Benge General Contracting, LLC and James Benge v. Hertz Electric, LLC and HTJ Global Electric, LLC

Court of Appeals of Texas·Decided September 7, 2021·No. 05-19-01506-CV·Published

Opinion

Reversed and Rendered in part, Affirmed in part, and Opinion Filed September 7, 2021

S In The

Court of Appeals

Fifth District of Texas at Dallas No. 05-19-01506-CV

BENGE GENERAL CONTRACTING, LLC AND JAMES BENGE, Appellants

V.

HERTZ ELECTRIC, LLC AND HTJ GLOBAL ELECTRIC, LLC, Appellees

On Appeal from the 160th Judicial District Court Dallas County, Texas

Trial Court Cause No. DC-16-03630

MEMORANDUM OPINION

Before Chief Justice Burns, Justice Partida-Kipness, and Justice Garcia Opinion by Justice Partida-Kipness Appellants appeal an adverse judgment on claims and counterclaims arising

from commercial services contracts. In five issues, appellants contend the trial court erred in awarding attorney’s fees, allowing a trial amendment of appellees’ counterclaims, awarding both contract and tort damages, granting summary judgment on appellants’ implied-warranty claim, and granting directed verdict on appellants’ breach-of-contract claim. We reverse the trial court’s judgment regarding attorney’s fees and affirm the remainder of the trial court’s judgment.

BACKGROUND

Appellant Benge General Contracting, LLC (BGC) hired appellees Hertz Electrical, LLC (Hertz) and HTJ Global Electric, LLC (HTJ) to perform electrical work on several commercial sites in North Texas. Appellees submitted single-page bids containing a bullet list of included and excluded tasks or items for each site. When identifying some of the included tasks or items, the bids refer to “plans” and, in one case, “specs.” BGC’s owner James Benge approved the proposals and stamped BGC’s terms of acceptance on the documents. The stamped terms state, among other things:

Acceptance of your bid/proposal and beginning work constitutes a binding contract. All work is to be completed with quality and in a reasonable time. Benge General Contracting reserves the right to adjust the schedule accordingly.

Two of the contracts also include a stamp, stating:

BEGINNING WORK WITH THIS RELEASE, YOU CONFIRM YOU ARE ADHERING TO THE PLANS AND SPECIFICATIONS. ANY DEVIATIONS MUST BE APPROVED IN WRITING. YOU ALSO CONFIRM THAT ALL CHANGE ORDERS MUST BE SIGNED BY A PROJECT MANAGER OR THE DIRECTOR OF OPERATIONS.

SUPERINTENDENTS AND CUSTOMERS ARE NOT AUTHORIZED TO MAKE CHANGES TO THE PLANS THAT RESULT IN FINANCIAL INCREASES.

Appellees began working on each site between August and November of 2015. Appellees completed all work they understood was required under the contracts. The record reflects that where city inspection was required, appellees’

work received a “green tag,” indicating the work passed inspection. Benge partially paid appellees for their services.

BGC contends, however, that it later learned that appellees had failed to perform the work competently. After hiring other electrical contractors to repair appellees’ allegedly shoddy work, BGC filed suit against appellees on March 29, 2016. BGC alleged that appellees “failed to perform their duties in a good and workmanlike manner” and brought claims for breach of contract, money had and received, and unjust enrichment. BGC also sought attorney’s fees. BGC filed an amended petition adding an allegation that Hertz and HTJ were merely alter egos for their owner, Joel Dennie.

Appellees answered and filed counterclaims. Appellees specifically alleged that BGC failed to pay all that was owed to appellees and their subcontractors and suppliers. Appellees further alleged that BGC had attempted to harm appellees’ business relationships by making allegedly false and disparaging remarks regarding Dennie to appellees’ existing and potential clients. Thus, appellees brought counterclaims for breach of contract and business disparagement. Appellees also alleged that BGC committed fraud when Benge forged Dennie’s signature on an Unconditional Final Waiver of Lien associated with one of the contracts. Appellees sought to make Benge liable for the fraudulent act by alleging that BGC was merely Benge’s alter ego. Appellees also sought attorney’s fees.

Appellees moved for no-evidence and traditional summary judgment on all of BGC’s claims. Appellees also moved for leave to add Benge as a party to the lawsuit. Appellees based their motion for leave on the deposition testimony of Joshua McDowell, BGC’s former Director of Operations, in which McDowell described conduct by Benge that supported appellees’ alter-ego claim. The trial court granted appellees’ summary judgment motion in part, dismissing BGC’s claims against Dennie and BGC’s claims for money had and received and unjust enrichment against Hertz and HTJ. The trial court denied appellees’ motion as to BGC’s breach-of- contract claim and attorney’s fees. The trial court also granted appellees’ motion for leave to add Benge as a party. Appellees filed amended counterclaims to include Benge as a third-party defendant.

