Beneficial Electric, LLC v. GGA Construction, LLC

CourtSuperior Court of Delaware
DecidedOctober 13, 2025
DocketN23L-11-036 CEB
StatusPublished

This text of Beneficial Electric, LLC v. GGA Construction, LLC (Beneficial Electric, LLC v. GGA Construction, LLC) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beneficial Electric, LLC v. GGA Construction, LLC, (Del. Ct. App. 2025).

Opinion

IN THE SUPERIOR COURT FOR THE STATE OF DELAWARE

BENEFICIAL ELECTRIC, ) LLC, ) ) Plaintiff, ) ) C.A. No. N23L-11-036 CEB v. ) ) GGA CONSTRUCTION, LLC; ) GRAYSON, GRAYSON, & ) ASSOCIATES; LANG ) DEVELOPMENT GROUP, ) LLC; 96 MAIN STREET ) ASSOCIATED, LLC, ) ) Defendant. )

Submitted: September 24, 2025 Decided: October 13, 2025

MEMORANDUM OPINION

Upon Consideration of Defendants’ Motion to Dismiss; GRANTED in part and DENIED in part.

William D. Sullivan, Esq. and Elihu E. Allinson, III, Esq., SULLIVAN HAZELTINE ALLINSON, LLC, Wilmington, Delaware. Attorneys for Plaintiff Beneficial Electric, LLC.

Victoria K. Petrone, Esq., BROCKSTEDT MANDALAS FEDERICO, LLC, Wilmington, Delaware. Attorney for Defendant GGA Construction.

BUTLER, R.J. INTRODUCTION

This dispute concerns a construction project in Newark, Delaware called the

Green Mansion Project. The project included a Hyatt Hotel and the Green Mansion

Apartment Building, dedicated to student housing. The Complaint explains that the

general contractor was GGA Construction, LLC (“GGA”). GGA hired Beneficial

Electric, LLC (“Beneficial”) as the electrical subcontractor – called the “trade

contractor” in the Subcontract Agreement.1 The original amount of the subcontract

was $2,248,215 and it was executed in February 2022. 2 After Beneficial began work

under the subcontract, the parties agreed to expand the scope of work.3 The

subcontract amount increased to $2,767,083.78 as reflected in change orders

prepared by GGA. 4

FACTS

On July 24, 2023, GGA terminated the Subcontract Agreement (the

“Termination Letter”). 5 The Termination Letter stated that Beneficial had made little

to no progress on a list of assignments from GGA for over sixty days and GGA was

1 Compl. at ¶6. 2 Id. 3 Id. at ¶11. 4 Id. 5 Id. at ¶12. 2 therefore exercising its right to terminate the Agreement.6 GGA subsequently hired

another subcontractor to complete the work.

The Complaint asserts that GGA wrongfully terminated the Subcontract

Agreement without providing proper written notice and that Beneficial is entitled to

receive payment of the fair and reasonable value of work performed up to the date

of termination.7 In addition to contract damages, the Complaint seeks a mechanic’s

lien on the property to secure payment.

By the terms of the Subcontract Agreement, GGA paid vendors who supplied

material and equipment for the project. In addition, it paid the “covering”

subcontractor to finish the job. When all told, Beneficial believes it is still owed

$592,425.8

ANALYSIS

1. Provisions of the Subcontract Agreement

A few terms of the Subcontract Agreement concern themselves with

resolution of disputes such as the one before us. First, Article 12.2 says that all

disputes will be subject to mediation “as a condition precedent to further

6 Id. 7 Id. at ¶¶ 13-19. 8 Id. There are five counts in the complaint: a mechanic’s lien, breach of contract, quantum meruit/quantum valebant, unjust enrichment, and a violation of the Building Construction Payments Act. 3 proceedings.”9 Second, when claims are not resolved at mediation, they “shall be

subject to arbitration or litigation at the sole discretion of the Construction

Manager.”10 Although the Construction Manager controls whether the dispute will

be resolved by either arbitration or litigation, the Agreement is silent as to when the

