Becker v. Lincoln Building Co.

187 N.W. 382, 218 Mich. 79, 1922 Mich. LEXIS 541
CourtMichigan Supreme Court
DecidedMarch 30, 1922
DocketDocket No. 124
StatusPublished

This text of 187 N.W. 382 (Becker v. Lincoln Building Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Becker v. Lincoln Building Co., 187 N.W. 382, 218 Mich. 79, 1922 Mich. LEXIS 541 (Mich. 1922).

Opinion

Moore, J.

Plaintiffs were the owners of a lot in the city of Detroit. On the 29th day of May, 1919, [81]*81they entered into a written contract, wherein defendant agreed to construct for plaintiffs, on the lot of the plaintiffs, a two-family flat, according to certain plans and specifications. The plaintiffs were to convey to defendant their title in such lot and the defendant was to construct the building, plaintiffs to pay a total sum of $14,500, $1,000 cash, a credit of $3,000 for the lot and the balance at the rate of $105 per month with interest, etc. On the same day the lot was deeded to defendant, a land contract for the re-conveyance of the land in the usual form was executed between the parties, and delivered to the plaintiffs. The building contract provided that defendant should proceed with the construction of said building with promptness. The contract further provided that if plaintiffs should fail to meet the payments, defendant was given the right to cancel the contract and recover for work done and materials furnished or continue the work and recover the contract price. If, on the other hand, defendant should not proceed and complete the building in accordance with such contract the plaintiffs might take over the building and finish it, holding defendant liable for any additional costs from the money due defendant when the entire job had been completed.

It is claimed the building was to be completed by August 1st, but there was no time limit in the written contract. In the meantime the plaintiffs had sold the house in which they were living at the time the contract was made, and agreed to give possession October 1st, and they got very impatient at the slowness with which the building progressed.

On or about the 1st day of October a controversy arose over the construction of waterproof floors in the bath rooms of said building which plaintiffs claimed were to be constructed under the terms of the contract and necessary in order to conform to the building code [82]*82of the city of Detroit, and which defendant refused to construct, unless plaintiffs paid extra for such work and material. Correspondence passed between the parties, which we quote:

“October 1, 1919.
“Mr. Anthony H. Becker,
“774 Leland Ave.,
“Detroit, Michigan.
“Dear Sir: In re two-family flat at lot 102, Dakota avenue.
“The city code requires that gas vents be installed in this building. The cost of this will be $25.
“The code also requires that waterproof floors be put in all bath rooms. A terrazzo floor will cost you $100 for each bath room, and cement floor $60 for each bath room.
“We are in receipt of your check for $7.50 covering the cost of surveying, and thank you very much for same.
“Please let us have your check for $225 if you wish a terrazzo floor in each bath room, or $145 if you wish us to have cement floor put in.
“Kindly give this matter your prompt attention, so as not to delay the progress of the building any more than is necessary.
“Yours very truly,
“Lincoln Building Company.
“P. S. The above items are not covered in the specifications, and we must therefore ask that you send us your check to cover the additional expense involved.”
“774 Leland St., Detroit, Mich., Oct. 11, 1919.
“Lincoln Building Co.,
“Detroit, Mich.
“Gentlemen: Re lot No. 104, Dakota Ave.
“Referring to your letter of October 1st in which you demand of us a payment of one hundred (100) dollars for putting in a waterproof floor in each bath room in the flat you are building for us.
“Notwithstanding our contract explicitly provides that you shall complete the building in all respects complying with the local ordinances and building code, [83]*83although the same are not explicitly mentioned, we find ourselves at present in a position where we are compelled to pay your demand, because we have already made a contract to deliver our present residence, at a time already past, intending to move into this flat, and we are daily increasing our liability for failure to do so. We are accordingly paying you the two hundred (200) dollars demanded, not because of any recognition on our part, of any liability to you to make such payment, but because our situation forces us to do it, and we protest and shall insist that you are legally liable to us for the money so paid, as paid without consideration.
“Yours truly,
(Signed) “Anthony H. Becker,
“Minnie Becker.”
“3003 Woodward Avenue, Oct. 13, 1919.
“Mr. Anthony H. and Minnie Becker,
“774 Leland St.,
“Detroit, Michigan.
“Dear Sir and Madam: We have your favor of the 11th inst, handed to us on the same date by Mr. J. W. Farrington, together with check calling for $200, signed by E. A. Becker, and in reply will say that your communication does not state what kind of a waterproof floor you wish us to install in your two family flat at lot 104, Dakota avenue.
“If it is for terrazzo floor, we wish you would kindly mail us letter instructing us to proceed with this kind of a floor, and that the $200 check is sent to us in payment of the work to be done on the terrazzo floors in the bath rooms. We also wish you would state in your letter that the terrazzo floors are extra, not called for in the plans and specifications or contract, with no strings attached to the payment of the check to us, as you know as well as anyone that there is no terrazzo floor called for in either the plans or specifications.
“If you do not want to pay for extras you had better advise us at once and we will stop putting them in. You know as well as we do that it costs money to build in these days.
“The writer was also down to the bank this morning and learned from the manager of the mortgage de[84]*84partment that you had not left the deeds and contracts with him, as you promised you would do. This is to inform you that unless this is done at once, it is our intention to stop the work after this week on this building, after which time it will be necessary for you to pay ns cash in full for all work, labor and material put into this job, and we will be compelled to insist that the money be paid for all work, labor and material before it is furnished in this job.
“Please be governed accordingly.
“Yours very truly,
“Lincoln Building Company,
President.”
“(Letter Head Rood & Visscher.)
October 15, 1919.
“Lincoln Building Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martus v. Houck
39 Mich. 431 (Michigan Supreme Court, 1878)
L. A. Thompson Scenic Railway Co. v. McCabe
178 N.W. 662 (Michigan Supreme Court, 1920)
Ginsberg v. Myers
183 N.W. 749 (Michigan Supreme Court, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
187 N.W. 382, 218 Mich. 79, 1922 Mich. LEXIS 541, Counsel Stack Legal Research, https://law.counselstack.com/opinion/becker-v-lincoln-building-co-mich-1922.