Bennett Road Sewer Co. v. Town Board of Town of Camillus

243 A.D.2d 61, 672 N.Y.S.2d 587, 1998 N.Y. App. Div. LEXIS 4980
CourtAppellate Division of the Supreme Court of the State of New York
DecidedApril 29, 1998
StatusPublished
Cited by15 cases

This text of 243 A.D.2d 61 (Bennett Road Sewer Co. v. Town Board of Town of Camillus) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bennett Road Sewer Co. v. Town Board of Town of Camillus, 243 A.D.2d 61, 672 N.Y.S.2d 587, 1998 N.Y. App. Div. LEXIS 4980 (N.Y. Ct. App. 1998).

Opinion

OPINION OF THE COURT

Boehm, J.

Plaintiff is a “sewage-works corporation”, so designated and organized pursuant to article 10 of the Transportation Corporations Law. This action stems from a long-standing dispute over the sewer rates recoverable by plaintiff for the use of its sewer facilities located in Camillus. On June 3, 1968, defendant Town of Camillus (Town) and Fabo S. Casale entered into an agreement providing for the formation of plaintiff corporation, which would construct, service and operate a sewer system in a [63]*63defined area of the Town (franchise area). Plaintiff would be paid maintenance charges and transportation fees to be collected by the Town, a tap-in fee of $360 for each unit connected to the corporation’s sewer lines, and an annual charge (sewer rate) of $75 per unit per year for a period of 30 years from the completion of the system. In accordance with the agreement, Casale incorporated plaintiff and completed a comprehensive plan for the installation of a sewer system within the franchise area. On October 16, 1968, defendant Town Board of the Town of Camillus (Board) by resolution unanimously consented to the incorporation of plaintiff, as required by Transportation Corporations Law § 116, and to the June 3rd agreement.

Plaintiff constructed the sewer system in seven separate sections between 1973 and 1982. In July 1984, the Board adopted a resolution providing that, in accordance with the agreement, it would collect and pay to plaintiff the sewer fees and charges.

On August 3, 1992, plaintiff filed a petition with the Board requesting that the current annual sewer rate be increased from $75 to $427.35 per unit pursuant to Transportation Corporations Law § 121, which provides that sewer rates be “fair, reasonable and adequate”. Plaintiff asserted that the current rate of compensation provided by the agreement was not fair, reasonable or adequate because it was based upon estimates of costs, construction and installation of the sewer facilities applicable in 1968 and did not take inflation into account for the years between 1973 and 1982, when the sewer system was under construction. Plaintiff based the new rate on the cost of construction and installation of the sewer facilities and applied a 6% return on its investment over a 20-year period. Plaintiff further asserted that the current rate was unfair because sewer fees and charges from the unimproved properties in the franchise area should be collected by the Town and, although commercial and industrial users generated more sewage, the Town charged them the same rate charged to single-family residential users. Plaintiff also requested that the Town collect sewer fees and charges from the unimproved properties in the franchise area because the presence of the sewer facilities enhanced the value of those properties.

The Board denied plaintiffs petition for a rate increase on the ground that plaintiff failed to establish that the current rate was not fair, reasonable and adequate. Plaintiff then commenced an action seeking a judgment declaring that it is entitled to the relief requested in the petition. Additionally, plaintiff alleged that two other sewer systems, the Milton Ave[64]*64nue Sewer District Extension and the Westover Sewer District, which was established by the Town, infringed upon its franchise rights and that it is entitled to those tap-in fees and transportation charges. Plaintiff further alleged that “Defendants have not collected [or] paid to [plaintiff] any tap-in or transportation fees for the use of its sewer facilities by the Milton Avenue Sewer District Extension or any of the other Defendants [i.e., Milton Avenue Sewer District, Westover Sewer District, the Town and the Board] for the years [1990-1993]”.

In August 1994, plaintiff presented a second petition for a rate increase. Plaintiff appended to the petition material contained in the 1992 petition as well as additional material, including records of the actual construction costs for sections 1, 2, and 3 of the sewer system, amounting to $123,310.08. In addition, because detailed records of the construction costs for sections 4 through 7 of the sewer system could not be located, plaintiff hired environmental and engineering consultants O’Brien & Gere to review plaintiff’s construction documentation and calculate the cost of sections 4 through 7. O’Brien & Gere calculated the total cost of those sections at $379,319.97. Based upon the foregoing figures, plaintiff alleged that the construction cost of the sewer system was $502,630.05 and that, applying a 6% return on its investment over a 20-year period, the annual sewer rate charge per unit should be increased to $427.35. Plaintiff also sought tap-in fees and transportation charges, increased sewer rates for commercial and industrial users, and application of the same sewer rates charged by the Town in its sewer district to the unimproved parcels of land in the franchise area.

