Bennett v. Mingjing Industrial Group Agricultural Technology Co. LLC

CourtSuperior Court of Maine
DecidedOctober 21, 2021
DocketANDre-19-30
StatusUnpublished

This text of Bennett v. Mingjing Industrial Group Agricultural Technology Co. LLC (Bennett v. Mingjing Industrial Group Agricultural Technology Co. LLC) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bennett v. Mingjing Industrial Group Agricultural Technology Co. LLC, (Me. Super. Ct. 2021).

Opinion

STATE OF MAINE SUPERIOR COURT ANDROSCOGGIN, ss. CIVIL ACTION DOCKET NO.: RE-19-30 RE-19-34 RE-19-38 RE-19-43 (Consolidated)

ROBERT H. BENNETT d/b/a R.H. BENNETT & SONS CONSTRUCTION and RH BENNETT AND SONS CONSTRUCTION LLC,

Plaintiffs ORDER ON DEFENDANTS' MOTION V. FOR SUMMARY JUDGMENT

MINGJING INDUSTRIAL GROUP AGRICULTURAL TECHNOLOGY CO. LLC and MINGTING INDUSTRIAL GROUP LTD. USA, LLC and MINGTING INDUSTRIAL GROUP CO. LTD.,

Defendants

NORTHERN LIGHTS MECHANICAL, LLC,

Plaintiff

v.

MINGJING INDUSTRIAL GROUP AGRICULTURAL TECHNOLOGY CO. LLC, et al.,

1 HANCOCK LUMBER COMPANY, INC.,

MINGTING INDUSTRIAL GROUP AGRICULTURAL TECHNOLOGY CO. LLC, et al.,

PD DRYWALL, LLC,

MINGTING INDUSTRIAL GROUP AGRICULTURAL TECHNOLOGY CO. LLC, et al.,

The matter before the court is Defendant Mingjing Industrial Group Agricultural

Technology Co. LLC's ("Mingjing") motion for summary judgment in all of the consolidated

lawsuits. For the following reasons, the motion will be denied.

Background

Mingjing is a limited liability company in Auburn, Maine. (Supp.'g S.M.F. ,r 1.) In July

of 2018, Mingjing signed two contracts with Robert H. Bennett d/b/a R.H. Bennett & Sons

Construction ("Bennett") to serve as a general contractor to build two houses in Auburn. (Id. ,r

3.) Pursuant to the first contract, dated July 18, 2018, Bennett agreed to build a single-family

home and attached garage at 694 Main Street, Auburn, Maine, (since renamed 12 Mingjing

Lane) for a price of$421,763.57. (Id. ,r 5.) The second contract, dated July 27, 2018, was also

2 for a single-family home located at 694 Main Street, Auburn, (since renamed 28 Mingjing Lane)

for a price of$730,028.21. (Id. ,i 6.) Both contract prices are expressly subject to additions and

deductions as provided by the contracts. (Trustee's Ex. 3, at 21; Trustee's Ex. 4, at 29.)

Both contracts contained the following provision regarding change orders:

4. CHANGE ORDERS: Owners reserve the right to order work changes in the nature of additions, deletions, or modifications, and agree to make corresponding adjustments in the contract price and completion date. Any alteration or deviation from the above contractual specifications that results in a revision of the estimated contract price will be executed only upon the parties entering into a written change order. Each change order must detail changes to the original Agreement that result in a revision of the contract price and must state the previous contract price and the revised contract price. Each change order must be agreed to and signed by both parties prior to commencement of work involved in the change order.

(Id. ,i 12.) Bennett and Mingjing agreed to several change orders to the contracts, following the

change order procedure in the above contract provision. (Id. ,i 14.) All of these change orders

were timely paid. (Id. ,i 15.)

The contracts both name an estimated completion date of January 31, 2019, subject to

certain conditions. 1 The contracts further provide:

7. DELAY IN PERFORMANCE: In the event that the Contractor is delayed at any time in the progress of the work by changes in the work, by the lack of readiness of the job site, by the unavailability of building materials, by labor disputes, fire, unusual delays in transportation, unavoidable casualties, or any other conditions beyond the Contractor's control, then the time for completion of the work shall be extended for such reasonable period as is necessary. The Contractor will notify the Owner immediately in writing of any substantial delay in completion of the project including reasons with revised completion date.

