Bellevue Farmers Grain Co. v. Fronizer

35 Ohio C.C. Dec. 213, 25 Ohio C.C. (n.s.) 151
Sandusky Circuit Court·Decided April 19, 1912·Published

Opinion

WXLDMAN, J.

The defendants in error sued in the court of common pleas as the surviving members of a partnership which formerly included' said defendants in error and one M. W. Hunt, now deceased. They asked judgment against the plaintiff in error for the balance of a contract price for the construction of a grain elevator, and for certain extras for work and materials rendered and furnished by them in connection with said structure. The elevator was constructed under a written contract and a supplement thereto, the original bearing date of June 1st and the supplement June 23, 1909. The defendant, which was an incorporated association of farmers, filed an answer and cross-petition asserting various matters of defense and counter-claim, and asking affirmative relief in the way of damages.

The essential points of the controversy between the parties may be' succinctly stated as follows:

The plaintiffs assert full performance of the contract on 'their part, and allege $2,994.79 as a balance on the contract price and for said extras. The defendant denies the performance of the contract, alleges numerous defects of construction, and asserts by way of defense as against the claim for extras that no order for said extras in writing was ever made by the defendant, as required by the written contract in the following terms:

“All necessary expenses are provided for by the amount contracted hereby to be paid said party of the first part, so that said amount will cover the entire cost to said party of the second [215] part. No claims for extra work shall be made unless the same be done in pursuance of a written order from said party of the second part and given to said party of the first part prior to the doing of said extra work, or the furnishing of extra materials.”

The principal claims asserted by the defendant by way of counter-claim are upon an alleged warranty, embodied in the written contract, and a stipulation that the entire work of construction should be performed between the date of the contract and,August 31, 1909. As stated in the plaintiff’s petition, the building was not in fact completed and ready for operation before December 6 of that year. The contract contained a provision that for any delay not due to certain specific causes beyond the control of the contractors, after the stipulated date of completion, the defendant company should be entitled to $10 for each day during such delay as liquidated damages. The total amount of damages claimed by the defendant was $4,890, for which the defendant asked judgment.

The ease was tried to a jury and resulted in a verdict for the plaintiff below in the sum of $2,725.95. The record brought up to us is a very long one, embodying about 1,000 pages of evidence in the bill of exceptions, and numerous claims of error are made. It is claimed that the verdict is not sustained by this evidence, but our attention has been called to the fact that although the certificate of the trial judge asserts that the bill contains all the evidence, it lacks a written exhibit which appears to have been offered and received, and for that reason we are not attempting to pass upon the weight of the evidence. It does not appear that this exhibit is not material to such inquiry.

Among the numerous claims of error are a few which seem to demand especial attention by reason of their importance, and the fact that especial emphasis has been placed upon them in argument. I have already referred to the requirement of the contract as to written orders for extras. The plaintiff contends that although no written orders were given, these extras were requested by the defendant and furnished under such circumstances as to evidence an expectation of payment. In view of the evidence bearing upon this point, at its close and before argument, the defendant among other requested instructions [216] asked the court to give to the jury instruction No. 10, which I read:

“You are instructed that in order for the plaintiff to recover for any extras save and excepting those expressly admitted by the defendant in open court, the plaintiffs must show that the condition in the contract providing that 'No claims for extra work shall be made unless the same be done in pursuance of a written order from said party of the second part and given to said party of the first part prior to the doing of said extra work, or the furnishing of extra materials,’ has been waived by the defendant and the plaintiffs must prove the waiver of the condition by such clear and convincing evidence as to leave no reasonable doubt about the waiver.”

This instruction the court refused to give. It is our view that the defendant was clearly entitled to this instruction before argument, and that it should have been given, pursuant to Ashley v. Henahan, 56 Ohio St. 559 [47 N. E. 573], The refusal of the court to give it was reversible error, and was not cured by the giving of a portion of it, in substance, in the general charge. That the action of the court may have resulted in prejudice is indicated by an express special finding of the jury that a part of their verdict to the amount of $316.91 was for extras in excess of such as were admitted by the defendant.

The written contract sued upon contained the following language:

‘ ‘ Said party of the first part shall indemnify and save harmless said party of the second part from all injury and damage by reason of any failure of said steel elevator or equipment thereof to be serviceable for the purposes intended, to-wit, the economical receiving, handling and shipping of grain.”

Free access — add to your briefcase to read the full text and ask questions with AI

Bellevue Farmers Grain Co. v. Fronizer, 35 Ohio C.C. Dec. 213, 25 Ohio C.C. (n.s.) 151 (Ohio Super. Ct. 1912).

35 Ohio C.C. Dec. 213 (Bellevue Farmers Grain Co. v. Fronizer) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.