Becker v. Hopper

138 P. 179, 23 Wyo. 209, 1914 Wyo. LEXIS 32
Wyoming Supreme Court·Decided January 27, 1914·No. No. 756·Published·Cited by 9 cases

Opinion

Potter, Chief Justice.

This was an action brought by the defendants in error, John W. Hopper and Edward T. Bartley, co-partners doing-business under the name of Hopper & Bartley, to enforce an alleged mechanics’ lien upon certain real estate of the plaintiff in error, Charles Becker, upon which the plaintiff in error, Henry Becker, held a mortgage; the lien, being claimed for certain -work performed and materials furnished in and about the construction of a building, at the request of and for the firm of Brice & Mitchell, the contractors engaged in constructing said building. The case came to this court on error for review of the judgment entered upon the trial of the action establishing the lien for the sum of $950.27 and costs of suit, including $25 for attorney’s fees. Upon the original hearing in this court the cause was ordered remanded to the District Court with directions to modify the judgment by deducting the sum of $392 from the amount of the lien and striking out the amount allowed as attorney’s fees, and as so modified the judgment was affirmed. (138 Píac. 179.) The plaintiff in error, Charles Becker, filed a petition for rehearing, complaining only of the conclusion stated in the opinion that the plaintiffs in error as defendants below, by failing to raise the objection by answer, had waived the objection that the surviving member of the firm of Brice & Mitchell, the original contractors, had not been brought into the case as a party defendant by proper constructive service. The defendants in error also filed a petition for rehearing, alleging error in the conclusions of the court in three particulars: 1. In holding the statute allowing an attorney’s fee in the case to be unconstitutional. 2. In holding the provisions of Chapter 68 of the Laws of 1911, with reference to the sufficiency of a lien [215] statement, inapplicable to this case. 3. In holding that the item of $1,292 was insufficiently described in the lien statement to entitle the parties filing the same to a lien. A rehearing was granted, and the cause has again been heard. A reconsideration of the' points on which a rehearing was asked has failed to convince the court of any error in the previous decision, and the writer hereof, who did not participate in that decision, joins the other members of the court in the view that the conclusions stated in the former opinion should be adhered to. The questions again raised by the petition of the defendants in error are sufficiently discussed in the former opinion, and what was there said as to those questions will be adopted for the purpose of disposing of them- upon this rehearing.

In the petition of plaintiff in error for a rehearing it was stated that the objection that there was a defect of parties through the failure to properly bring the contractor into the case as a defendant was disposed of by the court on a ground not referred to in brief or oral argument or suggested at the original hearing, viz.: that the objection had been waived by the failure to raise it by answer. The argument against the view that the objection was so waived is confined to a review of the Missouri cases on the subject, on the theory that they should be followed here since our mechanics’ lien statute was taken from that state. And it is contended that the effect of the Missouri decisions is to plainly declare it necessary and essential to a valid judgment enforcing a mechanics’ lien that the one with whom the contract for the labor or materials was made by the lien claimant be properly brought into the case as a party defendant, and that where he is not made a party the defect is not waived by a failure to take the objection by demurrer or answer. We are not satisfied that such is clearly the result of the Missouri cases, where the action is brought in a court of record governed in the matter of procedure by the provision of the statute in that state, similar to our own, to the effect that the objection on the ground of a defect of parties is waived unless taken by demurrer or answer. [216] (Horstkotte v. Menier, 50 Mo. 158; Johnson-Frazier Lumber Co. v. Schuler & Muench, 49 Mo. App. 90.) In Horstkotte v. Menier, a case decided in 1872, the court said: “What we now hold is that the original contractor ought to be brought before the court as a co-defendant, for the purpose of protecting his own rights and those of the owner. But if he is not so brought before the court at the proper time, the judgment will not for this omission be error or void. The objection should have been taken by the owner by demurrer or answer. If he fails to demur when the defect appears on the petition, or fails to set up the non-joinder by answer when it does not appear on the face of the petition, he will be presumed to have waived the objection. (Wagn. Stat. 1014-1015, Secs. 6, 10.) The defect of parties cannot be reached by way of instruction.” In Johnson-Frazier Lumber Co. v. Schuler & Muench, an action to enforce a mechanics’ lien originally brought before a justice of the peace, the court said: “It is contended by the plaintiff that, although the appealing defendants had the right to have the contractors, Schuler & Muench, made co-defendants and served with process, yet, as that was not done, and as they took no steps before judgment to have it done, that they thereby waived their right. It has been oftentimes decided under our practice act that unless the objection of defect of parties to the record is made, either by demurrer or answer, it will be deemed waived. (Gimbel v. Pignero, 62 Mo. 240; Butler v. Lawson, 72 Mo. 227.) And this rule has been held to apply in actions brought upon mechanics’ liens in courts of record. (Horstkotte v. Menier, 50 Mo-. 158; Fruin v. Furniture Co., 20 Mo. App. 313.) But the statute, Section 2047, upon which the foregoing rule of practice is based, is limited to actions in courts of record, Section 2038, and hence is not applicable to actions brought before justices of the peace.”

Our attention has not been called to any decision of the Supreme Court of Missouri overruling the case of Horst-kotte v. Menier. But we are cited to a case in one of the intermediate appellate courts of that state, viz.: Steinmann [217] v. Strimple, 29 Mo. App. 478, wherein the court distinguished Horstkotte v. Menier from the case then under consideration by stating- that the former was a case where the lien claimant was one whose contract had been made with a sub-contractor, so that the original or principal contractor was not one of the “parties to the contract” within the “mandatory provision” of the mechanics’ lien statute that “the parties to the contract shall” be made parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Becker v. Hopper, 138 P. 179, 23 Wyo. 209, 1914 Wyo. LEXIS 32 (Wyo. 1914).

138 P. 179 (Becker v. Hopper) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hamel v. American Continental Corp.
713 P.2d 1152 (Wyoming Supreme Court, 1986)
White v. Diamond International Corp.
665 P.2d 463 (Wyoming Supreme Court, 1983)
True v. Hi-Plains Elevator MacHinery, Inc.
577 P.2d 991 (Wyoming Supreme Court, 1978)
Lasich v. Wimpenney
278 P.2d 807 (Wyoming Supreme Court, 1955)
Jordan v. Natrona Lumber Co.
75 P.2d 378 (Wyoming Supreme Court, 1938)
Peters v. Dona
54 P.2d 817 (Wyoming Supreme Court, 1936)
Andrew v. Bishop
172 A. 752 (Supreme Judicial Court of Maine, 1934)
Prugh v. Imhoff
9 P.2d 152 (Wyoming Supreme Court, 1932)
Kirch v. Nicholson
297 P. 398 (Wyoming Supreme Court, 1931)