Benjamin R. Harvey Co. v. Board of Education

817 A.2d 1023, 358 N.J. Super. 383, 2002 N.J. Super. LEXIS 530
CourtNew Jersey Superior Court Appellate Division
DecidedNovember 21, 2002
StatusPublished

This text of 817 A.2d 1023 (Benjamin R. Harvey Co. v. Board of Education) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Benjamin R. Harvey Co. v. Board of Education, 817 A.2d 1023, 358 N.J. Super. 383, 2002 N.J. Super. LEXIS 530 (N.J. Ct. App. 2002).

Opinion

LAWSON, A.J.S.C.

This matter comes before the Court on a return date of Plaintiff Benjamin R. Harvey Company, Inc.’s (“Harvey”) Order to Show Cause why the Defendants Board of Education of Spring Lake Heights School District (“Board”) and Wallace Brothers, Inc. (“Wallace”) should not be prohibited from performing a contract awarded to Wallace on October 28, 2002. This Court granted temporary restraints prohibiting immediate performance of the contract on November 6, 2002, and set the matter for oral argument on November 19, 2002. The Court has reviewed the moving papers, entertained oral argument and accordingly makes the following findings of fact and conclusions of law pursuant to R. 1:7-4.

In August 2002, the Board solicited bids for a construction project involving additions and alterations to the Spring Lake Heights Elementary School (“the Project”). The Board invited bidders to submit a single bid for any or all of the seven “prime contracts”, which included 1) General Work, 2) Structural Steel and Ornamental Iron Work, 3) Heating and Ventilating Systems and Equipment, 4) Electrical Work, 5) Plumbing and Gas Fitting Work, 6) Case Work Equipment, and 7) Kitchen Equipment. Relevant to the complaint filed herein, one of the supplementary conditions set forth at Section 5.2.5 mandates that bidders for any of the seven prime contracts perform a minimum of thirty-five percent of the work with their own forces. Section 5.2.5 then allows for a relaxation of this requirement by specifying a procedure whereby a written request must be submitted with the bid:

A Contractor may request to have the percentage of work that has to be self-performed lowered. Such request must be in writing, submitted with the original Bid and must clearly delineate and specify exactly what work is to be seifperformed and what work will be performed by subcontractors.

Section 5.2.5 also states that “[t]he Owner may at its sole and unfettered discretion reduce the required percentage. No reduction in the percentage will be approved by the Owner unless it is in the best interest of the Owner.”

[387]*387In order to verily compliance with Section 5.2.5, the bid documents also contained Bid Form Attachment #5 (“Attachment # 5”), which required bidders to identify and allocate a dollar amount to each specific item of self-performed work. The bid documents also reserved to the Board discretionary power to waive any informalities in the bids, although bidders were advised that “under no circumstances will the Owner waive any informalities which would give one Bidder substantial advantage or benefit not enjoyed by all Bidders.”

When bids opened on October 10, 2002, Harvey and Wallace submitted bids on the General Work contract. Wallace’s bid of $3,537,960.00 was $192,040.00 lower than Harvey’s bid of $3,730,000.00 The total value of work which Harvey identified as self-performed was $1,534,000.00, or forty-one percent of its total bid. Wallace, however, identified one hundred percent of its total bid as being self-performed. Harvey avers that Wallace’s submission was non-responsive because Wallace could not, in fact, perform one hundred percent of the work.

Subsequent to the bid opening, on October 11, 2002, Harvey challenged Wallace’s bid on the grounds that Wallace improperly completed Attachment # 5 and submitted conflicting prices for the Terrazzo tile work. Prior to the award of the contract, however, Wallace cured the irregularity in Attachment # 5 by submitting a revised document at the request of the project architect. After reviewing Harvey’s claims and Wallace’s bid submission, the project architect recommended on October 24, 2002 that Wallace’s bid be accepted and that Wallace be awarded the general contracting portion of the Project. By way of a resolution dated October 28, 2002, the Board accepted the architect’s recommendation and awarded the contract to Wallace.

