Benard John Horak v. Warren Newman and Ruth Newman

CourtCourt of Appeals of Texas
DecidedJuly 21, 2009
Docket03-05-00170-CV
StatusPublished

This text of Benard John Horak v. Warren Newman and Ruth Newman (Benard John Horak v. Warren Newman and Ruth Newman) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Benard John Horak v. Warren Newman and Ruth Newman, (Tex. Ct. App. 2009).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-05-00170-CV

Bernard John Horak, Appellant

v.

Warren Newman and Ruth Newman, Appellees

FROM THE DISTRICT COURT OF BURNET COUNTY, 33RD JUDICIAL DISTRICT NO. 20,084, HONORABLE GUILFORD L. JONES III, JUDGE PRESIDING

MEMORANDUM OPINION

Bernard John Horak, a self-employed home builder doing business as Horak

Construction (“Horak”), appeals the trial court’s judgment in favor of appellees Warren Newman

and Ruth Newman, concerning Horak’s construction and repair of the Newmans’ residence. In

thirteen points of error, Horak challenges the sufficiency of the evidence to support the Newmans’

claims of breach of contract, breach of warranty, and violations of the Texas Deceptive Trade

Practices-Consumer Protection Act1 and the award of damages. Horak also contends that limitations

barred the Newmans’ claims of breach of contract and DTPA violations. For the reasons that follow,

we affirm the trial court’s judgment.

1 See Tex. Bus. & Com. Code Ann. §§ 17.41-.63 (West 2002 & Supp. 2008) (the “DTPA”). FACTUAL AND PROCEDURAL BACKGROUND

Horak and the Newmans entered into a contract in October 1993 for Horak to

construct the Newmans’ residence from architectural plans that the Newmans submitted to Horak.2

Among the contract’s terms, Horak agreed “to furnish the materials and perform the labor necessary

for the completion of 2800 SQ FT Residence. . . . All material is guaranteed to be as specified, and

the above work to be performed in accordance with the drawings and specifications submitted for

above work and completed in a substantial workmanlike manner for the sum of [ ] $217,700.” One

of the features of the residence was a room off the master suite with a bathtub that had a “glass”

ceiling and a “zero overhang” roofline.3 The architect’s plans and specifications did not provide

“flashing detail”4 for this feature.

The Newmans moved into the residence in October 1994 before Horak had completed

construction. In their first night staying in the residence, an unattached water line flooded the

kitchen, living area, a guest bedroom, and the floor vents for one of the three heating and

air-conditioning (“HVAC”) systems in the residence. Around this time, the Newmans also observed

2 The parties agree that a document titled “PROPOSAL” was the contract between the parties. 3 In his briefing to this Court, Horak describes this room as “a rectangular, predominately glass, enclosure which extends out from the master suite” and the “zero overhang feature” as a design that “is more liable to leak than would a more conventional design.” We refer to the room as the “tub room” as the parties do. 4 According to testimony at trial, flashing is “typically . . . referred to . . . as membranes such as sheet metal flashings that go above windows, door pan flashings that go underneath doors, . . . or any condition that requires a membrane or sheet metal or other type of flashing to insure a water tight product.”

2 that the residence was “sweating.”5 Horak repaired the damage from the flooding, including

replacing tiles in January 1995. At the time the tiles were replaced, standing water was discovered

in the HVAC ducts in the “crawl” space underneath the house. Horak, through his plumbing

subcontractor Wayne’s Air Control, repaired the ducts. They did not replace the ducts but drained

the water by disconnecting the ducts, drying them out, and then reconnecting them.

In January 1995, the Newmans experienced their “first real rain” in the residence and

“sheets of water came into the tub area.”6 Horak undertook repairs to the tub room by replacing

sections of plexiglass roofing panels with “tempered glass.” Horak finished the residence’s

construction and repairs in 1995, and the Newmans were unaware of any further flooding, leaks, or

“sweating” in the residence.

Beginning in 1995, the Newmans hired Wayne’s Air Control to service their HVAC

systems each year. As part of its service in May 1999, a technician from Wayne’s Air Control

discovered mold and mildew in the ducts located underneath the house that had been repaired in

1995. The Newmans hired Wayne’s Air Control to repair and replace the contaminated ducts at a

cost of $2,765.00. Around the same time, the Newmans hired a contractor to do some painting at

their residence, and the contractor discovered “rotting” in the interior of the walls in the tub room.

The Newmans hired Classic Constructors to repair the water damage in the tub room at a cost of

$5,901.71.

5 At trial, Mrs. Newman testified: “In the November/December [1994] time frame the house was sweating, the windows were sweating. You know, they were just covered in condensation.” 6 In his briefing to this Court, Horak states that “[i]n January 1995, after a heavy rain, water was observed leaking in large amounts” into the tub room.

