Becker v. City of New York

53 A.D. 301, 65 N.Y.S. 899, 1900 N.Y. App. Div. LEXIS 1918
Appellate Division of the Supreme Court of the State of New York·Decided July 1, 1900·Published·Cited by 1 cases

Opinions

McLaughlin, J.:

On the 13th of November, 1889, the defendant entered into a contract with one Carr for the regulating and grading of Claremont avenue, from One Hundred and Twenty-second to One Hundred and Twenty-seventh streets, in the city of New York. At the completion of the work a final certificate was made by the engineer in charge, to the effect that Carr was entitled to receive, under his contract, .the sum of $24,735.77. This amount, prior to the commencement of the action, had been paid to him, except the sums of $325, ‘‘ repairing security,” retained according to the provisions of the contract, and $2,044, paid by the defendant to an inspector of the work, retained by it upon the alleged ground that it had a right to withhold that sum for the reason that Carr had not completed his contract within the time specified. Subsequently Carr assigned his claim under the contract to one Brady, and the plaintiff, as his executrix, has brought this action to recover the $325, the $2,044 and $6,568.80 for work done under the contract, which she alleges the engineer falsely and fraudulently refused to include in the final certificate, and also the further sum of $9,739.95, increased cost of completing the work under the contract, which she alleges was occasioned by the city surveyor giving erroneous ■ center and grade lines of the street. Other causes of action were alleged, but inasmuch as the complaint was dismissed as to them, it is unnecessary to consider them since the plaintiff has not appealed.

At the close of the trial, which took place at the end of plaintiff’s case, the defendant offering no evidence, each party moved for the direction of a verdict, and it was then agreed between counsel that the jury be discharged and that the court might take the ease under consideration and thereafter direct a verdict in precisely the same way as though it had been done in the presence of the jury at the trial. This was done, and the agreement amounted to a submission of the whole case to the trial court, and the decision had the same effect as though a verdict had been rendered by direction of the court at the close of the trial. (Adams v. Roscoe Lumber Co., 159 N. Y. 176.) The court thereafter directed a verdict in favor of the plaintiff for $16,776.50, together with interest thereon to the date of the trial, and from the judgment entered on such direction defendant has appealed.

[303]*303In considering the question presented upon this appeal, we must assume that every fact necessary to be established by the plaintiff to entitle her to a verdict was found in her favor in so far as there was evidence to sustain the finding.

As to the $325, “ repairing security,” it is not questioned but that the plaintiff is entitled to recover that sum ; therefore, so much of the appeal as relates to that item may be dismissed without further consideration. The three remaining items will be considered together. It is not disputed but that the defendant paid $2,044 to an inspector, and that such payment was caused by reason of the contractor's failure to complete the work under the contract within the time specified therein. Neither is there any contest between the parties that the engineer did not include in the final certificate the amount of the second item, nor that it cost the contractor the amount claimed in the third item to do the additional work. But it is claimed by the appellant that it is not liable to the respondent for these items, or any of them, for the reason that the delay which resulted in the payment of the $2,044 to the inspector, as well as the cost of the additional work not included in the final certificate, and the increased cost of doing the work, was the fault of the contractor and not the fault of the defendant, since the same were occasioned by an error in designating the center and grade lines of the street.

After a careful consideration of the contract under which the work was done, and the evidence introduced by the plaintiff in explanation of the delay, the additional work and increased cost, we have been unable to reach a conclusion other than that the same were caused by the contractor and not the defendant. It will be remembered that the work was all done under a written contract, which provided that the contractor, prior to the execution of the contract, had satisfied himself of “ the location ” of the work by a personal examination, and he had agreed that he would not, at any time thereafter, dispute or claim that the statements or assertions contained in the proposals for the work were inaccurate in regard to the depth of the excavation to be made, or the nature or amount of the work to be done, and that the street for its whole width is to be regulated and graded, where required, in accordance with the plan and profile of the said street, * * * on file in the Bureau [304]*304of Street Improvements.” He also expressly agreed in his contract that “ A City Surveyor will be employed by the parties of the first part (the city) to see that the work is completed in conformity to the profile and to ascertain and certify the quantity of work done. Said surveyor, at the request of the contractor, will be directed to designate and fix grades for his guidance during the progress of the work, without charge, provided that the said parties of the first part shall not be liable for any delay or for any errors of said surveyor in giving such grades, and said surveyor shall be considered as the agent of the contractor so far as giving such grade is concerned, and not the agent of the City of New York.” By the contract the contractor agreed that he would regulate and grade the street in accordance with the plans and specifications, and the map and profile on file, and for the purpose of determining whether he was performing his work in accordance with -his contract, he had the right to employ a surveyor, at his own expense, or he could, without expense, if he saw fit, obtain the services of the city surveyor, but if he relied upon the latter, he expressly agreed that the city should “ not be liable for any delay or for amy errors, of said surveyor in giving such grades,” and that in case services were rendered by the city surveyor, he should be considered the agent of the contractor and not the agent of the city.

When the contractor commenced work, according to his own testimony, he found certain stakes set, indicating, as he supposed, the center line of the street, and, assuming that they were correctly set, he prosecuted his work for several days according to them, when one Grassnock appeared, wrlio informed him that he was an assistant to one Slater, the city surveyor, who had charge of the grading of that street; that Grassnock changed the stakes which he found set when he commenced work, and he thereafter worked according to the stakes set by Grassnock ; that he subsequently employed a surveyor, at his own expense — just when the record fails to disclose — who informed him sometime in July, 1890, that the stakes set by Grassnock did not correctly indicate thé center or grade line of the street, and he thereupon conveyed such information to the superintendent of public mprovements, who, in turn, directed him to proceed with the work in accordance with the grade lines and stakes to be given by Slater, the city surveyor; that he thereupon saw the [305]*305city surveyor and requested him to indicate the center and grade lines, which he did by moving the stakes set by Grassnock several inches to the west.

Free access — add to your briefcase to read the full text and ask questions with AI

Becker v. City of New York, 53 A.D. 301, 65 N.Y.S. 899, 1900 N.Y. App. Div. LEXIS 1918 (N.Y. Ct. App. 1900).

53 A.D. 301 (Becker v. City of New York) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Becker v. City of New York
78 N.Y.S. 1064 (Appellate Division of the Supreme Court of New York, 1902)