Benavidez Constr. LLC v. Lewicki

CourtNew Mexico Court of Appeals
DecidedApril 10, 2024
StatusUnpublished

This text of Benavidez Constr. LLC v. Lewicki (Benavidez Constr. LLC v. Lewicki) is published on Counsel Stack Legal Research, covering New Mexico Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Benavidez Constr. LLC v. Lewicki, (N.M. Ct. App. 2024).

Opinion

This decision of the New Mexico Court of Appeals was not selected for publication in the New Mexico Appellate Reports. Refer to Rule 12-405 NMRA for restrictions on the citation of unpublished decisions. Electronic decisions may contain computer- generated errors or other deviations from the official version filed by the Court of Appeals.

IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO

No. A-1-CA-40135

BENAVIDEZ CONSTRUCTION LLC,

Plaintiff-Appellee,

v.

PAUL LEWICKI; ELIZABETH PHILLIP; STREAMLAND LLC;

a Delaware limited liability company;

and ROSENALM WILDLIFE INSTITUTE LLC, a Delaware limited liability company,

Defendants-Appellants.

APPEAL FROM THE DISTRICT COURT OF MORA COUNTY Emilio J. Chavez, District Court Judge

Arnold Padilla Albuquerque, NM

for Appellee

Sheri A. Raphaelson Española, NM

for Appellants

MEMORANDUM OPINION

WRAY, Judge.

{1} Defendants Paul Lewicki, Elizabeth Phillip, Streamland LLC, and Rosenalm Wildlife Institute LLC appeal the district court’s judgment in favor of Plaintiff Benavidez Construction LLC, which was owned by Manuel Benavidez. This case involves a contract dispute over payment for the construction and renovation of Defendants’ Paul Lewicki and Elizabeth Phillip’s home. As both parties and the district court acknowledged, no written contract governed the parties’ expectations for the project. Instead, the parties agreed that Defendants hired Plaintiff for “construction and renovation work,” and Defendants paid invoices as Plaintiff submitted them. Disputes arose, however, about payment for “extras”—work Defendants maintained they did not approve in advance. After more than three years, Plaintiff stopped all activity on the property and filed a complaint against Defendants. Following a six-day bench trial, the district court entered judgment in favor of Plaintiff for breach of contract. On appeal, Defendants contend that the damages awarded are unsupported by any enforceable contract. We affirm.

DISCUSSION

{2} Because this is a memorandum opinion prepared solely for the benefit of the parties, we set forth only those facts necessary to our analysis as they become relevant.

{3} Defendants make six specific arguments on appeal. The first four relate to whether the district court improperly decided issues about broad categories of damages and the last two relate more specifically to the damages for particular projects. Before we begin with the four broad damages arguments, we note that in large part, Defendants contend that the district court “made no [c]onclusions of [l]aw, but only [f]indings of [f]act,” and that “[i]t is specifically the glaring absence of [f]indings of the elements of an enforceable contract . . . where the [district c]ourt’s error is contained.” See Rule 1-052(A) NMRA (requiring the district court in nonjury trials to “enter findings of fact and conclusions of law when a party makes a timely request”). Appellate courts, however, “are not bound . . . by the labels attached” by the district court or the parties and whether it is a finding of fact or conclusion of law is “itself a question of law and, therefore, freely reviewable in this [C]ourt.” Edens v. N.M. Health & Soc. Servs. Dep’t, 1976-NMSC-008, ¶ 9, 89 N.M. 60, 547 P.2d 65. We therefore read the district court’s findings of fact as a whole to determine whether taken together, the judgment is justified. See Bachmann v. Regents of Univ. of N.M., 2021-NMCA-050, ¶ 3, 496 P.3d 604; see also In re Hilton’s Est., 1982-NMCA-104, ¶ 17, 98 N.M. 420, 649 P.2d 488 (“Ultimate facts and conclusions of law are often indistinguishable, and their intermixture in the [district] court’s decision as written does not create reversible error where a fair construction of them justifies the court’s judgment.”).

