Begl Const. v. La Unified School Dist.

66 Cal. Rptr. 3d 110, 154 Cal. App. 4th 970
CourtCalifornia Court of Appeal
DecidedAugust 29, 2007
DocketB181933
StatusPublished
Cited by1 cases

This text of 66 Cal. Rptr. 3d 110 (Begl Const. v. La Unified School Dist.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Begl Const. v. La Unified School Dist., 66 Cal. Rptr. 3d 110, 154 Cal. App. 4th 970 (Cal. Ct. App. 2007).

Opinion

66 Cal.Rptr.3d 110 (2007)
154 Cal.App.4th 970

BEGL CONSTRUCTION COMPANY, INC., et al., Plaintiffs, Cross-defendants, and Appellants,
v.
LOS ANGELES UNIFIED SCHOOL DISTRICT, Defendant, Cross-complainant and Appellant;
Star Insurance Company, Cross-defendant and Respondent.

No. B181933.

Court of Appeal of California, Second District, Division Four.

August 29, 2007.

Bergman & Dacey, Inc., Gregory M. Bergman, John P. Dacey, and John V. *111 Tamborelli, Los Angeles, for Defendant, Cross-complainant, and Appellant.

Mark E. Baker; Bistline & Cohoon and Ted H. Luymes, Torrance, for Plaintiffs, Cross-defendants, and Appellants.

Mark E. Baker, for Cross-defendant and Respondent.

Certified for Partial Publication.[*]

EPSTEIN, P.J.

This case arises from a public works construction contract entered into by appellant Los Angeles Unified School District (the District) and cross-appellant BEGL Construction Company, Inc. (BEGL).

The District argues the trial court abused its discretion in admitting evidence of BEGL's lost profits due to impaired bonding capacity. In the published portion of this opinion, we reject that argument. In the unpublished portion of this opinion, we consider the District's further contentions that: the court erred in admitting certain expert testimony regarding lost profits, evidence of extra work that was not the subject of written change orders, and testimony regarding damages that were the subject of stop notices; BEGL's claim for earned project costs is not supported by evidence, and is an attempt to recover money already encompassed in BEGL's request for delay damages; the court erred in denying its new trial motion on the False Claims Act cause of action; the court erred in denying its motion to vacate the judgment; the court improperly granted Star Insurance Company's (Star) motion for nonsuit; and it should have been awarded attorney fees under Public Contract Code section 7107. We also consider BEGL's arguments on cross-appeal that: the contractual liquidated damages provision limiting delay damages to $250 per day is unconscionable; the court erred in failing to award sanctions and prejudgment interest; and BEGL should have been awarded attorney fees, costs and penalty interest under Public Contract Code section 7107.

We shall affirm the judgment.

FACTUAL AND PROCEDURAL SUMMARY

In August 2000, the District awarded BEGL a public works construction contract for a seismic retrofit of the Science Building at its Los Angeles Center for Enriched Studies (LACES), and for the demolition and reconstruction of the LACES West Arcade. Because the project was a public work, BEGL was required to post a performance and payment bond. After BEGL started the project, the West Arcade work was removed from the scope of the contract.

The District terminated BEGL in January 2002. It then filed a bond claim with BEGL's surety, Fidelity & Deposit Company of Maryland (Fidelity), for completion of the LACES project. The District and Fidelity entered into a takeover agreement, and Fidelity hired another contractor to finish the project. Fidelity then sued BEGL. That case was later settled.

In April 2003, BEGL filed an action against the District for breach of contract and breach of warranty of plans and specifications. BEGL alleged the District breached the contract between them by: "a. Failing to issue a notice to proceed in a timely manner; [¶] b. Supplying inadequate and faulty plans and specifications; [¶] c. Failing to supply necessary design information in a reasonable and timely manner; [¶] d. Failing to provide sufficient qualified representatives to provide for timely resolution of design and other technical issues; [¶] e. Failing to cooperate with plaintiff to allow for the efficient and timely completion of the project; [f] f. Frustrating, obstructing, hindering and interfering *112 with plaintiffs performance of the project; [¶] g. Demanding that plaintiff perform work which was not an agreed part of plaintiffs scope of work; [¶] h. Failing to disclose pertinent information in defendants' possession and control, when such information was relevant and necessary for the proper and timely completion of the project; [¶] i. Failing to process requests for information and clarification in an efficient and timely manner; [¶] j. Failing to process change order requests in a timely manner[;][¶] k. Failing to grant plaintiff extra time to complete the project due to delays ...; [¶] 1. Failing to pay plaintiff sums due under the contract, extra work and changes; [¶] m. Failing to pay plaintiff sums due for delays, disruptions, and impacts in the work; [¶] n. Failing to pay plaintiff interest and penalties under Public Contract Code section § 7107, and like statutes, for the LAUSD's failure to make payments promptly; and [¶] o. Unlawfully terminating the contract."

In an amended cross-complaint, the District claimed that BEGL had breached the contract: "Within the last four (4) years, [BEGL] breached the Contract with the District by, without limitation, failing to perform work on the Project pursuant to the terms and conditions of the Contract, failing to timely complete its work on the Project, failing to correct defective and/or nonconforming work, failing to perform work per plans and specifications, failing to provide adequate labor and/or supervision, failing to complete the project on time, and failing to develop and maintain an appropriate schedule." The District also alleged that BEGL and its president, Mehr Z. Beglari, violated the False Claims Act. (Gov.Code, §§ 12650-12656.) Finally, the District sought damages from Star, the surety that issued a contractor's license bond to BEGL, for BEGL's alleged violation of the Business and Professions Code.

At the close of evidence, the trial court granted nonsuit on the District's claim against Star. A jury found that both BEGL and the District had breached the contract, and awarded BEGL $954,197 in damages and the District $1 in damages. The jury found that the District did not breach the warranty of plans and specifications. It also found that BEGL and Beglari did not violate the False Claims Act. After several post-trial motions by both parties, the District filed a timely notice of appeal. BEGL filed a timely cross-appeal.

DISCUSSION

I

At trial, BEGL argued that as a result of the District's breach of contract, its bonding capacity was diminished, causing BEGL to lose $506,000 in profits. After beginning the LACES project, which was bonded by Fidelity, BEGL began doing business with a new surety, CNA. BEGL then moved from CNA to INSCO/DICO. In 2002, BEGL's bonding capacity was $3 million to $4 million per job, and $6 million to $7 million aggregate for all work in progress. INSCO/DICO decided to stop bonding BEGL in November 2002 after it learned of the dispute between Fidelity and BEGL regarding the LACES project. BEGL's bonding agent tried to place BEGL with another surety, but he was unsuccessful. Sureties would not bond BEGL because of the current dispute between Fidelity and BEGL. Eventually, BEGL was bonded for $500,000 per job, and $500,000 aggregate.

Consistent with its position before and during trial, the District argues the trial court abused its discretion in admitting evidence of BEGL's lost profits. The District's primary contention is that because it was not foreseeable at the time of contracting *113 that BEGL would lose profits as a result of the District's breach, the damages are improper as a matter of law, and thus the evidence should not have been admitted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. NBC UNIVERSAL
524 F. Supp. 2d 315 (S.D. New York, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
66 Cal. Rptr. 3d 110, 154 Cal. App. 4th 970, Counsel Stack Legal Research, https://law.counselstack.com/opinion/begl-const-v-la-unified-school-dist-calctapp-2007.