Bender v. Rookhuizen

CourtMontana Supreme Court
DecidedJuly 26, 1984
Docket83-290
StatusPublished

This text of Bender v. Rookhuizen (Bender v. Rookhuizen) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bender v. Rookhuizen, (Mo. 1984).

Opinion

No. 83-290 IN THE SUPREME COURT OF THE STATE OF MONTANA 1984

DUANE R. BENDER, d/b/a PALM TREE CONSTRUCTION, Plaintiff and Appellant,

CARL ROOKHUIZEN, et al. Defendants and Respondents.

APPEAL FROM: District Court of the Thirteenth Judicial District, In and for the County of Yellowstone, The Honorable William J. Speare, Judge presiding.

J

COUNSEL OF RECORD: For Appellant:

Hibbs, Sweeney, Colberg, Jensen and Roessles; Morton B. Koessler argued, Billings, Montana

For Respondents : Wright, Tolliver & Guthals; Kenneth D. Tolliver argued, Billings, Montana

Submitted: July 3, 1984 Decided: Jaly 26, 1984

- Clerk Mr. Justice L. C. Gulbrandson delivered the Opinion of the Court.

The plaintiff, Duane R. Bender d/b/a Palm Tree Construction, appeals from a summary judgment entered on April 1, 1983 in the District Court of the Thirteenth Judicial District for the defendants, Carl Rookhuizen d/b/a Rookhuizen Construction, the Housing Authority of Billings, Universal Surety Company and the United States of America. We reverse the judgment of the District Court. In March, 1981, Rookhuizen Construction (Rookhuizen) was awarded the general contract to construct a housing project known as Montana Housing Authority project MT 1-5 for the Housing Authority of Billings (Housing Authority), a public nonprofit Montana corporation. Prior to entering into the general contract with Rookhuizen, the Housing Authority hired E.F. Link & Associates architects, to prepare the necessary plans and specifications for the project. The entire project required and received approval from the Housing and Urban Development (HUD) office of the United States Government. E.F. Link & Associates hired various consultants for different phases of the project including the site preparation and mechanical work. The work of these individual consultants was compiled into a project Specifications Book and corresponding set of drawings. Subsequently, Rookhuizen entered into four subcontracts for completion of various portions of the project including a subcontract entered into on April 22, 1981 with Palm Tree Construction (Palm Tree) for the project's utility work. The terms and conditions of the subcontracts between Rookhuizen and the various subcontractors were set forth in the Specifications Book and corresponding drawings. On August 21, 1981, a dispute arose between the

utility subcontractor, Palm Tree, and Rookhuizen over whose responsibility it was to connect the water and sewer lines

to the individual housing units of the project. Palm Tree claimed the mechanical subcontractor was responsible for making the final connections. Palm Tree based this assertion on its interpretation of the specifications and corresponding drawings. Rookhuizen maintained the contract between the parties required Palm Tree to complete the connections. On the day the dispute arose Rookhuizen made a written demand upon Palm Tree to connect the lines but Palm Tree refused. Thereafter, Larry Marshall, an employee of E.F. Link & 02L WC. ~&~~~~6~9. 2 , , V ; ~ L ~ L Associates and for the project, became aware of the dispute and was asked to render an opinion as to who was responsible for the connections. The record does not indicate which party or parties requested Marshall's opinion. In a letter to Rookhuizen, Marshall expressed the opinion that the mechanical subcontractor, not

Palm Tree, was responsible for the disputed work. Subsequently, Rookhuizen hired another subcontractor

to connect the lines and then set-off that subcontractor's charges against the balance owed Palm Tree under the parties' subcontract. On October 27, 1981, Palm Tree filed a complaint against Rookhuizen, the Housing Authority and Universal Surety Company alleging breach of contract and seeking $17,750.32 the amount Rookhuizen set-off against the balance owed Palm Tree plus certain sums for water expenses and completion of a meter vault lid. In addition to its complaint, Palm Tree filed a mechanic's lien, lis pendens and mechanic's lien forclosure action against the Housing Authority's property. On November 16, 1981, Palm Tree filed an amended complaint naming the United States as an additional defendant. The United States, through HUD, had entered into a trust agreement with the Housing Authority to secure completion of the project and payment on any bonds or notes issued to finance the work. On February 17, 1982, Rookhuizen filed its answer to Palm Tree's amended complaint counterclaiming for damages due to breach of contract and the filing of a wrongful lien. Rookhuizen claimed Palm Tree's refusal to complete the work had caused damages in the amount of $25,000. Thereafter, the parties filed cross motions for summary judgment. On November 23, 1982, the District Court denied Palm Tree's motion for summary judgment and granted Rookhuizen's, reserving the issue of Rookhuizen's liability for Palm Tree's water expenses for trial. In granting Rookhuizen's motion for summary judgment, the District Court concluded that Palm Tree breached its contract with Rookhuizen when it failed to hook up the water and sewer lines; that Palm Tree's lien on the Housing Authority's property was improper; and that Rookhuizen was entitled to attorney's fees. On December 3, 1982, Palm Tree filed a motion to alter and/or amend the District Court's findings of fact and conclusions of law or, in the alternative, a new trial. On January 7, 1983, the District Court clarified its original findings and set the issue of water expenses and Roolthuizen's damages for trial on April 1, 1983. On March 31, 1983, the parties stipulated to an accounting and judgment was entered for Rookhuizen on April 1, 1983, in the amount of $2,555.13. Thereafter, Palm Tree filed its notice of appeal. The plaintiff, Palm Tree raises four issues on appeal: (1) The District Court erred in ruling that the contract between Palm Tree and Rookhuizen imposed a duty on Palm Tree to hookup the water and sewer service lines. (2) The District Court decision of Larry Marshall, the controlling the dispute. (3) The District Court erred in ruling that the mechanic's lien filed by plaintiff was improper. (4) The contract was ambiguous and therefore should have been construed against Rookhuizen. In granting Rookhuizen's notion for summary judgment, the District Court held that Palm Tree was obligated to make the necessary connections of the water and sewer service lines according to two provisions of the general contract that provided: "Article 3. Contract Documents. The Contract shall consist of the following component parts: a. This Instrument b. Bidding Documents c. Conditions d. Technical Specifications e. Drawings f. Supplementary Drawings and Schedules This instrument, together with other documents enumerated in this Article 3, which said documents are as fully a part of the Contract as if hereto attached or herein repeated, form the Contract. - In -----------------y----------------- the event that a n provision of a n y com~onentDart of this contract conflicts

govern, except as otherwise specifically stated. (Emphasis added.)

"13. Specifications and Drawings

"a. Anything mentioned in the Technical Specifications and not shown on the Drawings, or shown on the Drawings and not mentioned in the Technical Specifications, shall be of like effect as if shown on or mentioned in both. In case of difference between Drawings and - Technical Specifications, the Technical Specifications shall govern.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
Bender v. Rookhuizen, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bender-v-rookhuizen-mont-1984.