Belfance v. Standard Oil

8 Ohio App. Unrep. 433
CourtOhio Court of Appeals
DecidedDecember 12, 1990
DocketCase No. 14688
StatusPublished

This text of 8 Ohio App. Unrep. 433 (Belfance v. Standard Oil) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Belfance v. Standard Oil, 8 Ohio App. Unrep. 433 (Ohio Ct. App. 1990).

Opinions

REECE, P. J.

Kathryn A. Belfance, bankruptcy trustee for the estate of Eugene Stone Trucking, Inc. (Stone), appeals from the decision of the trial court granting summary judgment to the Standard Oil Company and its successor, BP Oil Company (Standard Oil), on Stone's nine-count complaint.

[434]*434Facts

Eugene Stone, a former employee of Standard Oil, founded Eugene Stone Trucking, Inc in the 1960s. Stone's business essentially consisted of delivery of Standard Oil packaged products to service stations in the northeast quadrant of the United States; Stone supplied tractors and drivers, and Standard Oil supplied trailers.

On December 14, 1981, Stone and Standard Oil entered into two contracts at issue in this appeal: an Ohio Intrastate Transportation Agreement and an Interstate Transportation Agreement (the Agreements). Both contracts provided for an initial term of five years and for annual renewal thereafter, with the following provision:

"This Agreement may be terminated, without cause, either by the carrier or by Sohio at any time during the initial period or thereafter by written notice of termination given by the terminating party to the other party at least thirty (30) days in advance of the effective date of termination, which effective date shall be specified in such notice."

In early 1985, a conflict arose between Wendy L. Hileman, manager of packaged products distribution for Standard Oil, and Daniel S. Schultz, president of Stone, concerning Stone's rates. Stone had requested a rate increase, which Standard Oil rejected, instead suggesting a reduction. Stone eventually agreed to the reduction.

In November 1986, Standard Oil ordered an audit of certain charges being made by Stone. Hileman analyzed the audit and determined that some Stone drivers were submitting excessive billings.

On November 25, 1986, Standard Oil notified Stone by letter of its termination of the Agreements, setting the terminus date at December 26, 1986. Standard Oil did not offer any loads for Stone to haul following the November 25, 1986 termination notice. On July 7, 1987, Stone filed a voluntary petition for bankruptcy under Chapter 7 of the United States Bankruptcy Code. On September 29, 1989, Stone's trustee in bankruptcy filed the complaint hereunder.

In its nine-count complaint, Stone alleged that Standard Oil breached the Agreements, forcing Stone into bankruptcy; that Standard Oil breached the Agreements by failing to exercise good faith in giving Stone adequate notice of its intent to terminate; and that Standard Oil's acts in terminating the Agreements were in bad faith, subjecting Standard Oil to liability in tort. Standard Oil denied each of the essential allegations and on March 30, 1990, moved the' trial court for summary judgment on Stone's complaint. Bath parties fully briefed the issues before the trial court.

The trial court granted Standard Oil's motion for summary judgment by written entry filed June 19, 1990, finding that the Agreements were clear and unambiguous, and that Standard Oil properly terminated the Agreements pursuant to the terms thereof. The court further determined that Standard Oil's alleged lack of good faith and exercise of bad faith was not relevant to its determination, because the contract terms permitted termination "by either party for any reason (or for no reason)!.]"

Stone appeals, asserting two assignments of error. Because the assignments of error are interrelated, and concern the propriety of summary judgment, they are addressed together.

Assignments of Error

"I. The trial court committed error by determining that there is no genuine issue as to any material fact that certain contract terms contained in the Agreements are clear and unambiguous entitling the defendants to judgment as a matter of law.

"II. The court committed error by holding that a contract can be terminated by either party for any reason without inquiry into the motivation for termination."

Trial and appellate courts apply the same standard in reviewing summary judgment. Inferences to be drawn from the underlying facts must be viewed in the light most favorable to the party opposing the motion; if when so viewed reasonable minds can reach but one conclusion, adverse to the party opposing the motion, summary judgment should be rendered. Delker v. Ohio Edision Co. (1989), 47 Ohio App. 3d 1, 2, and Civ. R. 56(C).

Stone first argues that the trial court erred by failing to find the language of the Agreements ambiguous and subject to more than one meaning. Stone claims that a viable interpretation of the Agreement provision at issue is that the thirty day notice may be employed either thirty days prior to the end [435]*435of the initial five year term or each successive one year renewal term. Standard Oil counters that to interpret the provision according to Stone's rationale would render other portions of the provision meaningless, thus thwarting the intent of the parties and violating a fundamental rule of contract construction.

Construction of a written contract is a matter of law to be determined by the courts. Alexander v. Buckeye Pipe Line Co. (1978), 53 Ohio St. 2d 241, paragraph one of the syllabus. Where a contract is clear and unambiguous, its interpretation may properly be subject to summary judgment; if terms cannot be determined from the four corners of the contract, however, interpretation should be left to the trier of facts. Inland Refuse Transfer Co. v. Browning-Ferris Industries of Ohio, Inc. (1984), 15 Ohio St. 3d 321, 322.

The trial court in the matter sub judice determined as a matter of law that the terms of the Agreements were clear and unambiguous. We have reviewed the entire record before us, including the contracts in question, and agree with this decision.

Stone's suggested interpretation of the duration and termination provision in the Agreements runs contrary to the plain meaning of the terms used therein. The Agreements initially provide that each "shall continue in force for an initial period of five (5) years commencing on the date hereof and from year to year thereafter, unless and until terminated as hereinafter provided."

The Agreements contain two separate termination provisions: the thirty day provision at issue here, and a for-cause provision not at issue. The former directly follows that quoted above: "This Agreement may be terminated, without cause, either by the carrier or by Sohio at any time during the initial period or thereafter by written notice of termination given by the terminating party to the other party at least thirty (30) days in advance of the effective date of termination, which effective date shall be specified in such notice." (Emphasis added.)

Stone claims that this should be read as permitting termination of the agreements only at the end of each contract period, requiring a thirty day notice which specifies the termination date as the last day of the current contract period. Such an interpretation ignores some language in the Agreements, and fails to accord plain meaning to the remainder. The provision permits either party to terminate the Agreements "at any time during the initial period or thereafter" by delivering written notice at least thirty days prior to an indicated effective date. "At any time" is not subject to Stone's claim that termination may only occur at the end of each contract period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cloverdale Equipment Company v. Simon Aerials, Inc.
869 F.2d 934 (Sixth Circuit, 1989)
General Aviation, Inc. v. The Cessna Aircraft Co.
915 F.2d 1038 (Sixth Circuit, 1990)
Brown v. Otto C. Epp Memorial Hospital
535 N.E.2d 325 (Ohio Court of Appeals, 1987)
Cavanaugh v. Nationwide Mutual Ins.
416 N.E.2d 1059 (Ohio Court of Appeals, 1976)
Firemen's Insurance Co. of Newark v. Antol
471 N.E.2d 831 (Ohio Court of Appeals, 1984)
Delker v. Ohio Edison Co.
546 N.E.2d 975 (Ohio Court of Appeals, 1989)
Blosser v. Enderlin
148 N.E. 393 (Ohio Supreme Court, 1925)
Ullmann v. May
72 N.E.2d 63 (Ohio Supreme Court, 1947)
Alexander v. Buckeye Pipe Line Co.
374 N.E.2d 146 (Ohio Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
8 Ohio App. Unrep. 433, Counsel Stack Legal Research, https://law.counselstack.com/opinion/belfance-v-standard-oil-ohioctapp-1990.