Beck v. Commonwealth Edison Co.

781 F. Supp. 1374, 1992 U.S. Dist. LEXIS 397, 1992 WL 5494
CourtDistrict Court, C.D. Illinois
DecidedJanuary 14, 1992
DocketNo. 88-3302
StatusPublished

This text of 781 F. Supp. 1374 (Beck v. Commonwealth Edison Co.) is published on Counsel Stack Legal Research, covering District Court, C.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beck v. Commonwealth Edison Co., 781 F. Supp. 1374, 1992 U.S. Dist. LEXIS 397, 1992 WL 5494 (C.D. Ill. 1992).

Opinion

[1375]*1375OPINION

RICHARD MILLS, District Judge:

Diversity.

Can a defendant in a diversity case add additional non-diverse parties to a pending federal case by virtue of a third-party complaint for contribution and indemnity?

Simply put: no.

I. Facts

Gilbert Beck — the Plaintiff and a resident of Missouri — was employed by Technical as an insulator and was working on the construction of a power plant for Commonwealth Edison, an Illinois resident. Commonwealth Edison had also contracted with Thiessen to perform asbestos removal and insulation work. While Beck was working on top of various pipes above the ground at the construction site, he slipped and fell resulting in permanent injuries to his back. Based on diversity of citizenship, Beck brought suit in federal court against Commonwealth Edison pursuant to the Illinois Structural Work Act, Ill.Rev.Stat. ch. 48, ¶¶ 60-69, and common law negligence.

Subsequently, Commonwealth Edison filed a third-party complaint against Technical and Thiessen, pursuant to the Illinois Structural Work Act, Contribution Among Joint Tortfeasors Act, Ill.Rev.Stat. ch. 70, ¶ 301 et seq. and common law principles of negligence, because Beck was employed by Technical and it and Thiessen were in charge of the construction work at the plant. Commonwealth Edison, Technical and Thiessen are all residents of Illinois and the complaint did not plead any independent basis for federal jurisdiction.

Technical filed a motion to dismiss Counts III and IV. contending that this Court lacked jurisdiction over the claim since the parties were not diverse. The Magistrate Judge submitted his recommendation that Technical’s motion to dismiss should be allowed, and after reviewing the parties’ objections to the recommendation, this Court adopted it.

Subsequently, Commonwealth Edison filed its motion for reconsideration due to an apparent conflict between this Court’s decision and the Peoria division’s ruling in Vallero v. Burlington Northern R.R. Co., 749 F.Supp. 908 (C.D.Ill.1990). Also, Theissen filed a motion to dismiss Counts I and II of the third-party complaint for lack of jurisdiction.

The Court first observes that there is no reference in the Federal Rules of Civil Procedure to a “motion to reconsider.” The closest provisions in the rules to such a motion are Rule 59(e) (Motion to Alter or Amend a Judgment) and Rule 52(b) (Amendment). Both rules provide that the motion must be made within “10 days after the entry of judgment.” Judgment was entered on March 19, 1991 and Commonwealth Edison failed to file its motion to reconsider within the 10 dáy limit. Nevertheless, because of the apparent conflict within this district and the Seventh Circuit, this Court will consider the motion despite its untimeliness. Furthermore, because this Court’s decision regarding the motion to reconsider will directly affect its ruling on Thiessen’s motion to dismiss, this Court has decided to consolidate those two motions for the purposes of this opinion.

Both Technical and Thiessen contend that the third-party complaint should be dismissed because the Supreme Court decision in Finley v. United States, 490 U.S. 545, 109 S.Ct. 2003, 104 L.Ed.2d 593 (1989) precludes the application of pendent and ancillary jurisdiction to claims and parties where no independent basis for federal jurisdiction exists. Commonwealth Edison asserts that Finley is only . applicable to claims brought pursuant to the Federal Tort Claims Act. Furthermore, even if Finley does apply, this case is distinguishable in that the plaintiff in Finley was attempting to add defendants to which no independent basis for federal jurisdiction existed, whereas Commonwealth Edison seeks to add third-parties in order to give effect. to any potential judgment of the Court, which is permissible under Finley.

II. Analysis

Federal courts are courts of limited jurisdiction.

[1376]*1376They are empowered to hear only those case that: 1) are within the judicial power of the United States as granted under Article III, section 1 of the Constitution, and 2) have been entrusted to them by a jurisdictional grant by Congress. Finley, at 548, 109 S.Ct. at 2006. Federal courts have original jurisdiction in all civil actions involving parties of diverse citizenship and where the amount in controversy exceeds $50,000.1 28 U.S.C. § 1332. Once an action is commenced in federal court, Fed. R.Civ.P. 14(a) allows a defending party to file a third-party complaint against an individual who is not a party to the action who may be liable to the defending party for the plaintiffs claim.

For many years, courts applied ancillary and pendent jurisdiction to third party claims brought pursuant to Fed.R.Civ.P. 14 when an independent basis for federal jurisdiction was lacking. Community Coffee Co. v. M/S Kriti Amethyst, 715 F.Supp. 772 (E.D.La.1989). The doctrine of ancillary jurisdiction permits a court that has jurisdiction over the principal claim to also adjudicate state claims arising out of the same aggregate of facts which are the subject of the federal claim. Owen Equipment and Erection Co. v. Kroger, 437 U.S. 365, 98 S.Ct. 2396, 57 L.Ed.2d 274 (1978).

Pendent jurisdiction has two components: “pendent-claim” jurisdiction and “pendent-party” jurisdiction. Harbor Insurance Co. v. Continental Bank Corp., 922 F.2d 357 (7th Cir.1990). The Supreme Court has defined pendent-claim jurisdiction as the “jurisdiction over non-federal claims between parties litigating other matters properly before the court.” Finley v. United States, 490 U.S. 545, 548, 109 S.Ct. 2003, 2006, 104 L.Ed.2d 593 (1989). Pendent-party jurisdiction has been defined as the “jurisdiction over parties not named in any claim that is independently cognizable by the federal court.” Finley, at 549, 109 S.Ct. at 2006.2

The recent Supreme Court decision in Finley v. United States effectively eliminates virtually all nonstatutory pendent-party and ancillary jurisdiction. In Finley, the plaintiff brought suit in federal court against the FAA under the Federal Tort Claims Act (FTCA). Almost one year later, the plaintiff moved to amend her complaint by adding claims against other defendants for which no independent basis for federal jurisdiction existed. The district court granted the motion and asserted pendent jurisdiction over the additional claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Mine Workers of America v. Gibbs
383 U.S. 715 (Supreme Court, 1966)
Aldinger v. Howard
427 U.S. 1 (Supreme Court, 1976)
Owen Equipment & Erection Co. v. Kroger
437 U.S. 365 (Supreme Court, 1978)
Finley v. United States
490 U.S. 545 (Supreme Court, 1989)
Vallero v. Burlington Northern Railroad
749 F. Supp. 908 (C.D. Illinois, 1990)
Community Coffee Co., Inc. v. M/S Kriti Amethyst
715 F. Supp. 772 (E.D. Louisiana, 1989)
Fidelity & Deposit Co. v. C & a Currency Exchange, Inc.
738 F. Supp. 302 (N.D. Illinois, 1990)
Aetna Casualty & Surety Co. v. Spartan Mechanical Corp.
738 F. Supp. 664 (E.D. New York, 1990)
Ryan v. Cosentino
776 F. Supp. 386 (N.D. Illinois, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
781 F. Supp. 1374, 1992 U.S. Dist. LEXIS 397, 1992 WL 5494, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beck-v-commonwealth-edison-co-ilcd-1992.