3 Beginning in1999, through counsel, the Newmans provided written notices to Horak

of their claims of defective construction and repair and corresponding injuries concerning the ducts

and the tub room. The parties were unable to resolve the dispute informally, and the Newmans filed

suit in April 2000, alleging claims for breach of contract, breach of warranty, and DTPA violations

arising from Horak’s construction and repairs. The Newmans sought damages, statutory additional

damages, and attorney’s fees.

The case was tried to the court in March 2003. The Newmans’ witnesses included

Mr. Newman; Mrs. Newman; Wayne Roark, the owner of Wayne’s Air Control; Shawn Solsbery,

the owner of Classic Constructors; and the Newmans’ attorney. Mrs. Newman testified to their

agreement with Horak, the construction of the residence, the flooding from the unattached water line

the first night that they stayed in the residence, the “sheets of water” that came into the tub room

when they had their “first real rain,” their belief that the respective repairs had addressed the water

intrusion problems, their subsequent discovery of interior “rotting” in the tub room walls and mold

in the ducts in 1999, and the repairs that were performed in 1999 to address these problems.

Mr. Newman testified to his communications with Horak, including representations that Horak made

after the repairs were completed in 1995 that Horak had “taken care of everything” and the repairs

were complete.7 Roark and Solsbery testified to their respective observations of the residence prior

7 During direct examination, Mr. Newman testified:

Q. And I just want to ask you a few questions. I’m taking you back to January, February 1995 when you closed on your house. Prior to closing, did Mr. Horak ever represent to you that he had repaired the damage from the plumbing defect which pertained to the plumbing and air conditioning system?

4 to undertaking repairs, the repairs that their companies performed, and the costs associated with their

repairs. The Newmans’ attorney testified to their incurred attorney’s fees.

Horak’s witnesses included Horak and Ken Cleveland, a builder in the construction

business. Horak testified to his agreement with the Newmans, the construction of the residence, and

to the repairs that he undertook to the ducts and the tub room in 1995. During cross-examination,

he testified that he did not make a settlement offer to the Newmans in response to their demand

A. Yes. Our main concern was that there had been damage to the system at the time. That was our only concern. And Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MacK Trucks, Inc. v. Tamez
206 S.W.3d 572 (Texas Supreme Court, 2006)
Guevara v. Ferrer
247 S.W.3d 662 (Texas Supreme Court, 2007)
BMC Software Belgium, NV v. Marchand
83 S.W.3d 789 (Texas Supreme Court, 2002)
Morgan v. Compugraphic Corp.
675 S.W.2d 729 (Texas Supreme Court, 1984)
Worford v. Stamper
801 S.W.2d 108 (Texas Supreme Court, 1991)
Holt Atherton Industries, Inc. v. Heine
835 S.W.2d 80 (Texas Supreme Court, 1992)
Perry Homes v. Alwattari
33 S.W.3d 376 (Court of Appeals of Texas, 2001)
Melody Home Manufacturing Co. v. Barnes
741 S.W.2d 349 (Texas Supreme Court, 1987)
Wagner & Brown, Ltd. v. Horwood
58 S.W.3d 732 (Texas Supreme Court, 2001)
Jim Walter Homes, Inc. v. Valencia
690 S.W.2d 239 (Texas Supreme Court, 1985)
Roberson v. Robinson
768 S.W.2d 280 (Texas Supreme Court, 1989)
Randy v. Squires Construction, Inc.
188 S.W.3d 396 (Court of Appeals of Texas, 2006)
Cadle Co. v. Wilson
136 S.W.3d 345 (Court of Appeals of Texas, 2004)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
McGalliard v. Kuhlmann
722 S.W.2d 694 (Texas Supreme Court, 1986)
Carrow v. Bayliner Marine Corp.
781 S.W.2d 691 (Court of Appeals of Texas, 1989)
2 Fat Guys Investment, Inc. v. Klaver
928 S.W.2d 268 (Court of Appeals of Texas, 1996)
Computer Associates International, Inc. v. Altai, Inc.
918 S.W.2d 453 (Texas Supreme Court, 1996)
ST. PAUL SURPLUS LINES INS. CO. INC. v. Dal-Worth Tank Co.
974 S.W.2d 51 (Texas Supreme Court, 1998)
GMC v. Saenz on Behalf of Saenz
873 S.W.2d 353 (Texas Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
Benard John Horak v. Warren Newman and Ruth Newman, Counsel Stack Legal Research, https://law.counselstack.com/opinion/benard-john-horak-v-warren-newman-and-ruth-newman-texapp-2009.