Bemas Construction, Inc. v. Dorland (In Re Dorland)

374 B.R. 765, 2007 Bankr. LEXIS 2683, 2007 WL 2309783
CourtUnited States Bankruptcy Court, D. Colorado
DecidedMarch 23, 2007
Docket17-19567
StatusPublished
Cited by8 cases

This text of 374 B.R. 765 (Bemas Construction, Inc. v. Dorland (In Re Dorland)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bemas Construction, Inc. v. Dorland (In Re Dorland), 374 B.R. 765, 2007 Bankr. LEXIS 2683, 2007 WL 2309783 (Colo. 2007).

Opinion

MEMORANDUM OPINION AND ORDER

SIDNEY B. BROOKS, Bankruptcy Judge.

THIS MATTER came before the Court for a trial regarding the Complaint filed by Bemas Construction (“Plaintiff’) against David Allan Dorland, f/o/d/s Ben Do Volt Construction, LLC (“Defendant Dorland”) and Matthew Lloyd Varholdt, f/o/d/s Ben Do Volt Construction, LLC, o/d/s Clear Creek Civil, Inc. (“Defendant Varholdt”) (together Defendant Dorland and Defendant Varholdt shall be referred to as “Defendants”). The trial was conducted on August 11, 2006. The Court, having reviewed the pleading, heard testimony, received exhibits, and reviewed the Court’s file in this matter, makes the following findings of fact, conclusions of law and Order.

I. Summary

This is a case in which the Plaintiff, a creditor and general contractor, seeks a judgment against its former subcontractor, the Defendants/Debtors. Specifically, this matter was brought by a general contractor, Plaintiff against the owners of two companies, Defendant Varholdt and Defendant Dorland, who subcontracted on a con *768 struction project. The Plaintiff is seeking this Court’s determination that the Defendants violated Colo.Rev.Stat. § 38-26-109 (the “Public Works Contractors’ Trust Fund Statute”). The Plaintiff further seeks treble damages against Defendants in accord with the Colorado Criminal Code, Colo.Rev.Stat. § 14-4-401 et seq. (“Colorado Criminal Code”), specifically, Colo.Rev.Stat. § 18^M:05, and a determination that the debts arising therefrom are nondischargeable under 523(a)(4).

For the reasons set forth below, the Court concludes that Defendant Varholdt, only, violated the Public Works Contractors’ Trust Fund Statute. The Court, however, declines to award treble damages under the Public Works Contractors’ Trust Fund Statute. Consequently, judgment shall enter in favor of Plaintiff and against Defendant Varholdt, only, in the amount of $134,287.32, together with post-judgment interest on that amount at the statutory rate of 8% per annum from the date of the judgment until paid. The Court further finds and concludes that the judgment entered herein is nondischargeable under 11 U.S.C. § 523(a)(4).

II. Findings of Fact

The Court makes the following findings of fact based upon those facts stipulated to by the parties and from those matters adduced during the trial of this matter.

A. Background

Plaintiff is involved in the general construction business and entered into a public works contract with CH2MHÍ11 to perform certain work at the Jefferson County Airport (“Project”).

On August 25, 2004, Bemas entered into a subcontract (“Subcontract”) with BenDo-Volt Construction, LLC (“BDV”) for a portion of the work to be performed at the Project. 1

In the fall of 2004, Defendant Varholdt advised Bemas, through Bemas’s project manager, Mike Bussey, that BDV desired to assign the Subcontract to a new company owned and operated by substantially the same owners of BDV. On or about December 13, 2004, Bemas and Clear Creek Civil, Inc. (“Clear Creek”) entered into an Assignment of Standard Subcontract Agreement (“Assignment”) in which Clear Creek, as assignee, accepted all of the terms and conditions of the Subcontract. 2

BDV and Clear Creek were owned and operated by the same individuals. Based on the evidence before the Court, this Court concludes that Defendant Varholdt controlled all financial, administrative and operational decisions involving Clear Creek. 3

All of the work to be completed by Clear Creek, and for which Clear Creek’s suppliers supplied material and equipment, related only to what was known as Schedule I and Schedule II of the Project.

In accordance with the Subcontract as assigned, Bemas paid Clear Creek the sum of $246,895.74 comprised of two checks, one check dated January 28, 2005, in the amount of $80,204.85 and another check dated February 18, 2005, in the amount of $166,690.89. 4

After receiving the payments referenced above, Clear Creek did not pay several of its material and equipment suppliers on the Project, including Carder Concrete Products Co. (“Carder”), Rocky Mountain Ready Mix Company (“Rocky Mountain”), *769 and Power Motive Corporation (“Power Motive”).

Clear Creek failed to complete the work on the Project. Defendant Varholdt testified that Clear Creek could not complete its work because it had run out of money and had no further operating capital. Be-mas, as principal, and Travelers Casualty and Surety Company of America, as compensated surety, provided a payment bond, pursuant to Colo.Rev.Stat. § 38-26-105, for the benefit of unpaid subcontractors, and material and rental equipment suppliers for the Project. 5

On January 31, 2005, Clear Creek deposited a check it received from Bemas, in the amount of $80,204.85 into its account with First Bank. 6 On February 17, 2005, Clear Creek deposited another check it received from Bemas, in the amount of $166,690.89, into its account with First Bank. 7 During the time period from January 28, 2005 through August 3, 2005, Clear Creek made over 200 individual payments to various individuals and entities from the bank account where the Bemas trust funds were deposited. Of the over 200 payments made to various individuals and entities, only one payment was made to Power Motive in the amount of $8,000.00 and only one payment was made to Carder in the amount of $10,069.80. 8

B. Components of Plaintiffs Claim Related to Carder

Carder was a material supplier to Clear Creek on the Project. Carder was not paid by Clear Creek for the materials it supplied on the Project. Carder submitted invoices to Clear Creek, which remained unpaid. 9 Despite demands for payments being made, Clear Creek did not pay and, consequently, Carder informed Bemas of Clear Creek’s failure to pay and provided Bemas with copies of the unpaid invoices. On April 4, 2005, Carder filed a Verified Statement of Claim with Jefferson County, Colorado, in accordance with Colo. Rev.Stat. § 38-26-107, asserting that it was owed $90,196.00. 10

In order to obtain the release of its retainage from Jefferson County and to forestall any claim on the payment bond, Bemas paid Carder $90,196.00. 11 Carder released its Verified Statement of Claim with Jefferson County thereafter. 12

C. Components of Plaintiffs Claim Related to Rocky Mountain

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
374 B.R. 765, 2007 Bankr. LEXIS 2683, 2007 WL 2309783, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bemas-construction-inc-v-dorland-in-re-dorland-cob-2007.