Bedford v. J. Henry Miller, Inc.

212 F. 368, 129 C.C.A. 44, 1914 U.S. App. LEXIS 2085
CourtCourt of Appeals for the Fourth Circuit
DecidedMarch 4, 1914
DocketNo. 1214
StatusPublished
Cited by5 cases

This text of 212 F. 368 (Bedford v. J. Henry Miller, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bedford v. J. Henry Miller, Inc., 212 F. 368, 129 C.C.A. 44, 1914 U.S. App. LEXIS 2085 (4th Cir. 1914).

Opinion

WOODS, Circuit Judge.

The defendant, J. Henry Miller, incorporated under the laws of Maryland, contracted with the United States-on March 26, 1910, for the reconstruction of the federal building in the city of Richmond, the work to be completed by December 1, 1911. On May 11, 1910, the plaintiff, A. C. Bedford, agreed as subcontractor with the defendant to do the stone work by May 11, 1911, for the sum of $190,000, payable in installments as the work progressed. On December 21, 1912, the plaintiff brought this action in the law and equity court of the city of Richmond, alleging full performance of his contract, and indebtedness of the defendant to him in the sum of $23,406.29, after allowing all credits. The cause having been removed on the ground of diversity of citizenship to the District Court of the United States for the Eastern District of Virginia, the defendant pleaded nonassumpsit, and with this plea gave notice that on the trial it would seek to recoup or set off damages for 392 days’ delay in the completion of the work, at $50 a day; that being the per diem measure of damages fixed in the contract. The defendant also set up as a separate item a claim for $5,000 damages for delay in the completion of the approach work within the time required by the contract, and several charges for labor and material furnished to plaintiff, amounting to $1,403.18. The District Judge overruled a motion to reject the set-off, made on the ground that it was not supported by the affidavit required by law, and was not in the form prescribed by the rules of court, and allowed the defendant to amend so as to conform his pleading to the legal requirements. At the trial the claim for the separate item of $5,000 damages was withdrawn; the separate account of $1,403.18 was submitted to the jury; and the peremptory instruction was given to the jury that the defendant’s claim for liquidated damages of $50 a day for 392 days must be allowed as a set-off. The verdict and judgment was in favor of the plaintiff for •$3,516.30, with interest from December 7, 1912.

[1] The error assigned in the refusal to reject defendant’s pleas because of absence of the affidavit required by law was abandoned at the argument. There is no ground for assignment of error in allowing the defendant to amend rather than in rejecting its plea because of a defect in form only. The discretion of the court to allow amend-[370]*370merits is so clearly conferred by section 954 of" the Revised Statutes (U. S. Comp. St. 1901, p. 696) that it is unnecessary to cite any of the numerous cases on the subject. When a party gets his cause of action, or his defense, or his appeal, before a court, of competent jurisdiction, he should not be turned out before trial of the merits of the controversy, except in obedience to a clear statutory mandate, or on a showing of gross carelessness or bad faith. The absolute’ dismissal of a plea or an appeal, for error in a matter of mere procedure, is in reality the infliction of the severest penalty for a minor fault, and is suggestive of the excessive punishments formerly inflicted for minor offenses in the administration of the criminal law. Conformity to rules of procedure is important, but usually it may be secured by imposing as a condition of amendment the payment of costs or other penalty, short of dismissal, on the party or his counsel, as circumstances may require, for negligence or inadvertence.

The vital question in the cause is whether the plaintiff was bound at all events to pay as liquidated damages the sum of $50 a day for the time he was in default in the performance of his contract. The agreement on this subject was as follows:

“It is further covenanted and agreed by and between the parties hereto that, the time being the essence of the said contract between the builder and the United States of America, it is also the essence of tMs contract, and therefore in the event of the failure on the part of the contractor to furnish the materials and labor provided for by this contract to be furnished by him (when and as required as aforesaid), within a reasonable time after such request, not to exceed five (5) days, or in the event of the failure of the contractor to furnish and set all the stone work required for the building proper (not including the approach work, pointing up or cleaning down) within twelve months after the date of this contract, or in event of the contractor furnishing materials which shall be condemned or rejected, thereby causing delay in the erection, construction or completion of the work to be performed by the builder under Ms contract with the United States of America, beyond said period of twelve months, then and in either event the contractor shall pay to the builder for each and every calendar day of such delay the sum of fifty dollars ($50.00). ■ The completion of the approach work, pointing up and cleaning down to be done in such time as the builder shall direct to be not less than fifteen (15) months after the date of this contract, or as' will permit the building to be finished in contract time as hereinbefore provided for, to wit, on December 1, 1911. The above forfeit is to be paid as and for liquidated damages and, not as a penalty and is to be taken from any money due 'hereunder. The said measure of such liquidated damages being fixed and agreed upon as the sum specified as the damages which will be suffered by the builder by reason of such default are difficult to estimate with exactness, and it is understood and agreed by the parties hereto that said liquidated damages are in lieu of the actual damages arising from such breach of this contract.”'

The builder, Henry Miller, did not perform his contract by completing, the entire work by December 1, 1911. But, under authority conferred by statute, the secretary of the treasury, for reasons appearing to him sufficient, remitted the claim of the government agains.t him for $50 a day liquidated damages, and paid Henry Miller, the builder, the entire contract price. Thus it appears that the defendant suffered no loss on account of its liability to the government by reason of the delay of the plaintiff in the completion of his work.

[2] Whatever may have been the conflict of authority as to tlie [371]*371rules to be applied in determining whether a contract like that here under consideration provided for a penalty or liquidated damages, certainly there can be no doubt now in this jurisdiction that this was a contract to pay $50 a day as liquidated damages and not as a penalty. In Sun, etc., Association v. Moore, 183 U. S. 642, 22 Sup. Ct. 240, 46 L. Ed. 366, the Supreme Court thus lays down the rule:

“The decisions of this court on the doctrine of liquidated damages and penalties lend no support to the contention that parties may not bona fide, in a case where the damages are of an uncertain nature, estimate and agree upon the measure of damages which may be sustained from the breach of an agreement. On the contrary, this court has consistently maintained the principle that the intention of the parties is to be arrived at by a proper construction of the agreement made between them, and that whether a particular stipulation to pay a sum of money is to be treated as a penalty, or as an agreed ascertainment of damages, is to be determined by the contract, fairly construed; it being the duty of the court always, where the damages are uncertain and have been liquidated by an agreement, to enforce the contract.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Manufacturers Cas. Ins.
113 F. Supp. 402 (S.D. New York, 1953)
McAllister v. Sloan
81 F.2d 707 (Eighth Circuit, 1936)
Boston Iron & Metal Co. v. United States
55 F.2d 126 (Fourth Circuit, 1932)
Northwestern Terra Cotta Co. v. Caldwell
234 F. 491 (Eighth Circuit, 1916)
Rainier v. Masters
154 P. 426 (Oregon Supreme Court, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
212 F. 368, 129 C.C.A. 44, 1914 U.S. App. LEXIS 2085, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bedford-v-j-henry-miller-inc-ca4-1914.