Bend Tarp and Liner, Inc. v. Bundy

961 P.2d 857, 154 Or. App. 372, 1998 Ore. App. LEXIS 917
CourtCourt of Appeals of Oregon
DecidedJune 10, 1998
Docket95CV-0515-AB; CA A96548
StatusPublished
Cited by9 cases

This text of 961 P.2d 857 (Bend Tarp and Liner, Inc. v. Bundy) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bend Tarp and Liner, Inc. v. Bundy, 961 P.2d 857, 154 Or. App. 372, 1998 Ore. App. LEXIS 917 (Or. Ct. App. 1998).

Opinion

*374 ARMSTRONG, J.

Plaintiff appeals from a judgment that denied its claim to foreclose a construction lien and that awarded defendants damages for breach of contract. We affirm.

Defendants hired plaintiff to install a polyethylene membrane liner in a pond on defendants’ golf course in Bend. The pond was to serve as a source of water to irrigate the course. The purpose of the liner was to prevent the water in the pond from escaping through the soil. Defendants had excavated the pond themselves, leaving a central island green that was surrounded by a retaining wall constructed of railroad ties and boards.

After the pond had been constructed and the liner installed, defendants began to fill the pond. The filling was done overnight, with no one observing the process. The next morning, defendants discovered that, at some point during the filling, a section of the retaining wall had collapsed. At the site of the collapse, the liner was torn and water had escaped through the tear. Although the tear was repaired soon after, water continued to escape from the pond in quantities greater than defendants had expected. Defendants believed that the water loss was attributable to a defectively installed liner, while plaintiff insisted that the collapse of the retaining wall was to blame for the tear in the liner and that any other defects were caused by defendants’ careless treatment of the liner after it had been installed. Defendants refused to pay plaintiff for the liner unless plaintiff repaired it. Plaintiff refused to repair the liner, claiming that defendants had caused the damage that they wanted plaintiff to repair.

After defendants refused to pay, plaintiff filed a construction lien for the amount of the contract plus interest. When defendants still did not pay, plaintiff brought this action to foreclose its lien. In addition to foreclosure, plaintiff sought damages for breach of contract and, in the alternative, recovery in quantum meruit for the work that it had performed on the pond. As an affirmative defense to plaintiffs claims, defendants alleged that plaintiff had breached the parties’ contract and that they had received no benefit from *375 the liner that plaintiff had installed. Defendants also asserted a counterclaim for plaintiffs alleged breach of contract, seeking damages for the cost to replace or repair the liner and for the loss of water attributable to the breach.

After trial, the court found that plaintiff had not allowed enough slack when it installed the liner and that the improper installation had caused the liner to stretch and to pull down the retaining wall to which it had been attached. That, in turn, had led to the large tear at the site of the wall collapse. The court also found that the liner was defective in areas away from the collapsed wall and that those defects were attributable to plaintiff. Accordingly, the court concluded that plaintiff was not entitled to foreclose its construction lien, and it awarded defendants attorney fees for defending against the lien. In addition, the court found for defendants on their counterclaim for breach of contract and awarded them $50,000 in damages.

Plaintiff makes three assignments of error. First, it contends that the court erred when it rejected plaintiffs quantum meruit claim, based on its determination that defendants had not received any benefit from plaintiff’s work. Second, it contends that the court erred when it did not offset the damage award to defendants on their counterclaim by the value of the pond liner. Third, it contends that the trial court erred when it concluded that plaintiff had breached the contract and was, therefore, not entitled to foreclose its construction lien. 1

Plaintiffs first and second assignments of error are, in essence, challenges to the sufficiency of the evidence on which the trial court based its findings on the legal claims. Addressing the quantum meruit claim, plaintiff argues that “uncontroverted evidence established that plaintiff conferred a benefit upon defendants [that] they elected to retain.” *376 Accordingly, plaintiff contends that it is entitled to recover the value of that benefit. The trial court found, however, that defendants had received no benefit from the installation of the liner, because the liner would have to be repaired substantially or replaced before it would perform as desired. The trial court’s refusal to offset defendants’ damages award on the counterclaim by the value of the liner is attributable to that same finding.

The alleged errors about which plaintiff complains were not preserved below. A party that contends that it is entitled to prevail on a claim or issue as a matter of law must ask the trial court to withdraw the claim or issue from the factfinder, whether the case is tried to a jury or to the court. See, e.g., Wilkes v. Zurlinden, 146 Or App 371, 378, 932 P2d 584, vacated on other grounds 325 Or 489, 940 P2d 518 (1997), adhered to on remand 152 Or App 130, 952 P2d 569, rev allowed 327 Or 192 (1998). 2 If, as plaintiff now contends, the uncontroverted evidence establishes that deféndants benefitted from plaintiffs labor and materials, plaintiff should have sought a decision as a matter of law on its right to recover in quantum meruit and to receive an offset on any award of damages to defendants. Plaintiff did not do that. At no time did plaintiff notify the trial court that it was entitled to prevail on those issues as a matter of law. Consequently, we will not disturb the trial court’s rulings on plaintiffs first two assignments of error. 3

*377 Plaintiffs third assignment of error is that the trial court incorrectly interpreted the evidence presented by the parties when it concluded that plaintiff was not entitled to foreclose its construction lien because it had not fulfilled its contractual obligations. In its letter opinion, the court stated:

“The greater weight of the evidence establishes that the liner failed due to being stretched too tightly when water was pumped into the pond, a situation which, according to [plaintiff], is always a consideration in liner installations. The observations of defendants’ witnesses, including Mr. Wick, the photographic evidence, the statements of Mr. [Perlatti] on the day the failure was discovered, the overall condition of the liner and continued serious leakage are persuasive.
“The liner, even after repairs by [defendants], continues to leak at an unacceptable rate. It does not work properly. Plaintiff breached its contract to install the liner. Plaintiff is not entitled to foreclose its lien or recover the contract price.”

Because a claim to foreclose a construction lien is an equitable claim, we review the decision on that claim de novo. ORS 19.415(3).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. M. D. M.
513 P.3d 622 (Court of Appeals of Oregon, 2022)
Ken Hood Construction Co. v. Pacific Coast Construction, Inc.
120 P.3d 6 (Court of Appeals of Oregon, 2005)
Northwest Country Place, Inc. v. NCS Healthcare of Oregon, Inc.
119 P.3d 272 (Court of Appeals of Oregon, 2005)
Stonebrook Hillsboro, L.L.C. v. Flavel
69 P.3d 807 (Court of Appeals of Oregon, 2003)
Peiffer v. Hoyt
63 P.3d 1273 (Court of Appeals of Oregon, 2003)
Resources Northwest, Inc. v. Rau
22 P.3d 1238 (Court of Appeals of Oregon, 2001)
Oldham v. Fanno
7 P.3d 672 (Court of Appeals of Oregon, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
961 P.2d 857, 154 Or. App. 372, 1998 Ore. App. LEXIS 917, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bend-tarp-and-liner-inc-v-bundy-orctapp-1998.