Beech Aircraft Corporation v. Ross

155 F.2d 615, 1946 U.S. App. LEXIS 2247
CourtCourt of Appeals for the Tenth Circuit
DecidedMay 20, 1946
Docket3242
StatusPublished
Cited by14 cases

This text of 155 F.2d 615 (Beech Aircraft Corporation v. Ross) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beech Aircraft Corporation v. Ross, 155 F.2d 615, 1946 U.S. App. LEXIS 2247 (10th Cir. 1946).

Opinion

MURRAH, Circuit Judge.

Beech Aircraft Corporation, as the manufacturer of airplanes for the United States Army and Navy, entered into a contract with the Douglas Aircraft Corporation to build wings for its A-26 Airplane. The A-26 had never been manufactured when Beech took the contract and its design required the production of many thousands of different' parts for which new “toolings” and “jigs” would have to be made. Beech entered into a sub-contract with Milburn M. Ross, doing business as Ross Engineering and Equipment Company to make the new ■“toolings” and “jigs,” and to manufacture certain parts. The contract was evidenced by purchase order No. 1007 and No. 1066, each of which set forth the quantity and price of each unit.

The “purchase order contracts” contemplated reduction or method changes, and provided that such change in price should be subject to negotiations prior to acceptance by the sub-contractor. 1 The prices stipulated in the sub-contracts were subject to revision after completion of the first one hundred units, based upon a cost analysis during the period of fabrication. 2 Any change in the contracts was to be effected by mutual agreement through the medium of supplemental sub-contracts. 3

In December 1943, before delivery of any units under purchase order contract No. 1007, Ross wrote Beech regarding a “revision of unit price per first orie hundred units.” Thereafter, the parties executed sub-contract “supplement No. 2” providing for a “tenfold” increase of the price of each unit covered by the original sub-contract, and providing" further “these price increases are made due to an underestimate on the original sub-contract and are subject to final revision after completion of the first one hundred (100) units, and are retroactive over the entire sub-contract.” 4

Statements were rendered and settlements were made from time to time in accordance with the revised prices under the supplemental contract. Delivery of the first one hundred units under the contracts was completed in May, 1944. In late June or early July of the same year Beech made a cost analysis, based upon a time study of Ross’ shop operations. As a result of this analysis Beech suggested that the unit prices be lowered, and conferences were held in an attempt to mutually agree on a new price. When the parties were unable *617 to reach, an agreement on a revision of prices Beech ceased paying Ross’ invoices. It continued, however, to accept delivery of parts at .the prices contained in the contracts, as supplemented, and to extend the contracts with orders for additional parts until September 1944, when it finally can-celled the contracts. .Ross-brought this suit on the contracts, as supplemented, to recover the unpaid balance-of the alleged,contract price' for units manufactured and delivered to Beech in. the sum of $98,865.43.

Beech’s defense -to the suit there, and here, is that the prices established by the contracts, as supplemented, were mere estimate, it being the plain intention of the parties to finally revise the unit prices, based upon experience gained from production and a time study of Ross’ operations after the first one hundred units had been produced. Accordingly, it tendered a cost analysis of Ross’ operations, based upon a time study, and argues that since the parties are unable to mutually agree upon a final revision of the prices the court should judicially determine a price, based upon a reasonable profit, to be retroactive over the entire contract.

The trial court held that by the original purchase order contracts the parties agreed in writing to negotiate price revisions only by mutual agreement; that the .parties did so revise the price schedule by the execution of the supplemental contracts, and the prices thus established were binding upon the parties to the contracts until revised by mutual consent, or until the contracts were cancelled under their provisions. In so holding, the court pointed out that there was nothing in the contracts or the supplements to indicate that upon failure of the parties to negotiate new prices, resulting in a cancellation of the contracts, the court was authorized to write a contract for the parties, thereby establishing prices upon which they did not, and could not agree.

It is true that the prices stipulated in the supplemental contracts were subject to final revision, after completion of the first one hundred units, and that the finally revised prices were to be retroactive over the entire sub-contract, but .the supplemental contracts provided no formula for final revision of

the prices. The parties obviously intended, to-rely upon the provisions of Item XXV (see footnote 2), which provides for revision after completion of the first one hundred units based upon an actual time study of a cost analysis. Indeed, when Ross requested a change in the unit prices, he expressly stated in his letter of December 23rd, 1943, that upon completion of the first one hundred units the price of each item was to be subject to the provisions of Item XXV.

It is the general rule that a contract, price must be definite and certain, or capable of ascertainment from the contract itself, else.it cannot be enforced. Vol. 12, American Jurisprudence Contracts, Sec. 70; Annotation, 92 A.L.R. 1396; Williston on Contracts (R.Ed.)- Sec. 45. If, however, the contract contains matter which will enable the court to ascertain .the terms and conditions on which the parties intended to bind themselves, it will give effect to the manifest intention of the parties. -The courts . will not permit a contract to fail .for the want of a formal detail, which can.be, supplied within the frame work, of the contract itself. Thus, if the contract provides,-for the payment of a reasonable or a, j_uqt¡U|pd equitable price, and .the parties are unable to agree upon what is reasonable'or jüst and equitable, the courts will imply that the parties intended for the court' to determine a reasonable price as a consideration for the contract. Joy v. St. Louis, 138 U.S. 1, 11 S. Ct. 243, 34 L.Ed. 843; United States v. Swift & Co., 270 U.S. 124, 141, 46 S.Ct. 308, 70 L.Ed. 497; Brunner v. Stix, Baer & Fuller Co., 352 Mo. 1225, 181 S.W.2d 643; Raisler Sprinkler Co. v. Automatic Sprinkler . Co., 6 W.W.Harr., Del., 57, 171 A. 214. Or, if the agreement makes no provision with reference to the price to be paid, the court may invoke the standard of reasonableness as a necessary implication of a policy to páy for services rendered, and the fair value of the services or property is the consideration. Vol. 12, Amer.Juris.Contracts, Sec. 324.

Neither party seeks to annul the contracts. Their differences lie in the matter of interpretation. The appellant contends . that we not only have a contract for ..work. *618 to be done without an established price, but one in which the final contract price was to be based upon a time study of a cost analysis after a certain amount of the work has been performed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Union Electric Co. v. Consolidation Coal Co.
188 F.3d 998 (Eighth Circuit, 1999)
Murphy v. Haws & Burke
344 A.2d 543 (Superior Court of Pennsylvania, 1975)
Lockheed Aircraft Corporation v. The United States
426 F.2d 322 (Court of Claims, 1970)
Coleman Engineering Co. v. North American Aviation, Inc.
420 P.2d 713 (California Supreme Court, 1966)
Hays v. Underwood, Administrator
411 P.2d 717 (Supreme Court of Kansas, 1966)
Alaska Creamery Products, Inc. v. Wells
373 P.2d 505 (Alaska Supreme Court, 1962)
Oil Trading Associates, Inc. v. Texas City Refining, Inc.
199 F. Supp. 829 (S.D. New York, 1961)
Potucek v. Blair
270 P.2d 240 (Supreme Court of Kansas, 1954)
A. M. Webb & Co. v. Robert P. Miller Co.
176 F.2d 678 (Third Circuit, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
155 F.2d 615, 1946 U.S. App. LEXIS 2247, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beech-aircraft-corporation-v-ross-ca10-1946.