Bennett v. Dayton

135 S.E. 13, 102 W. Va. 197, 1926 W. Va. LEXIS 105
CourtWest Virginia Supreme Court
DecidedSeptember 28, 1926
Docket5639
StatusPublished
Cited by1 cases

This text of 135 S.E. 13 (Bennett v. Dayton) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bennett v. Dayton, 135 S.E. 13, 102 W. Va. 197, 1926 W. Va. LEXIS 105 (W. Va. 1926).

Opinion

Hatcher, Judge:

This action was brought in the circuit court of Randolph County to recover damages for the breach of a contract. „ A trial was had at the March Term, 1925, resulting in a verdict in favor of plaintiffs for $2531.57. The defendants moved to set aside the verdict as excessive and as contrary to the law and the evidence. The court took the matter under advisement until the October Term, 1925,. when the motion of defendants was sustained and a new trial awarded. The case is here on a writ allowed the plaintiffs.

On May 17, 1921, a contract was made between the plaintiffs as first parties, and the defendants as second parties, the pertinent parts of which are as follows:

“THE SAID PARTIES OF THE FIRST PART are to furnish crushed lime stone to the second in at least the amount of 4000 net tons F. O. B. Faulkner, at $2.75 per net ton, for the wearing coat of the Elkins-Beverly project No. 78 Class A.Federal Aid Road, the said lime stone to be so crushed or manufactured to meet the requirements of the State specifications for bituminous macadam road.
“The said parties of the first part to begin shipment of said stone in the month of June, when the said second party gives notice so to do and to continue shipping said stone at the rate of one car load per day until the said 4000 tons are furnished.
“It is further understood that the said stone shall be shipped in drop bottom hoppers, but in case of shortage of cars, breakdowns, or other *199 unavoidable accidents which may prevent the said first parties from shipping said stone as rapidly as heretofore agreed upon, the said first parties shall not be liable for damages to the said parties of the second part, but the said parties of the second part shall have the right to purchase said stone from elsewhere until the said first parties can resume shipment.”

In June defendant Dayton told plaintiff Bennett that he would not “be ready to start at the specified time to use the stone”, and Bennett said “it was perfectly satisfactory, that he wanted to make a general overhauling of the crusher”. Notice to begin shipments was not given until July 9, and shipments were not commenced until July 19, when two cars were shipped. Another car was shipped July 20. The defendants claimed that these three cars were “out of the question for top surface use”. Bennett was sent for, and it was mutually agreed that defendants should take the stone at $1.75 a ton, and use it on the base. The plaintiffs re-adjusted their screens and commenced shipping again on August 1. During August and September they shipped defendants 32 cars. Bennett testified that the failure of plaintiffs to ship a car daily, (as provided by the contract), was unavoidable. Some of the stone shipped after August 1 was condemned by the road inspectors, and the defendants had to regrade, or clean, or otherwise prepare such stone before using it. Deductions were made at the time by defendants from the contract price for whatever such preparation cost. These adjustments were agreed to by plaintiffs.

On Oct. 5, the defendants wrote the plaintiffs as follows:

“Please stop shipment of all limestone, except two car loads of chips, to Elkins, as we need them at once. This is not due to bad stone, but to the fact that owing to the excessive freight rates and bad weather we are not using any more stone this year. We have a tank of tarvia here now and as soon as we get it on will close down for this fall.”

The plaintiffs shipped seven cars after receiving this letter. The two cars which contained the chips were accepted by *200 defendants. The other five cars were rejected. On Oct. 11, the defendants again wrote the plaintiffs: “We understand that you are still ordering ears shipped to Beverly, and this is to notify you that all stone will be refused except the two cars we agreed verbally to unload. ’ ’

The plaintiffs say that all of the stone in the five cars which were rejected had already been prepared when they received the letter of Oct. 5, and that three of the cars were already loaded. Bennett also testified that it required the manufacture of the five cars rejected, to get the two cars of “chips.” The plaintiffs testify that the five cars rejected, substantially met the State’s specifications; the defendants testify that they did not. Defendants admit that they had not provided tarvia for any stone except what was on hand on Oct. 5.

The five rejected cars were finally sold by the railroad company. The amount realized was small, leaving $325.47 due on demurrage. This sum was paid by plaintiffs.

The defendants accepted and paid for 1910.55 tons. The five rejected ears contained 267 tons.

On March 30, 1922, the plaintiffs notified the defendants in writing that they were ready and willing, upon notice from defendants, to comply with the contract of May, 1921, in “every particular.” The defendants made no reply and never ordered any more stone.

The only other contractors in that section who were operating in the spring of 1922, were Bramham and Yeater. These contractors had a road project, which commenced five miles from the railroad. In order to secure a contract with them, it was necessary for the plaintiffs to agree to deliver the stone. In making this delivery, the plaintiffs had to unload the stone from the railroad cars and haul, it across country five miles. The unloading was done by means of a mechanical unloader. The price paid by Bramham and Yeater was $2.85 a ton, delivered. The plaintiffs expended 85c a ton to transport, and 10c a ton to unload this stone.

The plaintiffs demand in this suit 75c a ton damage on the stone not taken by defendants under the contract, $2.75 a ton for the five cars rejected, .together with the demurrage *201 paid thereon, and $210.00 as rental on the unloader, used in unloading the stone sold to Bramham and Yeater. The defendants claim set-offs amounting to $17,885.00. Of this amount $203.00 is for “cost of re-breaking — napping and harrowing, 29 car loads of stone not crushed in accordance with contract, at $7.00 per car.” The balance of the offsets is for damages due to failure of plaintiffs to ship all of the stone in the summer of 1921 as provided by the contract.

The verdict of the jury indicates that small heed was paid to the defendants’ offsets. The defendants had the right to reject any of the stone shipped which was not according to specifications. However, adjustments were made at the time for inferior quality, and the stone was used. The defendants cannot now justify their refusal to complete the contract, on the ground of poor quality. This defense is precluded by the letter of Oct. 5, stating that the suspension order was not due to bad stone but to excessive rates and bad weather. “When refusal to accept goods purchased is based solely upon a particular objection, formally and deliberately stated, all other objections are deemed waived”. Linger v. Wilson, 73 W. Va.669. Damages for unavoidable failure to ship one car daily are expressly prohibited by the contract. The defendants offered no evidence in contradiction of Bennett’s testimony that the delays were unavoidable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burner v. Smith Coal Co.
147 S.E. 545 (West Virginia Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
135 S.E. 13, 102 W. Va. 197, 1926 W. Va. LEXIS 105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bennett-v-dayton-wva-1926.