Bell-Corley Construction, LLC v. Orange State Realty, Inc.

383 S.W.3d 442, 2011 Ark. App. 289
CourtCourt of Appeals of Arkansas
DecidedApril 20, 2011
DocketNo. CA 10-968
StatusPublished

This text of 383 S.W.3d 442 (Bell-Corley Construction, LLC v. Orange State Realty, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bell-Corley Construction, LLC v. Orange State Realty, Inc., 383 S.W.3d 442, 2011 Ark. App. 289 (Ark. Ct. App. 2011).

Opinion

JOHN B. ROBBINS, Judge.

|, The only issue presented in this appeal pertains to attorney’s fees. Appellant Bell-Corley Construction (BCC) argues that the Union County Circuit Court abused its discretion in denying its request for attorney’s fees as the successful party in its lien-foreclosure action against appel-lees Orange State Realty, Inc. and Orange State Realty, LLC (collectively “OSR”).1 We affirm.

|2On January 24, 2006, BCC and OSR executed a contract in which BCC agreed to construct a Walgreen’s store on property owned by OSR. The contract sum to be paid by OSR to BCC upon completion of the project was $1,615,600. The construction contract required the parties to arbitrate any disputes, subject to exceptions not relevant to this case. The contract also provided that if a claim relates to or is the subject of a mechanic’s lien, the party asserting such claim may proceed in accordance with applicable law to comply with the lien notice or filing deadlines prior to resolution of the claim by arbitration.

After BCC completed its construction, a dispute arose between the parties. On May 21, 2007, BCC recorded a mechanic’s lien in circuit court, asserting that OSR owed $407,799.61 for materials and labor provided to OSR by BCC under the contract. Later that day, OSR filed a bond to discharge the lien.

On May 30, 2007, BCC filed a complaint against OSR in circuit court, wherein it alleged that there had been a breach of contract. BCC sought to recover unpaid amounts on the construction contract and to foreclose its lien. OSR answered the complaint on July 18, 2007, and brought a counterclaim for breach of contract and negligence. Among other things, OSR sought damages for BCC’s alleged late completion of the project and faulty workmanship. Pursuant to an agreed order filed on August 22, 2007, the circuit court stayed the action pending arbitration. That order memorialized the parties’ agreement that their contract required arbitration of any dispute arising therefrom.

After a six-day arbitration hearing, the arbitrator awarded BCC $263,721, which included the undisputed retainage amount of $169,834. The arbitrator awarded |sOSR $123,379 on its counterclaim. Due to a clerical error, the award to BCC was subsequently corrected to $254,178. The modified arbitration award was dated October 29, 2008, and as modified, BCC obtained a net arbitration award in the amount of $130,798.

In both the original arbitration award and the modified award, the arbitrator addressed the issue of attorney’s fees. The original arbitration award recites:

BCC recovered 41% of its disputed monetary claim. It has been awarded 3% of its time claim. OSR has been awarded 56% of its counterclaim and has not been awarded specific performance. In these circumstances I cannot say either party was the prevailing party and, therefore, no award of attorney fees or costs is made.

The modified award of the arbitrator referenced a request by BCC for modification or clarification regarding attorney’s fees. In denying BCC’s request for modification of attorney’s fees, the arbitrator wrote:

The denial of an award of attorney fees to Claimant is confirmed. The Arbitrator’s determination that BCC recovered 41% of its “disputed” monetary claim was based on the following calculation:
$396,964.00 - Total Claim
-169,834.00 - Retainage (Undisputed)
$227,130.00 - “Disputed Monetary” Claim

That portion of $227,130.00 awarded Claimant per the Arbitrator Worksheet was $93,887.00. The latter sum is 41% of the “disputed” amount claimed. (I recognize that the Retainage was “disputed” in the sense that it was not paid, and that this arbitration was necessary to recover it. Retainage was never contested, however, and it was not considered in the “prevailing party” determination because, in my respectful opinion, both the equities and the overall outcome of the contested matters were pretty evenly balanced. I do not believe that the law, logic or common sense require me to award an attorney fee solely because one party recovers more money than the other party in the Claim/Counterclaim context. I regret any confusion caused by the lack of clarity in the determination.) It should also be noted that inclusion of Retainage in the calculation would not have affected the decision to deny [4an award of attorney fees. My decision denying attorney fees was the result of a conclusion that Claimant’s actions and failures were to blame for many of the problems besetting this Project.

On April 27, 2009, BCC petitioned the circuit court to confirm the arbitration award, to foreclose its lien, and to award attorney’s fees pursuant to Ark.Code Ann. § 18-44-128 (Repl.2003), which provides:

When any contractor, subcontractor, or material supplier who has filed a lien, as provided for in this chapter, gives notice thereof to the debtor or owner of property which has been subjected to the lien in writing sent by registered or certified mail, and the claim has not been paid within twenty (20) days from the date of the mailing, and if the contractor, subcontractor, or material supplier is required to sue for the enforcement of his or her claim, the court shall allow the successful party in the action a reasonable attorney’s fee in addition to other relief to which he or she may be entitled.

BCC requested $85,834.50 in attorney’s fees as the prevailing party in the action.

The circuit court held two hearings on BCC’s petition. After the first hearing, the circuit court issued an order on August 4, 2009, confirming the arbitrator’s award subject to a remand to the arbitrator on a postarbitration counterclaim by OSR.2 The August 4, 2009, order reserved the issue of attorney’s fees. After the second hearing, the circuit court entered an order on February 19, 2010, confirming the arbitration award but denying BCC’s request for attorney’s fees on the basis that “[t]he arbitrator addressed this issue and it will not be revisited.”

|SBCC now appeals from the circuit court’s February 19, 2010, order, arguing that the circuit court abused its discretion by failing to award attorney’s fees to BCC as the successful party in its lien-foreclosure action. Subsequent to an amendment that did not materially change the statute for purposes of this case, Ark.Code Ann. § 18^4-128 (Supp.2009) now provides:

(a) When any contractor, subcontractor, laborer, or material supplier who has filed a lien, as provided for in this chapter, gives notice thereof to the owner of property by any method permitted under § 18-44-115(f)(3) and the claim has not been paid within twenty (20) days from the date of service of the notice, and if the contractor, subcontractor, laborer, or material supplier is required to sue for the enforcement of his or her claim, the court shall allow the successful contractor, subcontractor, laborer, or material supplier a reasonable attorney’s fee in addition to other relief to which he or she may be entitled.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hart v. McChristian
42 S.W.3d 552 (Supreme Court of Arkansas, 2001)
Ruth R. Remmel Revocable Trust v. Regions Financial Corp.
255 S.W.3d 453 (Supreme Court of Arkansas, 2007)
Jackson v. Sparks Regional Medical Center
294 S.W.3d 1 (Supreme Court of Arkansas, 2009)
RMP RENTALS v. Metroplex, Inc.
146 S.W.3d 861 (Supreme Court of Arkansas, 2004)
Arkansas Department of Parks & Tourism v. Resort Managers, Inc.
743 S.W.2d 389 (Supreme Court of Arkansas, 1988)
Coleman Co. v. International Union
317 P.2d 831 (Supreme Court of Kansas, 1957)
Chrobak v. Edward D. Jones & Co.
878 S.W.2d 760 (Court of Appeals of Arkansas, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
383 S.W.3d 442, 2011 Ark. App. 289, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bell-corley-construction-llc-v-orange-state-realty-inc-arkctapp-2011.