(Trustee's Ex. 3, at 23; Trustee's Ex. 4, at 31.) The contracts leave material selection to

Mingjing, providing that "the estimates incorporated herein provide for allowances for certain

1 Mingjing characterizes this date as a binding deadline. (See Mot. Summ. J. 5.) The court can find no support for

this claim, as the contract provision containing the January 31, 2019 date is titled "Estimated Commencement & Completition Date" and only states that the contractor "expects" to complete the work by January 31, 2019, subject to conditions enumerated in a separate paragraph. (Trustee's Ex. 3, at 22; Trustee's Ex. 4, at 30.)

3 materials to be incorporated into the project as selected by the Owner ... materials selected by

them will determine the actual cost to the Owner for such materials, which actnal cost may be

more or less than the amount shown on the estimates as allowances." (Supp.'g S.M.F. ,r,r 5-6;

Trustee's Add. S.M.F. ,r,r 45-46.)

Work on the contracts continued well after the estimated January 31, 2019 completion

date specified in the contracts. On January 24, 2019, Bennett sent a letter to Mingjing describing

the status of the projects and explaining the delays. 2 (Trustee Add. S.M.F. ,r 48.) The letter

projected completion dates of April 31, 2019 for 28 Mingjing Lane and May 30, 2019 for 12

Mingjing Lane, subject to further delays from weather and subcontractor scheduling. (Id.)

Bennett continued work on the projects and Mingjing continued to make payments until May 1,

2019. (Id. if 49.)

A Certificate of Occupancy for 28 Mingjing Lane was issued by the City of Auburn on

June 7, 2019. (Id. ,r 50.) Bennett ceased work on both projects afterwards, as Mingjing had

ceased making payments. (Trustee's Resp. Supp.'g S.M.F. ,r 19; Supp.'g S.M.F. ,r 19.) Mingjing

never made any fwiher payments and work on the projects never resumed. (Id. ,r 20.)

Bennett recorded a mechanic's lien on 12 Mingjing Lane on September 9, 2019 in the

Androscoggin County Registry of Deeds at Book 10176, Page 54. (Trustee Add. S.M.F. ,r 52.)

Bennett also recorded a mechanic's lien on 28 Mingjing Lane on the same day, in the

Androscoggin County Registry of Deeds at Book 10176, Page 57. (Id. ,r 53.) Three of Bennett's

subcontractors also filed mechanic's liens against the properties; Hancock Lumber Company,

Inc. ("Hancock Lumber"), Northern Lights Mechanical, LLC ("Northern Lights"), and PD

2 Mingjing claims that this letter was not "accepted or agreed to" by Mingjing and that it was not a valid change order under the contracts. (Resp. Trustee Add. S.M.F.1\ 47.) The Trustee does not claim that the letter was a change order. (See Trustee Add. S.M.F. 1148.)

4 Drywall, LLC ("PD Drywall"). (Supp.'g S.M.F. '\[ 22.) Mingjing never had a direct contractual

relationship with any of Bennett's subcontractors, nor has it ever directly paid or promised to pay

them. (Id. ,r,r 24-26.) Bennett and the three subcontractors subsequently filed lawsuits to enforce

these liens and seeking recovery on other grounds, which have all been consolidated into this

lawsuit.

Bennett has filed for Chapter 7 bankruptcy since initiating this lawsuit. (Id. '\[ 37.) The

Chapter 7 Interim Trustee in Bankruptcy has intervened in this lawsuit to continue pursuing the

claim. (See Opp. Mot. Summ. J. 2.)

Standard

Summary judgment is granted to a moving party where "there is no genuine issue as to

any material fact" and the moving party "is entitled to judgment as a matter of law." M.R. Civ. P.

56(c). "A material fact is one that can affect the outcome of the case, and there is a genuine issue

when there is sufficient evidence for a fact-finder to choose between competing versions of the

fact." Lougee Conservancy v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Runnells v. Quinn
2006 ME 7 (Supreme Judicial Court of Maine, 2006)
Pond Cove Millwork Co. v. Steeves
598 A.2d 1181 (Supreme Judicial Court of Maine, 1991)
Nadeau v. Pitman
1999 ME 104 (Supreme Judicial Court of Maine, 1999)
Pendleton v. Sard
297 A.2d 889 (Supreme Judicial Court of Maine, 1972)
Lougee Conservancy v. Citimortgage, Inc.
2012 ME 103 (Supreme Judicial Court of Maine, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Bennett v. Mingjing Industrial Group Agricultural Technology Co. LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bennett-v-mingjing-industrial-group-agricultural-technology-co-llc-mesuperct-2021.