974 So.2d 749 (2007)

BELLSOUTH TELECOMMUNICATIONS, INC.
v.
EUSTIS ENGINEERING CO., INC.

No. 2007-CA-0865.

Court of Appeal of Louisiana, Fourth Circuit.

December 19, 2007.

James F. Perot, Jr., New Orleans, LA, for Plaintiff/Appellee.

Laurence R. DeBuys IV, Robert S. Reich, Reich, Album & Plunkett, L.L.C., Metairie, LA, for Defendant/Appellant.

(Court composed of Judge PATRICIA RIVET MURRAY, Judge MAX N. TOBIAS, JR., Judge DAVID S. GORBATY).

MAX N. TOBIAS, JR., Judge.

The defendant/appellant, Eustis Engineering Company, Inc. ("Eustis"), appeals from a partial summary judgment entered in favor of the plaintiff/appellee, BellSouth Telecommunications, Inc. ("BellSouth"). After reviewing the record and applicable law, we find that genuine issues of material fact exist and, therefore, reverse the judgment and remand the matter to the trial court for further proceedings.

BellSouth filed suit against Eustis and Burkeen Construction Company ("Burkeen"), seeking to recover damages to its underground utility cables located along St. Claude Avenue between the intersections of Elysian Fields Avenue and Frenchmen Street in New Orleans. BellSouth moved for partial summary judgment on the issue of liability contending that because Eustis violated statutory law, it was negligent per se and solely liable for BellSouth's damages. Eustis opposed the *750 motion, arguing that causation was a contested issue of fact and, therefore, summary judgment was inappropriate. On 28 February 2007, the trial court granted the partial summary judgment. In its written reasons for judgment, the trial court stated: "Statutory black letter law was violated and damage ensued when Eustis failed to comply with the applicable statute." The trial court designated the judgment as final pursuant to La. C.C.P.1915 and Eustis brought the instant appeal.

Appellate courts review summary judgments de novo, using the same criteria applied by the trial courts. Stanton v. Tulane University of Louisiana, 00-0403 (La.App. 4 Cir. 01/10/01), 777 So.2d 1242.

In 1988, the Louisiana Underground Utilities and Facilities Damage Prevention Law, La. R.S. 40:1749.11, et seq. ("Damage Prevention Law") was enacted. In particular, La. R.S. 40:1749.13 provides, in pertinent part:

A. Except as provided in this Section, no person shall excavate or demolish in any street, highway, public place or servitude of any operator, or near the location of an underground facility or utility, or on the premises of a customer served by an underground facility or utility without having first ascertained in the manner prescribed in Subsection B of this Section, the specific location as provided in R.S. 40:1749.14(D) of all underground facilities or utilities in the area which would be affected by the proposed excavation or demolition.
B. (1) Except as provided in R.S. 40:1749.15, prior to any excavation or demolition, each excavator or demolisher, including cable television owners or operators, shall serve telephonic notice of the intent to excavate or demolish to the regional notification center or centers serving the area in which the proposed excavation or demolition is to take place. Such notice shall be given to the notification center at least forty-eight hours, but not more than one hundred twenty hours, excluding weekends and holidays, in advance of the commencement of any excavation or demolition activity.

According to this provision, excavators must ascertain the location of underground facilities by calling the notification center, known as "Louisiana One Call," at least forty-eight but not more than 120 hours prior to excavation. Once the call is made to Louisiana One Call, the various utility operators are notified and given a "mark by" date by which the utilities must mark the locations of their underground cables, etc., so the excavator will not damage the underground utilities. The markings are "deemed good as long as visible but not longer than ten calendar days, including weekends and holidays, from the `mark by' time." See La. R.S. 40:1749.14 C(b)(iii).

In the instant case, Chad Held, a project engineer for Eustis, contacted Louisiana One Call on 25 May 2001 to provide notice that it intended to bore soil samples along St. Claude Avenue between the intersections of Elysian Fields Avenue and Frenchmen Street. Louisiana One Call issued a notice of intent to excavate, identified by ticket number 147832, and transmitted the ticket to various utility operators, including BellSouth. The assigned "mark by" date was 29 May 2001 at 3:15 p.m. BellSouth instructed Burkeen, a Bell-South contractor, to mark BellSouth's underground utilities.

Burkeen employee, Charles Hughes, placed orange marks to designate the alleged locations of BellSouth's utilities. According to his deposition testimony and the diagram he drew, Mr. Hughes marked only one telephone line; he allegedly failed to mark a set of copper telephone cables in the area where the soil borings were to be *751 taken. Deposition testimony from BellSouth indicated that there were two sets of lines in the area: copper telephone cables, that were damaged, and fiber optic cables that were not. That testimony further established that Burkeen had access to BellSouth's engineering drawings of utilities at the area where the damage occurred and it was expected to locate both the fiber optic and copper telephone cables.

Within ten days of those marks, Mr. Held placed white marks to indicate safe bore sites along St. Claude Avenue in the areas where no orange utility markings were found. Mr. Held testified in deposition that he did not see any orange marks in the area of the later-damaged cables; however, he did see utility marks in other areas while performing the soil boring project. Eustis personnel returned to the site on 3 July 2001, at which time the excavation that damaged BellSouth's cables and conduit took place.

BellSouth contends that Eustis violated the Damage Prevention Law by failing to begin excavation within 120 hours of notice. In other words, because Mr. Held provided notice to Louisiana One Call on 25 May 2001, actual excavation was required to commence no sooner that 29 May 2001, but no later than 1 June 2001. Actual excavation did not commence until 3 July 2001, more than one month beyond the legal window. In addition, BellSouth argues that Eustis should have provided a second notice to Louisiana One Call because orange markings were not visible to Mr. Held when he visited the site on either 6 June 2001 or 3 July 2001. Because Eustis failed to provide additional notice, BellSouth contends that Eustis is guilty of a second violation of the Damage Prevention Law.

In South Cent., Bell Tel. Co. v. Sewerage and Water Board of New Orleans, 94-1648 (La.App. 4 Cir. 3/16/95), 652 So.2d 1090, this court addressed the Damage Prevention Law when work performed by the defendant damaged the plaintiff's underground cables. In that case, we stated:

In Roberts v. Benoit, 605 So.2d 1032 (La.1991), the Louisiana Supreme Court held that in order to prevail on a negligence claim under La. C.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
974 So. 2d 749, 2007 WL 4632272, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bellsouth-telecom-v-eustis-engineering-lactapp-2007.