomason v. Toyota Motor Eng’g & Mfg. N. Am., Inc., 2017 WL 10901214, at *6 (D.S.C. Mar. 6, 2017) (citing United States v. Godwin, 247 F.R.D. 503, 506 (E.D.N.C. 2007)).

“If the movant satisfies Rule 16(b)’s ‘good cause’ standard, [he] must then pass the requirements for amendment under Rule 15(a).” Dilmar Oil Co. v. Federated Mut. Ins. Co., 986 F. Supp. 959, 980 (D.S.C. 1997). Under Rule 15, a party may amend a pleading as a matter of course within 21 days after serving it; however, in all other cases, a party may amend its pleading only with the opposing party’s consent or the court’s leave. Fed. R. Civ. P. 15(a). “The court should freely give leave when justice so requires.” Fed. R. Civ. P. 15(a)(2). “A motion to amend should be denied ‘only when the amendment would be prejudicial to the opposing party, there has been bad faith on the part of the moving party, or the amendment would be futile.’” HCMF Corp. v. Allen,

238 F.3d 273, 276 (4th Cir. 2001) (quoting Edwards v. City of Goldsboro, 178 F.3d 231, 242 (4th Cir. 1999)) (emphasis in original). B. Motion for Summary Judgment Summary judgment shall be granted if the pleadings, the discovery and disclosure materials on file, and any affidavits show that there is no genuine dispute as to any material fact and that the movant is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(c). “By its very terms, this standard provides that the mere existence of some alleged factual dispute between the parties will not defeat an otherwise properly supported motion for summary judgment; the requirement is that there be no genuine issue of material fact.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247–48 (1986). “Only disputes over facts that might affect the outcome of the suit under the governing law will properly preclude the entry of summary judgment.” Id. at 248. “[S]ummary judgment will not lie if the dispute about a material fact is ‘genuine,’ that is, if the evidence is such that a reasonable jury could return a verdict for the nonmoving party.”

Id. “[A]t the summary judgment stage the judge’s function is not himself to weigh the evidence and determine the truth of the matter but to determine whether there is a genuine issue for trial.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Louisiana
70 U.S. 164 (Supreme Court, 1866)
The Oregon
158 U.S. 186 (Supreme Court, 1895)
Johnson v. United States
333 U.S. 46 (Supreme Court, 1948)
Pope & Talbot, Inc. v. Hawn
346 U.S. 406 (Supreme Court, 1953)
Foman v. Davis
371 U.S. 178 (Supreme Court, 1962)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
In Re Kunstler.
914 F.2d 505 (Fourth Circuit, 1990)
Montgomery v. Anne Arundel County
182 F. App'x 156 (Fourth Circuit, 2006)
Nourison Rug Corp. v. Parvizian
535 F.3d 295 (Fourth Circuit, 2008)
Connelly v. General Medical Corp.
880 F. Supp. 1100 (E.D. Virginia, 1995)
Dilmar Oil Co., Inc. v. Federated Mut. Ins. Co.
986 F. Supp. 959 (D. South Carolina, 1997)
Goewey v. United States
886 F. Supp. 1268 (D. South Carolina, 1995)
Schumacher v. Cooper
850 F. Supp. 438 (D. South Carolina, 1994)
Witt v. AMERICAN TRUCKING ASS'N, INC.
860 F. Supp. 295 (D. South Carolina, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
Berenyi Inc v. Nucor Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/berenyi-inc-v-nucor-corporation-scd-2022.