Construction Manager must make that choice. On the other hand, if Beneficial

wishes to invoke the dispute resolution provisions of the contract, it “must

commence mediation or any other proceeding within one (1) year after substantial

performance of this Agreement.”11

Beneficial filed its Complaint in this Court in November, 2023, four months

after being removed from the job by GGA. After the Complaint was filed, the parties

jointly stipulated to conduct mediation in accordance with the Subcontract

Agreement. The Court ordered a stay of the proceedings in February 2024 while

mediation was conducted. 12

Due to scheduling conflicts among the parties, mediation did not begin until

September 2024. Another five months later, the Court received notice from GGA

that mediation had been unsuccessful. GGA filed its Motion to Dismiss shortly

thereafter.13

9 Compl. Ex. A, Article 12.2. 10 Compl. Ex. A, Article 12.3. The “Construction Manager” is GGA. 11 Compl. Ex. A, Article 12.8. 12 Stipulation & Ord. Stay Procs. in Favor of Mediation, D.I. 11. 13 Defs.’ Mot. to Dismiss, D.I. 34 [hereinafter MTD]. The Court received a letter from Plaintiff on May 30, 2025 that “mediation and follow-up exchange . . . has not resolved the case.” 4 2. Arbitration

GGA argues that the Superior Court lacks subject matter jurisdiction as these

claims are subject to arbitration under the Subcontract Agreement.14

It is not disputed that the parties engaged in mediation, a necessary predicate

to any next step in dispute resolution as required by Article 12.2 of the Agreement.

And Beneficial does not dispute that it received an email on January 12, 2024 when

the parties were still planning mediation. In the email, GGA’s counsel states that

“the parties’ contract calls for arbitration. The owner entities will stipulate to

participate in and be bound by arbitration.” 15

Beneficial argues that this email is not a sufficient demand for arbitration.16

It views the email as a mere proposal concerning the next phase of dispute resolution,

and not a demand under the Subcontract Agreement. Beneficial also argues that the

term “owner entities” is not a defined term in the contract and would not include

GGA, which is defined as the Construction Manager in the Agreement.17

Beneficial’s arguments are not convincing. The Agreement does not prescribe

any particular manner or language by which GGA must make its demand. In fact,

the Agreement gives GGA unfettered discretion to decide in what forum to resolve

14 MTD at ¶¶1-3. 15 MTD, Ex. A. 16 Pl.’s Obj. to Def. Mot. to Dismiss, at ¶¶6-7. 17 Id. 5 the dispute. Counsel’s email references the parties’ agreement and expressly agrees

to “participate in and be bound by arbitration.” 18 Nor is the Court persuaded that the

reference to the “owner entities” as the party seeking arbitration and not GGA

dispositive. While using the general contractor’s name and not the owner’s would

have been better form, it is altogether likely that by the time the demand for

arbitration was made, the building had been completed and turned over to the owner,

making the owner the party ultimately liable for any monies owed to Beneficial. If

Beneficial was confused by the change in identity of the opposing party, it never

sought clarification or expressed any doubt that the party withholding funds was the

one that wanted arbitration.

Beneficial’s second argument is that GGA disavowed arbitration and chose

litigation when it signed the joint stipulation to stay proceedings in this Court

pending mediation (“Stipulated”). The Stipulation states that the parties agree to

mediation “before proceeding with litigation” and so Beneficial argues that GGA is

bound to engage in litigation, not arbitration, now that mediation has failed.19

The Stipulation to stay proceedings was a communication between the parties

and the Court, not a contract provision. Terms of a Stipulated Order may be enforced

as Orders of the Court, but they are not the stuff of legal draftsmen working out the

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
Beneficial Electric, LLC v. GGA Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beneficial-electric-llc-v-gga-construction-llc-delsuperct-2025.