Becker v. City of Milwaukee

99 N.W.2d 804, 8 Wis. 2d 456
CourtWisconsin Supreme Court
DecidedDecember 1, 1959
StatusPublished
Cited by5 cases

This text of 99 N.W.2d 804 (Becker v. City of Milwaukee) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Becker v. City of Milwaukee, 99 N.W.2d 804, 8 Wis. 2d 456 (Wis. 1959).

Opinion

Fairchild, J.

Liability of the plumbing contractor. In the course of performing work for the owner of property abutting West Villard avenue, Wichman was required to dig a trench across the westbound roadway. He secured a permit from the city to do so, which, in turn, required him to fill the trench in compliance with certain specifications. After the fill was completed, a city inspector looked at it and approved it. Wichman claims that the approval constituted acceptance by the city, and relies upon a rule that an independent contractor is relieved from responsibility to persons for injuries suffered by them after he has completed his work and it has been accepted by his principal. Delaney v. Supreme Investment Co. (1947), 251 Wis. 374, 382, 29 N. W. (2d) 754.

The suggestion that this rule applies to the present case must be based upon the assumption that Wichman’s rela *461 tionship to the city was that of independent contractor to principal. That was doubtless the relationship between Wich-man and the property owner, but the relationship to the city was essentially different. Wichman’s work was not performed for the benefit of the city. The public had the right to use the roadway, and when the city granted the permit, it was temporarily limiting that right, and permitting the creation of a condition which would be dangerous if not properly restored. The city was acting primarily as a unit of government, protecting the interests of the traveling public in the safe use of the highway and of the property owner seeking a utility connection, as well as its own interests because of its duty to maintain its streets. Negligence in excavating and filling would directly endanger the safety of the traveling public, as well as burden the city. Under the theory of defendant Wichman, the approval of the city inspector would terminate any right of an injured member of the public to recover from the contractor for injuries caused by the contractor’s negligence. We can see no sound policy reason for such a result.

One who lawfully makes an excavation in a public highway, but negligently fails to fill it properly, is liable to a traveler who is injured as a result. Zimmer v. Schmitt (1918), 167 Wis. 430, 167 N. W. 739. See also Ptak v. Kuetemeyer (1924), 182 Wis. 357, 196 N. W. 855, 197 N. W. 363; Cummings v. Nelson (1933), 213 Wis. 121, 250 N. W. 759.

The trench excavated by Wichman’s employees had been 12 feet deep, and three feet wide. The street at that point consisted of two gravel or black-top roadways approximately 20 feet wide, with a center plot between them. The trench ran from a point in the center plot to a building site on the north side of the street, crossing the roadway for westbound traffic. After laying the pipe, the Wichman employees had inserted filling material in the trench, leaving it so that the surface of the fill was just a little bit higher than the surface *462 of the roadway. During the month of January, 1957, the fill sank so that for several weeks, there was a depression about six inches deep, and about three feet wide where the trench had been. The depression extended the entire width of the westbound roadway. On January 20th and 21st, there was thawing weather, and some rain. On the evening of January 21st, a Transport Company bus, not driven by plaintiff, became stuck with its front wheels in the hole. Witnesses estimated the depth of the hole at that time as between two and a half and three feet, filled with water and mud. Partial repairs were made by an employee of the city that night, but at the time of plaintiffs accident on the morning of January 22d, the depth of the hole was estimated at from 15 to 20 inches, and its width at three feet.

The record contains testimony by engineers that if the trench had been filled with acceptable materials and properly compacted according to specifications, the fill could not possibly have settled more than a few inches within the time which had elapsed. Thus, there is sufficient evidence to support the jury’s finding that Wichman’s employees were negligent in filling the trench.

The reason stated by the circuit court for directing a verdict in favor of Wichman was that because the fill sunk after the city approved of it, and plaintiff’s injuries occurred before the city gave the contractor any notice of the sinking, Wichman could not, as a matter of law, be liable for the defect in the street. Wichman’s liability to plaintiff would not be based, however, upon a failure to introduce further fill after the original fill commenced to settle, but upon the negligence of his employees in failing to fill the excavation properly in the first place. “It is no excuse that one who has created a peril did not intend or expect an injury to result therefrom; every person is held to a knowledge of the natural and probable consequences of his acts.” 38 Am. Jur., Negligence, p. 667, sec. 24.

*463 It follows that Wichman was not entitled to a directed verdict and that the complaint against him could properly be dismissed only if the verdict supported a judgment of dismissal.

Causal negligence of plaintiff. Plaintiff asserts that there is no credible evidence to support the jury’s findings that he was causally negligent as to speed, lookout, and management and control, and that, in any event, there was duplicity as to the findings of negligence as to lookout and management and control. We disagree.

West Villard avenue ended at Eighty-Fourth street, and the area was apparently newly developed. There had been recent construction, and the street west of Seventy-Seventh street was described as being somewhat bumpy, very bad, and having quite a few holes. After the Transport Company bus became stuck in front of 8140 West Villard in the evening of January 21st, a city police officer was called, and another employee of the city made temporary repairs that night. He testified that he inserted some fill for a length of about 10 feet, and put lighted barricades on each end, showing that the ends were hazardous, and that traffic was allowable through the middle.

Shortly after 6 a. m. on January 22d, plaintiff commenced a bus run toward a destination at Eighty-Third and West Villard. Traveling on West Villard, he stopped at Eighty-First street to discharge his only passenger. He started up again, and had just reached a speed of 15 to 18 miles per hour, when he noticed a puddle of water all the way across the roadway. He testified that he could remember nothing more until he found himself on the floor of the bus after it had stopped; that he tried to “jump the brake” when he hit the hole, but thought he did not get there. The front wheels of the bus went into the hole, and there is testimony by another witness that the front of the bus rested on the pavement, although plaintiff could not remember whether the *464 front wheels had come out of the hole again before the bus stopped. Pie was able, with some difficulty, to get the bus on its way under its own power. It was about 225 feet from the bus stop at Eighty-First street to the mudhole. The accident occurred at about 6:45 a. m., and it was foggy and still dark.

Plaintiff regularly drove a bus over this same route.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Graci v. Damon
374 N.E.2d 311 (Massachusetts Appeals Court, 1978)
Vincent v. Pabst Brewing Co.
177 N.W.2d 513 (Wisconsin Supreme Court, 1970)
Vargas v. Tió
87 P.R. 248 (Supreme Court of Puerto Rico, 1963)
Agosta Vargas v. Tió
87 P.R. Dec. 262 (Supreme Court of Puerto Rico, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
99 N.W.2d 804, 8 Wis. 2d 456, Counsel Stack Legal Research, https://law.counselstack.com/opinion/becker-v-city-of-milwaukee-wis-1959.