Harvey now challenges the Board’s award on grounds that Wallace submitted a materially deficient bid. Harvey maintains that it was the lowest responsive and responsible bidder and is therefore entitled to the award.

[388]*388The purpose of competitive bidding for local public contracts is not protection of individual interests of bidders, but rather advancement of public interest in securing the most economical result by inviting competition in which all bidders are placed on equal basis. See Township of River Vale v. R.J. Longo Construction Co., 127 N.J.Super. 207, 316 A.2d 787 (Law Div. 1974). Courts have consistently held that the purpose of the competitive bidding process is to secure the most economical result in the expenditure of public moneys by promoting uninhibited competition and guarding against “favoritism, improvidence, extravagance and corruption.” Township of Hillside v. Stemin, 25 N.J. 317, 136 A.2d 265 (1957); see also L. Pucillo & Sons, Inc. v. Mayor of New Milford, 73 N.J. 349, 375 A.2d 602 (1977). Accordingly, statutes authorizing competitive bidding demand that publicly advertised contracts be awarded to the “lowest responsible bidder.”

Although case law reveals that strict compliance with public-bidding guidelines is required, see, e.g., Pucillo, supra, at 349, 375 A.2d 602 (“[w]e are not, however, willing to transform the mandatory requirement in these specifications into a polite request.”), competitive bidding provisions should not be construed in such a way as to thwart the primary purpose of achieving economy. Tec Electric, Inc. v. Franklin Lakes Board of Education, 284 N.J.Super. 480, 484, 665 A.2d 803 (Law Div.1995). As such, material conditions contained in bidding specifications may not be waived, while immaterial deficiencies may be waived. See Meadowbrook Carting Co. v. Island Heights Borough, 138 N.J. 307, 314, 650 A.2d 748 (1994)(holding that the inclusion of a consent of surety is a material condition precedent to a responsive bid). The Public School Contracts Law reflects this precedent, mandating:

Where there have been developments subsequent to the qualification and classification of a bidder which in the opinion of the board of education would affect the responsibility of the bidder, information to that effect shall forthwith be transmitted to the department for its review and reconsideration of the classification. Before taking final action on any such bid, the board of education concerned shall notify the bidder and give him an opportunity to present to the department any [389]*389additional information which might tend to substantiate the existing classification.
[N.J.S.A 18A:18A-31.]

The question thus presents itself: Did Wallace’s bid, pledging that it would perform one hundred percent of the work with its own forces, rise to the level of a material deficiency for which waiver may not be granted?

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prismatic Dev. v. Somerset County
564 A.2d 1208 (New Jersey Superior Court App Division, 1989)
Terminal Construction Corp. v. Atlantic County Sewerage Authority
341 A.2d 327 (Supreme Court of New Jersey, 1975)
Meadowbrook Carting Co. v. Borough of Island Heights
650 A.2d 748 (Supreme Court of New Jersey, 1994)
Pucillo v. Mayor and Council of Borough of New Milford
375 A.2d 602 (Supreme Court of New Jersey, 1977)
Tp. of River Vale v. RJ Longo Const. Co.
316 A.2d 737 (New Jersey Superior Court App Division, 1974)
Township of Hillside v. Sternin
136 A.2d 265 (Supreme Court of New Jersey, 1957)
Waterbury Hosp. v. Comm on Hospitals Health Care
316 A.2d 787 (Connecticut Superior Court, 1974)
Schlumberger Industries, Inc. v. Borough of Avalon
599 A.2d 589 (New Jersey Superior Court App Division, 1991)
Tec Electric, Inc. v. Franklin Lakes Board of Education
665 A.2d 803 (New Jersey Superior Court App Division, 1995)
Gaglioti Contracting, Inc. v. City of Hoboken
704 A.2d 1301 (New Jersey Superior Court App Division, 1997)
Iager v. Rogers
341 A.2d 827 (Court of Special Appeals of Maryland, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
817 A.2d 1023, 358 N.J. Super. 383, 2002 N.J. Super. LEXIS 530, Counsel Stack Legal Research, https://law.counselstack.com/opinion/benjamin-r-harvey-co-v-board-of-education-njsuperctappdiv-2002.