Belden v. State

38 N.Y. Sup. Ct. 409
CourtNew York Supreme Court
DecidedJanuary 15, 1884
StatusPublished

This text of 38 N.Y. Sup. Ct. 409 (Belden v. State) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Belden v. State, 38 N.Y. Sup. Ct. 409 (N.Y. Super. Ct. 1884).

Opinion

Smith, P. J.:

The claimants established a prima facie right to recover the amounts unpaid for work done and materials furnished under contracts B ” and C ” mentioned in the record book, and they are entitled to judgment for the same unless some defense thereto has been made out. The board of audit found that the amount unpaid on contract “ B ” was $7,491, and on contract “ C,” $9,750.60. In ascertaining the amount unpaid on contract ££B,” the board seem to have adopted the sum shown by the estimate of February, 1875, to have been unpaid on the first day of that month. It appears by uncontradicted evidence, that there was unpaid for work done during that month, and not included in said estimate, the sum of $ 114. That sum should be added to the amount found by the board, making the sum of $7,605 unpaid on contract “ B.” If the claimants are entitled to recover those sums there should be added to them interest from the 1st day of September, 1875.

The board of audit found that the claimants had been overpaid on contract “ A ” in a sum largely exceeding the amounts unpaid on contracts B ” and C,” and -on that ground the entire claim was dismissed. The claimants contend not only that their claims under the last two contracts were improperly denied, but that they were entitled to recover a large sum in addition for work done and materials furnished under contract “ A.”

In respect to the latter contention, it is to be observed that the board found that the several items of work done and materials furnished by the claimants under contract “A,” or in extra work pursuant thereto, amounted, at the prices agreed on therefor in said contract, to only the aggregate sum of $314,960.70, which was less by $102,610.30 than the sum which the claimants admitted they had received from- the State on said contract. If that finding is warranted by the evidence, it defeats the claim to recover under contract “A.”

The principal items embraced in said finding are “ earth ” and £í rock ” excavation, embankment,” vertical wall dry,” and cement,” and hemlock timber.” There are several minor items to which it is not necessary to refer, for the reason that if the finding is sustained as to the larger items above, mentioned, it is sufficient for all the purposes of the defense.

[412]*412The difference in the amount of earth excavation and also of embankment allowed by the board, and that claimed by the appellants, depends to some extent on the interpretation of the contract. The specifications forming part of the contract provide that “ all materials removed as aforesaid ” (excavated) shall be deposited so as to form the necessary banks for the canal, and in such other places as the State engineer shall direct, and when the same are carried over 200 feet parallel with the line of the canal for the purpose of making embankments for the canal, or for the same distances in direct line to form bridge embankments or guard banks (spoil banks not included), the same shall be paid for both as excavation and embankments. No materials embraced under the head of excavation, and paid for as such, will, when deposited in any embankment, be paid for as embankment unless the same has been moved 200 feet in a line parallel with the canal, except as before specified for bridge embankments, and all embankments made from materials not embraced in the excavation will only be paid for as embankment.”

The appellants claimed for 73,460 cubic yards of embankment,- and the board allowed 10,445f yards only. The board found that of the embankment so claimed all but 10,445f yards was composed of materials which had been embraced under the head of excavations and paid for as such, and that none of it had been moved 200 feet in a line parallel with the canal, and none of it was for biidge embankment. This finding appears to be supported by the evidence. But it is claimed by the appellants that the evidence shows also that at the time when the excavation for the wall was made much of the earth excavated was frozen and unfit to be placed at that time in the bank. It was therefore placed in what is known as “ spoil bank,” much of it in the prism of the canal, and when it thawed out it was removed to the side of the canal and there placed as embankment. These latter circumstances are supposed by the appellants to take the case out of the provisions of the contract above quoted, it being contended that those provisions applied only to the excavated earth, which could be immediately placed as embankment, and did not apply to earth which, as in the present instance, was handled twice. ¥e think the interpretation above suggested cannot be maintained. The language of the specifications, bearing upon the question is clear and [413]*413hardly admits of construction. If the necessity of putting the earth in spoil banks arose from the fact of its being frozen when excavated, the parties to the contract must be presumed to have foreseen that contingency, as the contract expressly provided that the work should be conducted in such a manner as not to interfere with or disturb the navigation and use of the canal, and consequently the bulk of the work could only be carried on when the canals were closed by reason of frost and ice. To adopt the interpretation contended for by the claimants would be to alter the contract.

Proof was given as to the custom in such a case. It is very doubtful whether custom could affect the contract made by the parties in that regard, but however that may be, the testimony as to the custom was conflicting, and the conclusion of the board, in that particular, cannot be said to 'be so clearly against the weight of evidence, as that it should be disturbed for that reason.

The difference between the findings of the board and the claims of the contractors as to the amount of enbankment, and of earth and rock excavation, and also of wall and timber, is largely accounted for by the different methods adopted by the witnesses for ascertaining such amounts. "Without going particularly into a description of those methods, in respect to which there is a large mass of testimony, it is enough to say that upon reading it with the aid of the very full and helpful briefs of counsel on each side, we are satisfied that the evidence warrants the conclusion of the board as to the amount of the several principal items of work done and materials furnished above referred to, and that a reversal of their findings in those respects, as being clearly against the weight of evidence, would not be justified.

It does not appear that the board rejected any part of the claim on the ground that it was for work or materials not within the contract, or on the ground that in making the contract the State officers exceeded their authority. They allowed the claimants the prices fixed by the contract for all the items of work done and materials furnished which, in their judgment, were established by a preponderance of evidence; and a complete defense to the claim made under contract “A” (and also to that made under the other contracts, if there is no legal obstacle in the way of extending the defense to [414]*414"those contracts, a point that will be considered presently), consists in the fact that the aggregate sum so found to have been earned by •the claimants under contract “A,” falls short of the payments made to them under said contract in a sum exceeding the amounts unpaid on contracts “ B ” and C.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Glacius v. . Black
50 N.Y. 145 (New York Court of Appeals, 1872)

Cite This Page — Counsel Stack

Bluebook (online)
38 N.Y. Sup. Ct. 409, Counsel Stack Legal Research, https://law.counselstack.com/opinion/belden-v-state-nysupct-1884.