BGC filed a third amended petition, modifying its breach-of-contract claim and adding claims for breach of implied warranty and fraud. As to its breach-of- contract claim, BGC alleged that appellees “failed to perform most of the agreed items, failed to perform others correctly, and did not perform any work timely.” The newly asserted claim for breach of implied warranty contained allegations previously stated in support of BGC’s breach-of-contract claim. Namely, BGC alleged that appellees failed to perform their services “in a good and workmanlike manner.” BGC alleged in its fraud claim that appellees fraudulently misrepresented that they had paid subcontractors and suppliers and that they were capable of completing the contracted work “timely and in a good and workmanlike manner.”

Appellees moved for no-evidence summary judgment on BGC’s newly asserted claims. Regarding BGC’s implied-warranty claim, Appellees argued that BGC had no evidence that it had no other remedy available or that appellees failed to perform the contracted services. Appellees also argued that BGC had no evidence of any element of its fraud claim. BGC filed a response, asserting that appellees had improperly added an element to the implied-warranty claim. Specifically, BGC argued that it did not need to prove it had no other remedy to prevail on this claim. BGC then cited 344 pages of documents, including Benge’s affidavit, as evidence that appellees failed to perform in a good and workmanlike manner. The trial court granted appellees’ motion and dismissed BGC’s implied-warranty and fraud claims.

The parties proceeded to trial on BGC’s claims for breach of contract and attorney’s fees and appellees’ counterclaims for breach of contract, fraud, alter ego, business disparagement, and attorney’s fees. At the close of BGC’s evidence, appellees moved for a directed verdict on BGC’s breach-of-contract claim. The trial court granted appellees’ motion.

At the close of appellee’s evidence, BGC moved for a directed verdict on appellees’ fraud claim on the ground that it was not “a broad form of fraud.” According to BGC, there was no evidence of conspiracy between Benge and BGC to forge Dennie’s signature on a lien waiver. BGC also asserted that there was no evidence that Benge communicated with McDowell with intent to harm appellees’ business relationships or that Benge used BGC as an alter ego to protect himself

from fraudulent activities. BGC asserted that Benge’s communications with McDowell concerned use of “money from these jobs to pay for [Benge’s] wife’s vacations and things like that; however there was no evidence to tie any of those alleged very general allegations to any damage to Mr. Dennie.”

Free access — add to your briefcase to read the full text and ask questions with AI

Benge General Contracting, LLC and James Benge v. Hertz Electric, LLC and HTJ Global Electric, LLC, (Tex. Ct. App. 2021).

Benge General Contracting, LLC and James Benge v. Hertz Electric, LLC and HTJ Global Electric, LLC (Benge General Contracting, LLC and James Benge v. Hertz Electric, LLC and HTJ Global Electric, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re Bank One, N.A.
216 S.W.3d 825 (Texas Supreme Court, 2007)
Hamilton v. Wilson
249 S.W.3d 425 (Texas Supreme Court, 2008)
Timpte Industries, Inc. v. Gish
286 S.W.3d 306 (Texas Supreme Court, 2009)
Epps v. Fowler
351 S.W.3d 862 (Texas Supreme Court, 2011)
Crown Life Insurance Company v. Casteel
22 S.W.3d 378 (Texas Supreme Court, 2000)
Allan v. Nersesova
307 S.W.3d 564 (Court of Appeals of Texas, 2010)
Stephenson v. LeBoeuf
16 S.W.3d 829 (Court of Appeals of Texas, 2000)
Halmos v. Bombardier Aerospace Corp.
314 S.W.3d 606 (Court of Appeals of Texas, 2010)
Jim Walter Homes, Inc. v. Reed
711 S.W.2d 617 (Texas Supreme Court, 1986)
Greenhalgh v. Service Lloyds Insurance Co.
787 S.W.2d 938 (Texas Supreme Court, 1990)
Stewart Title Guaranty Co. v. Sterling
822 S.W.2d 1 (Texas Supreme Court, 1992)
Crawford v. Ace Sign, Inc.
917 S.W.2d 12 (Texas Supreme Court, 1996)
Melody Home Manufacturing Co. v. Barnes
741 S.W.2d 349 (Texas Supreme Court, 1987)
Trans-Gulf Corp. v. Performance Aircraft Services, Inc.
82 S.W.3d 691 (Court of Appeals of Texas, 2002)
Exxon Corp. v. Breezevale Ltd.
82 S.W.3d 429 (Court of Appeals of Texas, 2002)
Waite Hill Services, Inc. v. World Class Metal Works, Inc.
959 S.W.2d 182 (Texas Supreme Court, 1998)
Coastal Transport Co. v. Crown Central Petroleum Corp.
136 S.W.3d 227 (Texas Supreme Court, 2004)