BEN O'CALLAGHAN COMPANY v. Schmincke

376 F. Supp. 1361
CourtDistrict Court, N.D. Georgia
DecidedJune 13, 1974
DocketCiv. A. 18811
StatusPublished
Cited by1 cases

This text of 376 F. Supp. 1361 (BEN O'CALLAGHAN COMPANY v. Schmincke) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BEN O'CALLAGHAN COMPANY v. Schmincke, 376 F. Supp. 1361 (N.D. Ga. 1974).

Opinion

ORDER

EDENFIELD, Chief Judge.

The plaintiff originally filed this suit in the Superior Court of DeKalb County. The complaint seeks a “special in rem judgment” against a stated piece of real property in the amount of $42,117.50 plus interest at 7% per annum from October 30, 1970. The defendants removed the case to federal court. Both parties have moved for summary judgment and the case has been submitted to this court for a ruling on those motions.

In Georgia foreclosure of real property by the holder of a material-man’s lien is essentially a four-step process. The claimant must (1) comply with the terms of his contract, (2) file his claim for record within three months of completion of the work, (3) commence an action for the recovery of his claim within twelve months from the time his claim has become due, 1 and (4) institute a proper suit for foreclosure. 2 Although it is not entirely clear from the complaint, the plaintiff apparently regards this suit as an action to foreclose a materialman’s lien on real property pursuant to Ga.Code Ann. § 67-2301 (1967). 3 In this action no contention has been made that the plaintiff failed to fulfill either of the first two requirements on which foreclosure of a *1363 lien is conditioned. 4 The controversy centers around whether or not the plaintiff complied with the requirement of Ga.Code Ann. § 67-2002, ft 3 (Supp. 1973) that he institute “an action for the recovery of the amount of his claim within 12 months from the time the same shall become due.” This action must be brought against a defendant in direct privity with the plaintiff. 5 This requirement is presumably designed to protect any landowner who is situated as are the defendants in this case. The plaintiff here is a subcontractor who furnished materials and labor used for improvements on real property which the defendants purchased after the improvements had been made and after plaintiff’s lien had been recorded. The statute thus insures that the subcontractor will seek compensation from the general contractor before he will be allowed to foreclose on the owner’s real property. 6 The general contractor is obviously in the best position to know of and assert any good defenses against the materialman (for instance, that the materialman did not comply with the terms of his contract).

On February 3, 1970, the plaintiff filed a suit styled Ben O’Callaghan Co. v. Security Development & Investment Co., Civil Action No. 310,883 (Civil Court of Fulton County, Georgia). It is conceded that Security Development and Investment Company was the general contractor on the construction project in question and that the suit was filed within twelve months of the time plaintiff’s claim became due. The controversy arises from the fact that the suit was upon a note executed by Security Development and Investment Company rather than on the lien and was for the amount of the note rather than for the amount claimed in the lien. The defendant contends that this suit was not sufficient to fulfill the requirements of § 67-2002, jf 3, that as a result the lien has never been properly established under § 67-2002, and that therefore one of the preconditions for foreclosure on the lien under § 67-2301 is lacking. The plaintiff understandably disagrees. For the reasons stated below the court concludes that the defendants’ position is correct.

After extensive research the court has concluded that this precise question has never been decided by the Georgia appellate courts. All of the reported cases appear to be either suits directly on liens or suits on an open account between the subcontractor and the general contractor or owner. One case contains dicta that is in point:

“ . . . The function of a foreclosure suit is not to establish for the first time when and what materials were furnished for a particular job. It is not a suit in personam, when the contractor is not a party and the purpose is merely to absolutely establish a special lien against the property involved, and no general verdict and judgment can be obtained therein against the owner. Ryals v. Smith, 102 Ga. 768, 29 S.E. 968; Langley v. Simmons, 143 Ga. 699, 85 S.E. 832; Griffin Bros. v. Gainesville Iron Works, 144 Ga. 840(1), 88 S.E. 201; Middle Georgia Lumber Co. v. Hunt, 53 Ga.App. 578, 580, 186 S.E. 714. Although the initial suit against the contractor is in personam, the foreclosure suit against the owner is strictly in rem. Buck v. Tifton Mfg. Co., 4 Ga.App. 695, 696, 62 S.E. 107, citing. It is in the antecedent suit against the *1364 contractor that the adjudication is made as to items furnished and the amount due with respect to a particular contract. As to the contractor the obligation is primary; as to the owner it is collateral only and conditioned on the recording by the materialman of a claim of lien within the statutory period.” Chambers Lumber Co. v. Gilmer, 60 Ga.App. 832, 835, 5 S.E.2d 84, 87 (1939) (emphasis added).

Although this language is dicta it seems wholly consistent with the case law in the area and this court is convinced that it indicates the direction the Georgia courts would take if squarely presented with this issue. The question thus becomes whether the prior suit brought by the plaintiff against the general contractor was a sufficient adjudication of the “items furnished and the amount due” under the lien. This court has not been furnished with the entire record in the prior litigation. The complaint and the final judgment in that suit have been filed as exhibits to the defendants’ proposed findings of fact. The complaint is founded entirely upon the personal note and ’makes no mention whatsoever of the lien or of any contractual relationship between plaintiff and defendant. The judgment is for the exact amount of the note plus interest and attorney’s fees. It also allows a set-off for Security Development and Investment Company in the amount of $1,433 for “water treatment system”. The court is not informed what this item represents or whether it has any connection to the current controversy. Thus Ben O’Callaghan Co. v. Security Development & Investment Co., Civil Action No. 310,883 (Civil Court of Fulton County, Georgia) appears to have been a suit in which plaintiff successfully sought judgment on a personal note but it apparently does not constitute a judicial determination of the amount which was owed on the materialman’s account and which therefore formed a potential basis for foreclosure on the property of the defendants in this suit. In the opinion of this court that suit did not constitute “an action for the recovery of [plaintiff’s] claim” within the meaning of Ga. Code Ann. § 67-2002

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lenox Hotel Co. v. Charter Builders, Inc.
717 F. Supp. 1558 (N.D. Georgia, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
376 F. Supp. 1361, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ben-ocallaghan-company-v-schmincke-gand-1974.