Benson v. County of Kern

208 P. 141, 58 Cal. App. 137, 1922 Cal. App. LEXIS 320
CourtCalifornia Court of Appeal
DecidedJune 16, 1922
DocketCiv. No. 3849.
StatusPublished

This text of 208 P. 141 (Benson v. County of Kern) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Benson v. County of Kern, 208 P. 141, 58 Cal. App. 137, 1922 Cal. App. LEXIS 320 (Cal. Ct. App. 1922).

Opinions

This is an action to recover damages for the breach of a contract entered into between plaintiffs and defendant whereby plaintiffs engaged to construct a certain highway for defendant. Judgment went for the latter and plaintiffs appeal.

The contract between the parties provided for the building of nearly eleven miles of road. Appellants had entered upon the performance of the work, had fully completed more than four miles of the road and had done the preliminary work of clearing the land throughout the remainder of the distance, when the uncompleted portion of the highway was "eliminated" from the contract. Notice of this elimination was given orally to appellant, according to some of the testimony, by the engineer and certain members of the highway commission of respondent and appellants were by the engineer, according to his own testimony, ordered to "shut down" the work under the *Page 138 contract. Later, on December 6, 1917, the clerk of the board of supervisors of respondent wrote appellants that on that day the board had by resolution "eliminated that portion of the work provided for by contract and specifications" which had not been completed, the portion thus "eliminated" being particularly described in the letter. The notice to shut down work on the uncompleted part of the highway and the elimination of that part of it from the contract constitute the principal breach of which appellants complain. There is also an allegation in the complaint to the effect that appellants were damaged in a certain amount by reason of respondent's delay for a specified number of days in furnishing a quantity of broken stone and screenings to be used in the work and agreed by respondent to be furnished by it therefor. This allegation apparently refers to materials used in constructing the completed portion of the road, but as the trial court found the averment to be untrue, and as the finding is not assailed by appellant, we shall consider the action as if it were one commenced to recover damages alone for what we have termed the principal breach of the contract.

[1] It was alleged in the answer and found by the trial court that the elimination of the uncompleted portion of the highway from the contract was made pursuant to a mutual agreement of the parties to that end. Appellant contends that the court's finding on this subject is not supported by the evidence, and, as we view the case, the determination of the appeal depends upon the solution of this question alone. One of the members of the board of supervisors of respondent testified, in part: "I had a conversation with the plaintiffs in this case concerning the contract now before the court. I do not remember the exact date, but it was some time during the fall of 1917. The conversation was with Mr. Paul Benson. . . . I cannot give the exact words. . . . As I understand, Mr. Benson's position was that if they were compelled by the county to complete the entire contract, there was a doubt whether there would be funds enough to pay them. . . . I cannot give the exact language, but Mr. Benson was attempting to ascertain from me what the disposition of the board of supervisors of the county would be toward settling the contract in full, and they got me to admit in my judgment there wouldn't be *Page 139 money to pay them. . . . The Court: Q. Do you mean . . . Mr. Benson asked you what would be the attitude of the board of supervisors? A. Yes, sir. Q. He said he thought there was not funds? A. And I agreed with him . . . he stated that it would interfere with his business for the county to compel him to carry out the contract when it was a general rumor that there wouldn't be funds enough to settle for the work if he did it, and then he went to ask me some questions as to what the board thought about that, and then afterward he took up with me the question of [if (?)] it, the contract, a portion of it was eliminated, then what would the board of supervisors do toward paying him for the necessary work to complete what he called the long haul of the contract. . . . I had several conversations with the same gentleman concerning this contract. The second conversation was in the office and he introduced his father. We talked along the same lines somewhat at that time and I recall another time that he was in the board of supervisors' room, not where we were in formal session, but we were all up there, I mean the board of supervisors. . . . Mr. Claude Benson brought his father in and introduced him. . . . I had another conversation about the contract in question in the supervisors' room. I think all of the members of the board of supervisors were there. . . . The conversation that was had in the presence of these supervisors was in reference to the amount which would be right to be paid Mr. Benson for the excess cost of the work which was completed. The substance of the conversation was that the board of supervisors would be willing to pay this additional cost if there was money enough in the fund to pay it and the district attorney would advise us it was a legal charge against the county. By the extra work I mean that Mr. Benson explained to me that owing to the other work that he had been expecting to do, the entire contract, and also owing to the fact that the pieces that he was to complete was further away from his hauling point that it would cost more than the average if he had the entire contract, and that it wasn't fair to ask him to do the hard end of the contract and have the easy or lowest average eliminated. I agreed with him on that point, and I assured him that I was satisfied that the board of supervisors wouldn't insist upon his completing the entire contract as *Page 140 long as there was doubt as to being enough money in the fund to pay for it if completed. . . . At the particular time in my office Mr. Benson stated that there was doubt as to whether there was money enough to pay for the entire contract if it was completed. . . . I have related all that I can recall at this time of the conversation I had with Claude Benson, one of the plaintiffs in this action, concerning the contracts in question. I do not recall any other reason being stated in any of these conversations with Claude Benson why he and his partners desired to be relieved from the contract except what I have stated. He desired to be relieved of it owing to the condition of the funds. I have no recollection of any proceedings in the matter except the resolution passed eliminating that portion of the work." This testimony was all given on direct examination and it was followed by a cross-examination which served to strengthen the witness' story as to the conversations between him and Claude Benson. We reproduce but two of the statements of the witness on cross-examination: "I know we both [he and Benson] agreed in regard to the fairness of cancelling the contract instead of demanding that they go on, and also as to the fairness of his being paid the right figure for the work he had completed and was going to complete in order to use up the material on the ground as I understood it. . . . I do not think he [Benson] put it in the manner, that the Highway Commission had eliminated it, but putting it rather as a suggestion that the contract would be partially canceled and after I agreed with him either at that time or at subsequent meetings, why, we went on and discussed the amount of what would be fair to him in the matter of payment for the part that he had completed." This testimony was substantially corroborated by a witness who was a member of the highway commission of respondent during the year 1917, as he testified to similar conversations with one or more of appellants.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
208 P. 141, 58 Cal. App. 137, 1922 Cal. App. LEXIS 320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/benson-v-county-of-kern-calctapp-1922.