Beinhauer v. Gleason

15 N.Y. St. Rep. 227
CourtNew York Supreme Court
DecidedMarch 28, 1888
StatusPublished
Cited by2 cases

This text of 15 N.Y. St. Rep. 227 (Beinhauer v. Gleason) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beinhauer v. Gleason, 15 N.Y. St. Rep. 227 (N.Y. Super. Ct. 1888).

Opinion

Daniels, J.

The plaintiff performed work and labor in erecting and finishing a house on the north side of Fifty-eighth street, in the city of New York.. The work was done and the materials for it supplied under a written contract entered into on the 19th of September, 1885, by which it was covenanted that the work should be completed on or before the 1st of March, 1886. It was not completed at that time, but the evidence tended to establish the fact that it was completed by the first of the following month of June. This was denied by the defendant, and evidence on her part was given to establish the fact that it was not completed before the commencement of these proceedings for the enforcement of a lien in the plaintiff’s favor to obtain the payment of his debt, under chapter 342, of the Laws of 1885. His letter of the 10th of June, 1886, contained a statement which on its face appeared to be in conflict with his evidence that his work was completed on the first day of that month. But the explanation given by him of the letter was, that the reference contained in it to unfinished work was not what he had agreed to perform by the contract, but other things which the defendant or her husband, who acted for her in the supervision and direction of the work, desired to have performed. Which side was right was a question that addressed itself to the determination of the court, before which the witnesses were sworn. and examined. And as credit has been given to the plaintiff’s statement in the decision which was made, it must be assumed now that his evidence appeared more reliable as to this fact than the other evidence contained in the case relating to it.

The work to be performed and the material to be supplied by the plaintiff, included carpenters, framers, roofers, tinners, bell hangers, and other works required in the erection and completion ” of the building. But while this clause is broad enough to include all the work required in the erection and completion of the building, it was evidently not the design of the parties that it should be so understood.

[229]*229For the mason work, as well as the painting about the building and the materials required for these divisions of the work, were awarded to and performed by other persons. And it has not been claimed on behalf of the defendant that either or any part of the other work was included in or to be performed by the plaintiff. And for the construction and effect of the agreement, the court is entitled to place itself in the same position as the parties were at the time when it was made, and to give it the understanding and effect which it must have had with them under the other circumstances appearing in the case. The language was loosely used and it tends to characterize the contract as one which was made, without either close attention or accurate discrimination. The amount to be paid to the plaintiff for his labor and material was the sum of $11,500. This was divided into seven payments. Five of them were made without any substantial dissention or disagreement between the parties. And an additional sum of $1,000 was, also, paid, which it was alleged by the plaintiff was part of the $3,000, forming the sixth payment under the agreement. This, however, was denied by the defendant upon her information and belief accompanied with the statement that so much of the sixth payment had been made upon the extra work performed by the plaintiff upon the building. But as the extra work amounted to no more than- the sum of $759.90, this payment could not be exhausted in that manner. But. if it was to include the extra work, concerning which, however, no proof was given, still a portion of the sum would remain to be applied upon and constitute a part of the sixth payment mentioned in this agreement. The court concluded this $1,000 to have been made as a part of the sixth payment mentioned in the agreement. Whether it was right in drawing this conclusion from the case it is not essential to discuss or consider, for the reason .that for" all the practical purposes of the case, the result will be the same whether the entire $1,000 was applied upon and paid as a part of the sixth installment, or only so much of it as remained after paying for the extra work.

Neither the work of the masons nor that of the painters was completed by the 1st of June, 1886, or by the time when this action was commenced, on the twenty-third day of that month. And for that reason it is objected that the residue of this sixth payment, as well as the remaining balance afterwards of $500, had not become due or payable ■ at the time when the suit was commenced.

The objection has been placed upon the language of the contract binding the defendant only to pay the sixth payment “when the building is all completed,“ and the [230]*230balance of $500 “after the expiration of thirty days and when all the drawings and specifications have been returned to the architects. The contract further provided that in each case of the payments a certificate should be obtained from and signed by the architect to the effect that the work had been done in strict accordance with the drawings and specifications, and that he considered the payment properly due. And that a certificate should also be obtained by the contractor from the clerk of the office where liens are recorded, that he had carefully examined the records and found no liens or claims recorded against the work or on account of the contractor. These provisions, like the one already considered, are to be construed under the light afforded by the attendant circumstances and the intent of the parties as that is to be gathered from the language of the agreement. It was made to include the plaintiff’s labor, services and material, and not that of either the masons or the painters. And it is accordingly not reasonable to suppose that the obligation to pay the payment of $3000 was intended to be subordinated in point of time to the final completion of the building by the masons and painters, or other persons who might be employed upon it after the plaintiff had performed his contract. There was no object which could have been subserved by making the obligation to pay the plaintiff for his work and materials dependent upon the performance of the agreement of the other persons, over whom he had no control and with whom he was in no way connected.

And while the language is broad and general, it is not entitled to a construction which would subject him to that degree of delay in obtaining payment for his services and material. The more consistent construction is, and that which probably may safely be inferred to have been within the contemplation of the parties, .that he was to be paid this sum of money when the building was all completed so far as its completion depended upon the performance of his agreement. That is as far as the language under the circumstances in which it was employed can reasonably be extended. And if the plaintiff performed his obligations as they have been defined in the agreement, then upon that performance, he became entitled certainly to the payment of the residue of this sixth payment.

He was not deprived of his right to this money by the circumstances that his work was not finished or completed on or before the 1st of March, 1886, but extended to the 1st of June, three months afterwards. For the delay in this time appears to have been caused by extra work required to be, and which in fact was performed under the authority of the defendant, and by the loss of time in waiting for the [231]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
15 N.Y. St. Rep. 227, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beinhauer-v-gleason-nysupct-1888.