Bechard v. Amey

136 A. 370, 82 N.H. 462, 1926 N.H. LEXIS 58
Supreme Court of New Hampshire·Decided December 7, 1926·Published·Cited by 8 cases

Opinion

*464 Branch, J.

The defendant at the trial asserted and reasserted in various ways his position that the plaintiff’s rights were strictly limited by the terms of the written contract. This contention was the basis of exceptions to evidence, of motions for a nonsuit and a directed verdict, of requests to charge the jury and of the motion to set aside the verdict. A decision upon the fundamental question thus presented will therefore go far toward disposing of the numerous exceptions which appear in the recor’d.

The defendant contracted to pay the plaintiff for cutting and hauling the logs on a certain lot at the rate of $10 per thousand feet board measure. The point in dispute between the parties was the quantity of logs delivered by the plaintiff at the defendant’s mill. The plaintiff sought to prove by a survey of the logs made at the time when they were delivered that he cut and hauled 1,408,086 board feet. The actual report of this survey was 1,225,961 board feet, but it appeared that in making this computation the surveyor allowed 115 cubic feet to 1,000 board feet. The plaintiff claimed that under the New Hampshire rule (P. L., c. 167, s. 5) the computation should have been made on the basis of 100 cubic feet to 1,000 board feet, and that he was therefore entitled to add fifteen per cent to the surveyor’s return. The defendant sought to prove that the lumber manufactured from the logs delivered by the plaintiff, as .shown by a survey made at the mill after it was sawed, amounted only to 1,091,733 board feet, and contended that the plaintiff could recover only for this amount by reason of the clause in the contract which reads as follows: “Scale of the manufacturer and the owner, of lumber at the brow of the mill shall be final and binding on both parties and is to determine the amount delivered by the ■contractor.”

The defendant introduced evidence that the words “brow of the mill” mean “the tail of the mill or where the lumber comes out,” and although it may be doubted whether this is the accepted meaning of the phrase among lumbermen, the plaintiff did not question the interpretation placed upon it by the defendant. It was in fact conceded by the plaintiff that the clause of the contract above set forth had reference to the measurement of the manufactured lumber as it came from the saw.

With this definition of terms in mind, the meaning and effect of the above provision is not doubtful. The plaintiff agreed that the quantity of logs delivered by him should be determined by the scale •of the manufactured lumber as it came from the mill, and unless *465 some legal ground of relief from this stipulation is established, he is bound by it.

The plaintiff seeks to avoid the effect of this clause upon four different grounds as follows: 1. That no separate scale of his logs was kept at the mill. 2. That the mill scale was fraudulent. 3. That the defendant waived his right to insist upon the mill scale. 4. That the plaintiff was entitled to rescind the contract and recover upon a quantum 'meruit.

These four claims of the plaintiff will be considered in order.

1. It was conceded by the defendant that no separate mill scale of the plaintiff’s logs was kept and that a relatively small number of logs hauled by three other contractors, amounting to about 156,354 feet, were mixed with the plaintiff’s logs before they were sawed. These facts were well known to the plaintiff, as appears by the following excerpt from his testimony upon direct examination: “Q. Well, did somebody else outside of your crew haul logs? A. No, there was n’t any other — Oh, Fred Amey. Q. Did anybody else haul? A. John Laroche. Q. Did he haul separate from you? A. He hauled separate, but it was rolled onto the slip with mine. Q. Well, didn’t Amey have another contractor, Arthur Laroche? A. Yes. . . . Q. Now, when the mill was running, you may state whether Laroche’s teams and your teams hauled onto the rollway and his logs were mixed with yours? A. Yes, sir. Q. And did you speak to Mr. Cook about it? A. Yes. Q. What did you say to him? A. I asked him how they were going to keep it separate so that I could have mine scaled and he have bis. Q. What did he say? A. He was going to take a hundred feet for Laroche, and I would have the rest. Q. What do you mean by a hundred feet? A. Why, a hundred cubic feet. Instead of taking a thousand feet, he took eleven hundred.”

From this testimony, which evidently had reference to the mill scale, it is plain that the plaintiff knew during the progress of the work not only that no separate scale of his logs was being kept, but that the defendant proposed to determine the amount delivered by the plaintiff by deducting from the mill scale the amounts hauled by other contractors. There was no evidence that he then objected to this method of computation.

A complete scale of all the lumber manufactured at the mill was kept, and a preliminary scale of the quantity of logs delivered by each contractor was also kept, as will more fully appear hereafter. It would therefore seem that all the data necessary to a computa *466 tion of the quantity delivered by the plaintiff upon the basis of the mill scale were available. The total mill scale amounted to 1,248,087 board feet. Clearly, the fact that other logs were added to his would not justify the plaintiff in claiming more than the total mill scale, as he does in this case. The mill scale at least fixed the maximum quantity of logs for which the plaintiff could claim compensation. From this maximum some deductions ought obviously to be made on account of logs hauled by other contractors. The proper amount of such deductions was a question of fact for the jury,' and the evidence furnished an adequate basis for a decision upon it.

Since the total amounts of the preliminary scale and the mill scale were in evidence, it would have been easy to compute the percentage of shrinkage upon the whole lot and distribute it among the various contractors in proportion to the amounts delivered by each, according to the preliminary scale. There was also conflicting evidence upon the question whether the plaintiff’s logs were of such a character that they would shrink more or less than those drawn by other, contractors. Upon all this evidence it would' have been possible for the jury to determine how much should be deducted from the total mill scale on account of logs furnished by other contractors, and the remainder would represent with substantial accuracy the quantity of the plaintiff’s logs.

The plaintiff’s contention that he was not bound by the mill scale, because no separate scale of his logs was kept, must therefore be overruled.

2. Plaintiffs claim that the mill scale was fraudulent was not set up in his pleadings and was first suggested during the discussion of .a question of evidence at the trial. It does not appear to have been seriously pressed by the plaintiff during the remainder of the proceedings,, and the presiding justice did not submit it to the jury as an issue in the case. It cannot avail the plaintiff now because there was no evidence to support it.

The testimony upon which the plaintiff now relies as evidence of fraud may be summarized as follows: (a) The testimony of two witnesses that the preliminary scale was tested while the mill was in operation and that it overran,

Free access — add to your briefcase to read the full text and ask questions with AI

Bechard v. Amey, 136 A. 370, 82 N.H. 462, 1926 N.H. LEXIS 58 (N.H. 1926).

136 A. 370 (Bechard v. Amey) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Shafmaster v. Shafmaster
642 A.2d 1361 (Supreme Court of New Hampshire, 1994)
Mariotti v. Moore Business
First Circuit, 1993
Abbadessa v. Moore Business
First Circuit, 1993
Plymouth Village Fire District v. New Amsterdam Casualty Co.
130 F. Supp. 798 (D. New Hampshire, 1955)
White v. Brown Co.
159 A. 124 (Supreme Court of New Hampshire, 1932)
Billings v. Missoula White Pine Sash Co.
292 P. 714 (Montana Supreme Court, 1930)
Cavanaugh & McCaffrey, Inc. v. Barnard
142 A. 700 (Supreme Court of New Hampshire, 1928)