Beiseker v. Moore

174 F. 368, 98 C.C.A. 272, 1909 U.S. App. LEXIS 5194
CourtCourt of Appeals for the Eighth Circuit
DecidedNovember 13, 1909
DocketNo. 2,862
StatusPublished
Cited by8 cases

This text of 174 F. 368 (Beiseker v. Moore) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beiseker v. Moore, 174 F. 368, 98 C.C.A. 272, 1909 U.S. App. LEXIS 5194 (8th Cir. 1909).

Opinions

ADAMS, Circuit Judge

(after stating the facts as above). It was settled by the judgment in the former case as elucidated by the opinion rendered that, by reason of the peculiar facts and circumstances surrounding the parties at the time the contract was made and the action of the parties then and subsequently taken in the way of performance, the limit of 30 days fixed for such performance by the contract was waived.

According to its provisions, which are set forth at length in the former opinion, the defendants were first required to deliver to the purchaser complete abstracts of title to the lands, and the purchaser, after taking 10 days to examine the same, was required to take the next step towards performance by tendering the cash payment which was to be one-third and notes secured by mortgage on the land conveyed for the balance or two-thirds of the purchase price. Acting on the construction of the contract which they had adopted, abstracts were from time to time furnished by the vendors, dissatisfaction of one kind or another was found with them, and corrections were made until the latter part of August, 1902, when satisfactory abstracts of title to 8,829.08 acres were furnished to the purchaser. The parties then agreed to close the deal so far as -these lands were concerned, and proceeded to do so. While arranging to consummate their conveyance, a controversy arose with respect to the time when interest should begin to run on the notes to be given for the deferred portion of the purchase price. The vendors claimed that it should run from December 21,1901, because the contract provided that the notes should each be dated December 21, 1901, and all should draw interest at the rate of six per cent, per annum until paid. The vendee contended that, in view of the waiver of the time limit and the delays in furnishing satisfactory abstracts of title, interest should run only from the time of actual performance, and that the earliest possible date, fixed by the standard he suggested, was September 1, 1902.

Whether it was the fault of the plaintiff or not which occasioned the delay in furnishing the abstracts and whether the defects in them complained of by plaintiff: from time to time were defects in ownership, title or otherwise, within the exact purview of the stipulation of the contract in that regard, or whether the contract was indivisible so as to require a purchase of all the lands described in them, [370]*370if anjr (questions learnedly argued by defendant’s counsel), are quite immaterial in view of the fact that the parties did away with all these questions when they proceeded to the execution of their contract as practically construed by them. As said in the former opinion, they then treated it as.“a recognized, subsisting contract obligatory upon both, whereby the one-third of the purchase money for the acres thus accepted was to be paid and deeds and mortgages exchanged.” Abstracts of title were furnished, and they treated them as delivered to the plaintiff in execution of the contract obligation in that respect, and proceeded to close the deal so far as those lands were concerned. Many of the contentions of defendants’ learned counsel are in manifest disregard of the contemporaneous construction which the parties placed upon the contract, and fall well within the general denunciation of such things expressed by Judge Philips in the opinion in the former case. As the parties brushed many of the questions now minutely argued by defendants’ learned counsel away, so will we; and, as many of those now argued were settled by the former judgment and have become the settled law of the casé, we will come directly to the new things involved in this writ of error about which there was a real controversy.

There do not seem to have been any very serious differences between the parties until September, 1902. The defendants had then furnished, as already stated, satisfactory abstracts of title for 8,829 acres of land, and the parties had agreed to proceed immediately to the execution of their contract so far as those lands were concerned, leaving the balance in abeyance to be dealt with as fast as abstracts of title could be perfected. Between August 29th and September 18th some correspondence and personal interviews were had by the parties concerning the time when interest should begin to run on the deferred payments; but they failed to agree. The plaintiff finally determined that the notes evidencing the deferred payments should bear interest only from the time defendants were ready to, and did, convey the lands to him, and proceeded to act accordingly. He was required to take the next step in the way of performance of the contract in order to put the defendants in default (Michigan Home Colony Co. v. Tabor, 141 Fed. 332, 72 C. C. A. 480), and on September 18th made a tender of the cash payment due on the lands and also of notes bearing interest from September 1, 1902, secured by mortgage to evidence the deferred payments, and demanded a conveyance of legal title by the defendants which was refused. If plaintiff was right in his general contention about interest, the date of September 1st fixed by him from which interest should run is probably as liberal to the defendants as the facts in the case warrant.

It is conceded by the defendants that upon the theory that plaintiff was bound to pay interest only from the 1st of September, 1902, and on the theory that the number of acres tendered for, to wit, 8,829, was correct, a sufficient amount of cash and sufficient notes for the deferred payments were tendered by him.

Four objections, however, are made to the tender: First, that the notes should have borne interest from December 21, 1901, instead [371]*371of September 1, 1902; second, that the tender was insufficient, in that it did not embrace cash or notes for about 136 acres of land which were found on that date not to have been included within the aggregate of 8,829 acres, reported by defendants to be ready for conveyance; third, that plaintiff nullified the tender of performance after it was made by failing to keep it good a reasonable length of time for the defendants to accept; and, fourth that the tender was a conditional one, conditioned upon the sttrrender to the plaintiff of defendants’ claim to interest upon the deferred payments.

We will take up these objections in the order stated; but, before doing so, we should remember that this is not a case of tender to extinguish a debt or stop interest, but is rather an offer of performance by one party to a contract containing mutual and dependent covenants, requisite to put the other party in default.

Were the defendants entitled to the interest demanded? This very question framed in the same words precedes its careful discussion in the former opinion. It was then answered in the negative, and that would seem to be conclusive of the present inquiry. But learned counsel for defendants say it was not conclusive, because, using his own language, “the decision proceeded upon the theory of default of the defendants and not upon any consideration of the contract itself.”

We do not construe the opinion as adjudicating merely that by reason of defendants’ wrongful default in the matter of furnishing abstracts of title interest could not be exacted. That is quite too narrow and constricted a view of the opinion taken as a whole. Whatever was said in the discussion of the subject of interest was said after we had determined the true meaning of the contract not only in the light of its own terms, but in the light of the contemporaneom construction put upon it by the parties themselves.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keeler v. Fred T. Ley & Co.
65 F.2d 499 (First Circuit, 1933)
McKenzie v. Hilleboe
149 N.W. 342 (North Dakota Supreme Court, 1914)
United States v. Hammond
226 F. 849 (N.D. California, 1914)
City of Omaha v. Omaha Water Co.
192 F. 246 (Eighth Circuit, 1911)
St. Louis & S. F. R. Co. v. Cundieff
184 F. 891 (Eighth Circuit, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
174 F. 368, 98 C.C.A. 272, 1909 U.S. App. LEXIS 5194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beiseker-v-moore-ca8-1909.