{4} Generally, the district court found that “the parties entered into an agreement regarding the project on [D]efendant[s’] property” but that the agreement did not detail the breadth, scope, and billing for the project. We view this finding as a determination that the breadth, scope, and billing terms of the contract were ambiguous. See Mark V, Inc. v. Mellekas, 1993-NMSC-001, ¶¶ 12-13, 114 N.M. 778, 845 P.2d 1232 (holding that “[a]n ambiguity exists in an agreement when the parties’ expressions of mutual assent lack clarity”). As a result, the district court turned to evidence of the parties’ course of performance to discern the terms of the parties’ agreement. See id. (“Once the agreement is found to be ambiguous, the meaning to be assigned the unclear terms is a question of fact” that “must be resolved by the appropriate fact[-]finder.”); Bachmann, 2021-NMCA-050, ¶ 24 (noting that where a contract is ambiguous, the judge, as “the fact-finder[,] may consider . . . evidence of . . . course of performance of the contract”). This is evident in the following findings.

{5} Plaintiff billed approximately $4.76 million. Defendants contended that they agreed to pay only amounts based on written or express approval and they only approved approximately $2.84 million in bids (or 64 percent of the total amount billed by Plaintiff). Defendants, however, paid approximately $4.46 million (or 94 percent of the amount billed by Plaintiff), and Plaintiff sought the balance of approximately $281,000. 1 From this it is apparent that the district court determined that Defendants by their conduct agreed to pay and did pay far more than the expressly approved bids. See id. (construing the parties’ agreement, “as evidenced by their conduct and practices” to ascertain “their intention and understanding” of the agreement). Defendants do not specifically challenge these findings on appeal. See Roybal v. Chavez Concrete & Excavation Contractors, Inc., 1985-NMCA-020, ¶ 11, 102 N.M. 428, 696 P.2d 1021 (“Unless findings are directly attacked, they are the facts on appeal.”). We therefore consider Defendants’ arguments in this context—an ambiguous agreement that the district court construed in light of the parties’ conduct—to evaluate the evidence supporting the district court’s findings.

I. Defendants’ Broad Damages Arguments

{6} Defendants challenge the district court’s damages determinations regarding (1) amounts related to invoices for “extras,” (2) negotiated reductions for certain invoices, (3) modification of the agreement in order to complete the project, and (4) employment- related taxes on materials. We address each of these arguments in turn.

A. Invoices for Extras

{7} The parties and the district court defined “extras” as “work that did not have a specific bid” and the district court determined that Defendants owed damages for the payment of extras. Defendants broadly contend that the evidence did not support that the invoices for “extras” were enforceable contracts and point to their own evidence for support. As we have explained, the district court’s findings read as a whole indicate that the parties’ agreement was ambiguous and their course of performance supported a conclusion that Defendants agreed to pay more than only approved bids. Additional evidence presented at trial supports this conclusion.

{8} Benavidez and Defendants testified, and Defendants concede on appeal, that Defendants requested changes that were not part of the original plans and were not initially anticipated by the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bishop v. Evangelical Good Samaritan Society
2009 NMSC 036 (New Mexico Supreme Court, 2009)
Roybal v. Chavez Concrete & Excavation Contractors, Inc.
696 P.2d 1021 (New Mexico Court of Appeals, 1985)
Mark V, Inc. v. Mellekas
845 P.2d 1232 (New Mexico Supreme Court, 1993)
Edens v. New Mexico Health & Social Services Department
547 P.2d 65 (New Mexico Supreme Court, 1976)
Matter of Estate of Hilton
649 P.2d 488 (New Mexico Court of Appeals, 1982)
Balboa Const. Co., Inc. v. Golden
639 P.2d 586 (New Mexico Court of Appeals, 1981)
Shaeffer v. Kelton
619 P.2d 1226 (New Mexico Supreme Court, 1980)
Bovee v. State Highway & Transportation Department
2003 NMCA 025 (New Mexico Court of Appeals, 2002)
Valerio v. San Mateo Enterprises, Inc.
2017 NMCA 59 (New Mexico Court of Appeals, 2017)
Bachmann v. Regents of UNM
2021 NMCA 050 (New Mexico Court of Appeals, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Benavidez Constr. LLC v. Lewicki, Counsel Stack Legal Research, https://law.counselstack.com/opinion/benavidez-constr-llc-v-lewicki-nmctapp-2024.