Beckmann Concrete Contractors, Inc. v. United Fire & Casualty Co.

600 S.E.2d 76, 360 S.C. 127, 2004 S.C. App. LEXIS 173
CourtCourt of Appeals of South Carolina
DecidedJune 1, 2004
Docket3814
StatusPublished
Cited by5 cases

This text of 600 S.E.2d 76 (Beckmann Concrete Contractors, Inc. v. United Fire & Casualty Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beckmann Concrete Contractors, Inc. v. United Fire & Casualty Co., 600 S.E.2d 76, 360 S.C. 127, 2004 S.C. App. LEXIS 173 (S.C. Ct. App. 2004).

Opinion

ANjDERSON, J.:

Beclmann Concrete Contractors, Inc. (Beckmann) brought suit against United Fire and Casualty Co. (United) to collect on a payment bond that United issued to Golf Construction of America (Golf Construction). United was found in default for failing to file an answer. The court entered a default judgment against United. United moved for relief from the judgment alleging it did not receive notice under Rule 55(b)(2), SCRCP, and contending it was entitled to relief under Rule 60(b)(1), SCRCP. The court denied the motion. We vacate and remand.

FACTUALIPROCEDURAL BACKGROUND

Golf Construction was employed to perform work at the Golf Club at Westcott Plantation. United supplied a payment bond to Golf Construction in the amount of $367,373.06 for the amount of the contract. The contract required Golf Construction to perform clearing, grubbing, and silt fence installation. Subsequently, the work to be performed by Golf Construction was expanded. However, United did not provide any additional payment bond, nor was the scope of its bond expanded to include the additional work of bridge construction or concrete work.

Beckmann was a subcontractor hired to work on the concrete golf cart paths. In a letter, Beckmann notified United that it was asserting a claim on the payment bond. United denied the claim and maintains that it owes nothing under the bond for the work performed by Beckmann. Beckmann subsequently filed a Summons and Complaint, alleging United issued a payment bond and is liable under that bond for the work performed by Beckmann. Beckmann averred it is owed $80,938.25.

*130 Beckmann’s counsel filed an Affidavit of Default, claiming United had failed to answer the complaint and failed to serve a notice of appearance. Beckmann filed a Certification and Petition for Default Judgment which iterated its claim of damages in the amount of $80,938.25, asserted the damages were liquidated damages, and claimed to have attached supporting documentation for the damages. The Certification and Petition for Default Judgment provided:

The undersigned attorney for Plaintiff hereby certifies that this application for default judgment, pursuant fo Rule 55, SCRCP, against United Fire and Casualty Company is based upon a complaint alleging a cause of action based upon a liquidated debt; and further certifies that the following documents are either attached or have been filed with the Clerk of Court in support of the foregoing, to wit:
a. Summons and complaint;
b. Proper proof of legal service upon the defendant, United Fire and Casualty Company;
c. Proper documentation supporting liquidated demand in the amount of eighty thousand nine hundred thirty-eight dollars and twenty-five cents ($80,938.25) set forth in complaint as provided by statute; together with proper documentation for award of attorney’s fees and interest, if applicable, pursuant to the terms of a written agreement; and
d. Affidavit of Default.

The court entered an order of default judgment against United and awarded $80,938.25 to Beckmann. United filed a motion for relief from the default judgment. United argued notice was required under Rule 55(b)(2), SCRCP, because the damages were not liquidated or sum certain damages. Additionally, United contended the judgment should be set aside under Rule 60(b)(1), SCRCP, or Rule 55(c), SCRCP, because the failure to answer was the result of excusable neglect or good cause.

The court found the claim was for liquidated damages and, therefore, notice was not required. The court concluded the reasons alleged by United for failing to file an answer were neither “excusable neglect” under Rule 60(b)(1) nor “good cause” under Rule 55(c).

*131 STANDARD OF REVIEW

The power to set aside a default judgment is addressed to the sound discretion of the trial court whose decision will not be disturbed on appeal absent a clear showing of an abuse of that discretion. Frank Ulmer Lumber Co. v. Patterson, 272 S.C. 208, 250 S.E.2d 121 (1978); In re Estate of Weeks, 329 S.C. 251, 495 S.E.2d 454 (Ct.App.1997). “An abuse of discretion in setting aside a default judgment occurs when the judge issuing the order was controlled by some error of law or when the order, based upon factual, as distinguished from legal conclusions, is without evidentiary support.” Estate of Weeks, 329 S.C. at 259, 495 S.E.2d at 459.

LAW/ANALYSIS

I. Unliquidated Damages

United claims the damages alleged by Beckmann were not liquidated damages and Beckmann did not follow the procedure mandated by Rule 55(b)(2), SCRCP, in regard to unliquidated damages. United argues the damages were unliquidated and, therefore, it was entitled to notice of the damages hearing.

When the defendant has not answered or otherwise appeared, there is no requirement that notice be given before entering a default judgment. See Rule 55(b), SCRCP; Roche v. Young Brothers, Inc., 318 S.C. 207, 456 S.E.2d 897 (1995). However, when the relief which is sought is unliquidated damages, Rule 5(a) specifically states that “notice of any trial or hearing on unliquidated damages shall also be given to parties in default.” Rule 5(a), SCRCP.

In Lewis v. Congress of Racial Equality, 275 S.C. 556, 274 S.E.2d 287 (1981), our Supreme Court declared: “In liquidated-damages cases, the amount is usually a sum certain, or at least the amount is capable of ascertainment by computation.” Id. at 560, 274 S.E.2d at 289. Black’s Law Dictionary defines liquidated damages as “[a]n amount contractually stipulated” in contrast to unliquidated damages which are “[damages that ... cannot be determined by a fixed formula, so they are left to the discretion of the judge or jury.” Black’s Law Dictionary 395-97 (7th ed.1999). Liquidated damages *132 “are damages the amount of which has been made certain and fixed either by the act and agreement of the parties or by operation of law to a sum which cannot be changed by the proof.” 22 Am.Jur.2d Damages § 489 (2003). “They are also defined as damages the amount of which has been ascertained by judgment or by the specific agreement of the parties or which are susceptible of being made certain by mathematical calculation from known factors.” Id. “In general, damages are unliquidated where they are an uncertain quantity, depending on no fixed standard, referred to the wise discretion of a jury, and can never be made certain except by accord or verdict.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paul David Hess v. Morphis Pediatric Group
Court of Appeals of South Carolina, 2025
Wells Fargo Bank v. Marion Amphitheatre, LLC
757 S.E.2d 557 (Court of Appeals of South Carolina, 2014)
Johnny's Oil Co. v. Eldayha
978 N.E.2d 86 (Massachusetts Appeals Court, 2012)
Dixie Bell, Inc. v. Redd
656 S.E.2d 765 (Court of Appeals of South Carolina, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
600 S.E.2d 76, 360 S.C. 127, 2004 S.C. App. LEXIS 173, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beckmann-concrete-contractors-inc-v-united-fire-casualty-co-scctapp-2004.