Beckwith v. United States

38 Ct. Cl. 295, 1903 U.S. Ct. Cl. LEXIS 127, 1902 WL 1105
CourtUnited States Court of Claims
DecidedFebruary 16, 1903
DocketNo. 16618
StatusPublished

This text of 38 Ct. Cl. 295 (Beckwith v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beckwith v. United States, 38 Ct. Cl. 295, 1903 U.S. Ct. Cl. LEXIS 127, 1902 WL 1105 (cc 1903).

Opinion

Peelle, J.,

delivered the opinion of the court:

This action is to recover for certain work performed b}^ the claimants for the United States in the extension of the Washington Aqueduct and for money retained for like work under their contract, dated October 29, 1883, with the defendants, through Maj. G. J. Lydecker, Corps of Engineers, U. S. Army, approved by the Chief of Engineers November 19, 1883, and sundry supplemental agreements hereinafter referred to, all being made part of the petition in this case.

Under the original contract the claimants obligated themselves to furnish the materials, to do the work, and to construct a tunnel about”twenty thousand eight hundred and twenty-six (20,826) feet in length, eleven (11) feet wide, and seven and one-half (7i) feet high, from the distributing reservoir above Georgetown to the proposed new reservoir east of Howard Universit3T, in consideration of which the United States agreed to payr therefor (on monthty estimates approved by the engineer, less 10 per cent to be retained until the final completion and acceptance of the work) as follows:

“For excavation in tunnel, eight (8) dollars per cubic yard.
“For earth excavation in shafts, six (6) dollars per cubic yard.
“ For rock excavation in shafts, ten (10) dollars per cubic juird.
“For brick masonry in tunnel, fourteen (14) dollars per cubic j-ard.
“For concrete masomy in tunnel, five (5) dollars per cubic 3rard.
“For dry stone packing in tunnel, two (2) dollars and fift3r (50) cents per cubic yard.
“For brick masonry in shafts, eighteen (18) dollars per cubic 3rard.
“For concrete masonry in shafts, five (5) dollars per cubic 3Tard.
“For dry stone packing in shafts, two (2) dollars and fifty^ (50) cents per cubic 3rard.
“For air shafts, complete, fifteen (15) dollars per lineal foot.”

[306]*306The work was to be commenced on or before the 20th day of November, 1883, and to be completed on or before the 30th day of June, 1885.

The contract, among other things, provided that—

“All materials furnished and work done under this contract shall, before being accepted, be subject to a rigid inspection by an inspector appointed on the part of the Government, and such as does not conform to the specifications set forth in this contract shall be rejected. The decision of the engineer officer in charge 'as to quality and quantity shall be final.”

The specifications made part of the contract provided fox-dry stone packing for filling large void spaces wherever the same could be advantageously done to save concrete masonry.

II nder the terms of that contract the claimants began work in December, 1883, and continued until the 30th day of January, 1886, when work thereunder was suspended by the United States.

Thereafter, on October 18,1886, the same parties executed a supplemental agreement, whereby it was, among other things, in substance provided that, as the Congress had by the general deficiency act of August 4,1886, in making appropriations for the completion of the tunnel, instructed the Secretary of War “to submit to the board of engineers for fortifications and for river and harbor improvements whether any changes are demanded for reasons of safety or economy in the method of lining said tunnel heretofore adopted and pursued; ” and as said board had, as. recited in said supplemental agreement, made a report August 24, 1886, requiring ‘ ‘ rubble laid in cement mortar or with fine concrete packed solidly around larger stone,” in lieu of the dry stone packing provided for m the original contract, thereb}^ necessitating a modification in the original project, increasing the cost of the work, it was for that reason agreed:

“That the said party of the second part, iri consideration of the extension of the original contract to include the work of lining that may be done under the appropriation made by the act approved August 4, 1886, hereinbefore referred to, and of payment to be made as hereinafter provided, shall furnish all material for, and place rubble laid in cement mortar wherever required in the tunnel, all as directed by and to the entire satisfaction of the party of the first part.
[307]*307“ In consideration of the material being- furnished and the rubble laid as provided for in the foregoing- paragraph, the said party of the first part shall pay to the said party of the second part at the rate of four (4) dollars and seventy-five (75) cents per cubic yard; all payments being subject to the conditions named in the original contract.”

It was therein further provided that the original contract should “ apply to the work and materials provided for by the supplemental articles of agreement so far as the provisions are deemed applicable by the party of the first part.”

The claimants resumed work August 30, 1886, and continued under the original and supplemental agreement aforesaid until September 30,1887, when the work was again suspended by the United States.

Thereafter, December 5, 1887, the same parties entered into a second supplemental agreement wherein, among other things, it was in substance provided that in furtherance of and supplemental^ to the aforesaid original and supplemental contracts, and by reason of the exhaustion of the appropriations theretofore made for the work, it became necessary to suspend active operations, and for that reason it was deemed for the mutual interest of both parties:

“First. That in consideration of the work already done to the satisfaction of the party of the first part, and of the further consideration that the entire work in contemplation can not be completed under any contract in which the parties of the second part are now concerned, the party, of the first part shall surrender and pay to the parties of the second part the sum of seventy-eight thousand two hundred and seventy-nine dollars and fifty-one cents ($78,279.51), such sum being eighty-five (85) per cent of the percentage heretofore retained and •withheld from the parties of the second part as a guarantee for the faithful performance of their work as provided in the original articles of agreement.”

Further provision was made therein for delay in the removal of the machinery, rubbish, and refuse material until after an appropriation should be made for the resumption of operations and for keeping the pumping machinery in proper order for use when needed, the Government to pay the expenses of operating the same in the meantime and to compensate the contractors for the use thereof.

[308]*308It was further provided tnat nothing therein contained should “be construed to release from or add to any obligation, liability, right, or duty devolving on either partjr under the operations of the two several articles of agreement to which the foregoing are supplemental.”

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
38 Ct. Cl. 295, 1903 U.S. Ct. Cl. LEXIS 127, 1902 WL 1105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beckwith-v-united-states-cc-1903.