Bench Canal Drainage Dist. v. Maryland Casualty Co.

278 F. 67, 1921 U.S. App. LEXIS 1941
CourtCourt of Appeals for the Eighth Circuit
DecidedDecember 14, 1921
DocketNo. 5862
StatusPublished
Cited by4 cases

This text of 278 F. 67 (Bench Canal Drainage Dist. v. Maryland Casualty Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bench Canal Drainage Dist. v. Maryland Casualty Co., 278 F. 67, 1921 U.S. App. LEXIS 1941 (8th Cir. 1921).

Opinion

YOUMANS, District Judge.

This was a suit by plaintiff in error against the Maryland Casualty Company as surety on a bond executed by the company, to insure the performance on the part of the contractor of a certain contract entered into between the drainage district and one William P. Bullock for the construction by him of certain ditches or drains. The bond recites that a written contract dated June 16, 1916, was entered into between the contractor and the drainage district. A copy of the contract is attached to the bond and made a part of it, [68]*68■as if recited at lergth in the bond. The complaint alleged that Bullock, the contractor, had failed to complete the work stipulated for in. his contract. The condition of the bond is:

“That, if the principal shall indemnify the obligee against any loss or damage directly arising by reason of the failure of the principal to faithfully perform said contract, then this obligation shall be void; otherwise, to remain in full force and effect.”

Then follows this provision:

“Provided, however, that this bond is executed upon the following express conditions, the performance of each of which shall be a condition precedent to any right of recovery hereon, anything in the contract to the contrary notwithstanding.”

The conditions are five in number. The first relates to the right of the surety in the event of default upon the part of the principal to proceed with the performance of the contract. The second relates to the time within which suit shall be brought upon the bond. The third provides that the surety shall not be liable for damages resulting from strikes or from any ac;t of God causing delay. The fourth con-' dition is as follows:

“That tbe obligee shall faithfully perform all the terms, covenants and conditions of such contract on the part of the obligee to be performed, and shall also retain that proportion, if any, which such contract specifies the obligee shall or may retain of the value of all work performed or materials furnished in the prosecution of such contract (not less, however, in any event, than 10 per centum of such value) until the complete performance by the principal’s part to be performed, and until the expiration of the time within which liens or notice of liens may be filed, and until the discharge of suen liens, if any; and the obligee shall at all times observe and conform to the laws relating to liens of the state wherein said contract is to be performed. That the plans and specifications mentioned in said contract are not in any respect defective, and are and at all times will be kept adequate for the complete performance of such contract, and that no change shall be made in such plans and specifications which shall increase the amount to be paid the principal more than 10 per centum of the penalty of this instrument, without the written consent of the surety.”

The fifth condition is as follows:

“That no right of action shall accrue upon or by reason hereof, to or for the use or benefit of any one other than the obligee herein named, and that the obligation of the surety is and shall be construed strictly, as one of suretyship only, shall be executed by the principal before delivery, and shall not, nor shall any interest therein or right of action thereon, be assigned without the prior consent in writing of the surety over the signature of its- president, or one of its vice presidents, attested by its secretary, or one of its assistant secretaries.”

The answer sets up five defenses as follows:

(1) “That the contract referred to in said bond was, by plaintiff and said Bullock, and without the knowledge or consent of defendant, materially and substantially altered in its terms and substance, and thereby abrogated, and said bond and the defendant as surety thereon were thereby released and discharged.”
(2) “That it is expressly provided in said bond, as an express condition thereof, the performance of which, is also by the terms thereof, made a' condition precedent to any right of action on said bond, anything in the con[69]*69tract secured to the contrary notwithstanding, that in tho event of any default on the part of the principal a written statement of the particular facts showing such default, and the date thereof, shall be delivered to the surety by registered mail, at its office in the city of Baltimore, Maryland, promptly, and in any event within 10 days after the obligee or its representative, or the architect, if any, shall learn ol' said default, and defendant further states that it is also provided in said bond that the obligation of said surety is and shall be construed strictly as one of suretyship only, and the defendant now states that plaintiff violated said condition in that it failed, refused, and neglected to so notify the defendant of the default of said Bullock within ten days after discovery of said default by said plaintiff and its representatives, or at any time, or in any manner or form for many days in excess of said 10-day period subsequent to the default of said Bullock; that by reason of the violation of said condition aforesaid this defendant was released from liability thereon and no action can be maintained thereon as against this defendant.”
(3) “That besides providing particularly that tho obligation of the surety named in said bond shall be construed strictly as one of suretyship only, said bond provides by its terms that the said plainliff, obligee named herein, shall faithfully perform all the terms, covenants and conditions of said contract on the part of the obligee to be performed, and that said plaintiff shall and will retain that portion, if any, which said contract specifically provides shall or may be retained by it, of the value of all work performed or material furnished in the performance of said contract, and in any event not less than 10 per cent of such value, until the complete performance by Bullock as principal of all the terms, covenants, and conditions of said contract on said principal’s part to be performed; that by the terms of said bond it is likewise expressly provided that the retention of said 10 per cent, aforesaid is one of the express conditions thereof to liability on the part of said defendant, and a condition precedent to the right of plaintiff to maintain an action on said bond.
“In the contract, Exhibit A aforesaid, which' is attached to and made a part of plaintiff’s petition, it is also provided that, during the progress of the work therein provided for, monthly estimates should be made of the work done and material furnished on the ground by said Bullock, and accepted by the district, and that 10 per cent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
278 F. 67, 1921 U.S. App. LEXIS 1941, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bench-canal-drainage-dist-v-maryland-casualty-co-ca8-1921.