Benes v. Hickox Bldg. Co.

89 N.E.2d 315, 55 Ohio Law. Abs. 289, 1949 Ohio App. LEXIS 821
CourtOhio Court of Appeals
DecidedOctober 17, 1949
DocketNo. 21340
StatusPublished
Cited by3 cases

This text of 89 N.E.2d 315 (Benes v. Hickox Bldg. Co.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Benes v. Hickox Bldg. Co., 89 N.E.2d 315, 55 Ohio Law. Abs. 289, 1949 Ohio App. LEXIS 821 (Ohio Ct. App. 1949).

Opinions

[290]*290OPINION

By McNAMEE, J:

The parties will be referred to as they appeared in the common pleas court.

This is an appeal on questions of law from a judgment of the common pleas court in favor of the defendant, entered at the close of plaintiff’s evidence._ Six assignments of error have been filed but a determination of the principal issue, whether the trial court erred in holding that plaintiff failed to establish a prima facie case for damages for breach of contract, will be dispositive of this appeal.

Plaintiff’s suit is for loss of profits claimed to have been occasioned by the defendant’s alleged wrongful repudiation of a building contract after the plaintiff had commenced work thereunder. The facts essential to an understanding of the decision herein reached, are:

Plaintiff is a building contractor; defendant is the owner of premises located at the northwest corner of Euclid Avenue and East Ninth Street in the City of Cleveland upon which formerly was situated the Hickox Building. At the time the contract between plaintiff and defendant was executed, and pursuant to the terms of a long term lease between the defendant as lessor and Bond Stores Inc., (hereinafter referred to as “Bond”) as lessee, the Hickox Building was being razed to permit the construction of a commercial building specially adapted for the use and occupancy of Bond. By the terms of the lease the defendant and Bond each were to bear a portion of the cost of the construction of the new building. On March 22, 1946, plaintiff and defendant entered into a written contract for the construction of the commercial building in question. The contract which was prepared and drafted by defendant, provides that plaintiff as contractor “shall furnish all necessary labor and materials required to perform and shall perform all of the work shown on the drawings entitled ‘Building for Bond Stores, Inc., Euclid Avenue and East 9th Street, Cleveland, Ohio’ (except such portions of the work as arc specifically excepted from the scope of this contract by the provisions of Section 1 of Article I thereof) as prepared by Walker & Weeks, Architects, hereinafter called the ‘Architect’ whose address is 1240 Huron E.oad, Cleveland, Ohio.”

[291]*291The items specifically excepted from the scope of the contract are:

1. Plumbing work

2. Heating and Air Conditioning work

3. Electrical work

4. Elevators

5. Pneumatic tube system

6. Sprinkler system

The defendant, however, reserved the right to include any part or all of these excepted items within the scope of the work to be performed by the contractor. It was further provided that in no event was the contract to include:

(a) The demolition of the existing structure known as The Hickox Building

(b) Furnishing of the structural steel

(c) Furnishing and installation of the store fixtures and equipment.

Article II of the Contract under the caption “Commencement of the Work and Time for Completion thereof” provides in part as follows:

“The Contractor shall commence work on the foundations at once and shall proceed with the same as rapidly as permitted by the progress of the work of demolition of the Hickox Building. The Contractor shall commence the balance of the work covered by this Contract forthwith upon the approval of this Contract by Bond, and the deposit with the Disbursing Agent, in accordance with the provisions of Section 3 of Article I of the aforesaid lease, of the cost of the new building.

All work covered by this Contract shall be completed by the Contractor within one hundred (100) working days after the first delivery by the Owner to the Contractor of structural steel. * *

The provisions for payment to the Contractor are upon a “cost plus” basis. By the terms of the Contract plaintiff was to receive reimbursement for the funds expended by him for the cost of the work, together with a fee for his services. The governing provisions in respect to the contractor’s compensation read:

“Section 1. The owner shall pay the contractor for the performance of this contract, in current funds as .follows:

[292]*292(a) The cost of the work performed by the contractor hereunder as such cost is defined and restricted by the provisions hereinafter contained in Section 2 of this Article III; and

(b) The Contractor’s fee which shall be Twenty-Five Thousand Dollars ($25,000.00) plus an amount equivalent to Five Percent (5%) of the cost as defined and restricted in Section 2 of this Article III, of such of Items (1) to (8) inclusive, as set forth in Section 1 of Article I hereof, as the Owner, in accordance with the provisions of said Section, causes to be included in the work covered by this Contract; provided, however, in no event shall such additional fee of the Contractor exceed Ten Thousand Dollars ($10,000.00) and provided, further, anything in this Contract to the contrary notwithstanding, if this Contract is not approved by Bond, then the Contractor’s fee shall not exceed Five Percent (5%) of the cost as defined and restricted in Section 2 of this Article of the work performed by the Contractor hereunder.”

At the end of the contract appear the following:

“New York, New York, 1946

The foregoing Contract is hereby approved.

BOND STORES INCORPORATED

By-----------------------”

It does not appear that the contract was approved by Bond.

At the trial, plaintiff introduced the contract in evidence and by his own testimony established that he commenced work on the foundation forthwith. After performing a small part of the foundation work, plaintiff was required to discontinue the same because of danger to workmen, occasioned by the razing of the Hickox Building.

Pursuant to the terms of the contract, plaintiff billed defendant for the cost of the work performed on the foundation, amounting to $161.01 plus five percent or a total of $171.16. This amount was paid by the defendant.

No claim is made that this stoppage of work on the foundation was due to any breach of the contract by plaintiff. Immediately following the suspension of the work on the foundation, plaintiff and the president of the defendant company visited the offices of the Civilian Production Administration where a conference was had in respect of the manner of complying with the regulations of the C. P. A. At that conference, plaintiff was introduced by the president of the defendant company as the “contractor on the job.” Following this .«plaintiff made the necessary calculations and prepara[293]*293tions for a resumption of the work. Plaintiff was at all times ready, willing and able to proceed with the work, but defendant denied him access to the premises and refused to permit plaintiff to proceed with the performance of the contract.

On or about July 15, 1946, defendant entered into another contract with The Higley Construction Company for the constructiion of the same building. The building was completed by Higley at a cost of $909,641.44. The sum of $910,000.00 was deposited with the Disbursing Agent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Aurora v. City of Bay Village
272 N.E.2d 175 (Ohio Court of Appeals, 1971)
Knox v. Knox
59 N.W.2d 108 (Michigan Supreme Court, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
89 N.E.2d 315, 55 Ohio Law. Abs. 289, 1949 Ohio App. LEXIS 821, Counsel Stack Legal Research, https://law.counselstack.com/opinion/benes-v-hickox-bldg-co-ohioctapp-1949.