The Board refused to act on plaintiff’s petition, stating as its reason that five years had not elapsed since the first petition was presented in 1992. The Town then commenced an action seeking a judgment declaring that plaintiff’s 1994 petition could not be maintained and that plaintiff had abandoned its sewer system and title thereto had passed to the Town. Plaintiff counterclaimed for a judgment declaring its right to the relief requested in the 1994 petition, and moved to consolidate the two actions and for summary judgment.

Without disposing of those actions, Supreme Court, by consent order dated November 22, 1995, remitted plaintiffs petitions to the Board for a hearing. The consent order directed, inter alia, that the Milton Avenue Sewer District pay plaintiff the $360 tap-in fee as well as annual transportation costs to be [65]*65determined at the hearing. A hearing was held, and after the hearing, the Board denied plaintiffs request for a rate increase “based on failure to prove a case for an increase of the rate”. The Board made no reference to transportation costs.

On May 8, 1996, plaintiff commenced this action seeking a judgment declaring its right to a rate increase, tap-in fees and transportation charges, an increase in the rates charged to commercial and industrial users based upon the waste generated, and application of the same rates charged by the Town in its sewer district to unimproved property in the franchise area. After issue was joined, plaintiff moved to consolidate this action with the two other actions and for summary judgment. Defendants cross-moved to dismiss the present action as time barred. Because issue had been joined, defendants should have moved for summary judgment rather than moving to dismiss plaintiffs action (see, CPLR 3212 [a]). However, we ignore that technical irregularity and treat the motion as one for summary judgment (see, CPLR 2001; see also, Technical Tape v Spray-Tuck, Inc., 146 AD2d 517, 518, lv dismissed 74 NY2d 791).

The court determined that the Board had breached its statutory duty to agree to a fair, reasonable and adequate sewer rate, and that plaintiff had provided adequate documentation to support its request for a rate increase. In addition, the court held that, based upon the agreement and the 1984 resolution authorizing the Town to collect the tap-in fees, plaintiff was entitled to payment of those fees. The court directed the Town to collect and pay to plaintiff a $360 tap-in fee for each unit that had tapped into plaintiff’s facilities.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rimar v. Country Club of Buffalo
2025 NY Slip Op 01455 (Appellate Division of the Supreme Court of New York, 2025)
Matter of McGraw v. Town Bd. of Town of Villenova
2020 NY Slip Op 4644 (Appellate Division of the Supreme Court of New York, 2020)
DOORLEY, SANDRA J. v. DEMARCO, HON. JOHN L.
Appellate Division of the Supreme Court of New York, 2013
Doorley v. DeMarco
106 A.D.3d 27 (Appellate Division of the Supreme Court of New York, 2013)
GRESS, MARLINO v. BROWN, BYRON
Appellate Division of the Supreme Court of New York, 2011
Gress v. Brown
82 A.D.3d 1654 (Appellate Division of the Supreme Court of New York, 2011)
HSBC Guyerzeller Bank AG v. Chascona N.V.
42 A.D.3d 381 (Appellate Division of the Supreme Court of New York, 2007)
Foley v. Masiello
38 A.D.3d 1201 (Appellate Division of the Supreme Court of New York, 2007)
Koehnlein v. Jackson
12 A.D.3d 1185 (Appellate Division of the Supreme Court of New York, 2004)
Trager v. Town of Clifton Park
303 A.D.2d 875 (Appellate Division of the Supreme Court of New York, 2003)
Town of Webster v. Village of Webster
280 A.D.2d 931 (Appellate Division of the Supreme Court of New York, 2001)
Joy Builders, Inc. v. Town of Clarkstown
279 A.D.2d 553 (Appellate Division of the Supreme Court of New York, 2001)
Bennett Road Sewer Co. v. Town Board of Camillus
273 A.D.2d 902 (Appellate Division of the Supreme Court of New York, 2000)
Huff v. C. K. Sanitary Systems, Inc.
260 A.D.2d 892 (Appellate Division of the Supreme Court of New York, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
243 A.D.2d 61, 672 N.Y.S.2d 587, 1998 N.Y. App. Div. LEXIS 4980, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bennett-road-sewer-co-v-town-board-of-town-of-camillus-nyappdiv-1998.