Beaver Engineering & Contracting Co. v. City of New York

139 Misc. 751, 249 N.Y.S. 198, 1931 N.Y. Misc. LEXIS 1212
CourtNew York Supreme Court
DecidedApril 9, 1931
StatusPublished

This text of 139 Misc. 751 (Beaver Engineering & Contracting Co. v. City of New York) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beaver Engineering & Contracting Co. v. City of New York, 139 Misc. 751, 249 N.Y.S. 198, 1931 N.Y. Misc. LEXIS 1212 (N.Y. Super. Ct. 1931).

Opinion

Hammer, J.

The plaintiff corporation entered into contract No. 84069 with the defendant city of New York through its commissioner of water supply, gas and electricity. The contract was “For furnishing, delivering and laying water mains and appurtenances, transferring taps, rearranging connections and setting valves and hydrants on existing mains in Avenue A, Amsterdam, Lexington, Madison, Payson and Second Avenues, Allen, East 30th, East 40th, West 102nd, West 44th, West 45th, West 65th, West 158th and West 215th Streets, Borough of Manhattan.”

The National City Realty Corporation Was originally a defendant. As to it, on trial the action was discontinued.

There are two causes of action in the complaint. The second cause of action was withdrawn at the trial. The contract was for the “ lump ” sum of $34,630. The first cause of action is for the sum of $2,198.88, with interest, for the cost of installing fifty-two house service connections claimed by the plaintiff not to have been included in the contract and to have been ordered by the city’s engineer under his claim that it was included in the contract and done by the plaintiff under protest.

[752]*752The commissioner advertised for bids prior to May 20, 1927, for a contract under the above title. All the work called for under the contract, including the work in dispute, has been performed and a certificate of completion has been issued. This certificate plaintiff claims is false, untrue and not made in good faith and under a misconstruction of the terms of the contract in that it did not certify the sum of $2,198.88 for the work in dispute.

The contract contains the following provision:

2. The proposal for bids, bid, specifications, and the drawings described in the specifications and the bond, are hereby made a part of this contract with like effects as if herein set out in full, and the term ‘ contract ’ as herein used includes all of said instruments. All work and materials mentioned in the specifications and not shown on the drawings, and all work and materials shown on the drawings and not mentioned in the specifications, shall be furnished, performed and done as if the same were both mentioned in the specifications and shown on the drawings.”

The proposal for bids provided:

8. The number and sizes of straight pipe, special and valve box castings, valves and hydrants to be furnished by the Contractor under this contract are as listed herein. Prior to their fabrication, however, the Department shall have the right of modifying the fist of special castings without increasing their total weight, either by varying the number and kind given or by substituting other castings for same; but such variation or substitution will not be made for more than ten per cent (10%) of the total weight of special castings listed. Any additional straight castiron pipe, special and valve box castings, valves and hydrants required to complete the work called for under the contract will be furnished to the Contractor by The City on the ground at one of the Department yards located in the Borough in which the work under this contract is to be done, unless otherwise noted on the drawings. The cost of loading, hauling and unloading the material shall be included in the lump sum bid. [Here follows a fist of cast iron pipes, special castings, etc.]

13. The drawings accompanying the specifications and the work to be done are referred to in the contract General Provisions for Water Main Specifications/ Section 1, as follows:

“ ‘ The work to be done includes furnishing and delivering all the labor and materials necessary or proper to lay and construct the water mains and appurtenances in the streets or places mentioned in the proposal and shown on the drawings signed .by the Chief Engineer, and numbered 18346-X herewith made a part hereof. During the progress of the work the City may furnish additional [753]*753drawings explanatory of those hereinbefore mentioned, which will thereupon become a part hereof.’

“ 14. Bidders shall submit a lump sum bid for furnishing all the material listed in section 8 herein and for furnishing all other materials and all labor required to lay and install all the mains and appurtenances shown on the contract drawings, complete, including the removal of any mains or appurtenances where called for. The lump sum bid shall include the cost of loading and unloading and of hauling back all materials not used in the work to one of the yards of the Department of Water Supply, Gas and Electricity. Unused material furnished by the City shall be returned to the yard from which it was originally taken by the Contractor.

“15. The quantities of the work to be done and the materials to be furnished as herein estimated and as shown on the drawings are approximate only, and The City shall not be held responsible that any of the quantities shall strictly obtain in the construction of the work. Bidders must judge for themselves as to such quantities and as to the character of the work to be done and the materials to be furnished and the other circumstances affecting the cost of the performance of the work.

“ Bidders are particularly cautioned against the submission of a bid before making a personal examination of the location proposed for the work under the contract, and familiarizing themselves with all existing conditions and with all difficulties to be met with during construction.

“ Information is given to assist bidders in reaching their own conclusions as to the requirements of the contract to be entered into.”

A copy of the plan (No. 18346-X) was furnished to the contractor. There is a note on this plan and copy reading as follows:

“ All house services (about 160) shall be transferred by the contractor from the mains shown to be abandoned or removed to the new parallel mains. * * *

“ Locations of new and existing mains and appurtenances: The location of new mains, valves, hydrants and connections shown on the plan and arrangement of the connections are diagramatic and approximate only; the exact locations and arrangements will be given by the engineer during the progress of the work.

“ The locations of the existing mains which are to be abandoned and from which services are to be transferred as shown on the plan are also approximate only; the lengths of the new service connections will vary accordingly, and no extra compensation will be allowed to the contractor for the lengths of services in excess of [754]*754that which may be indicated or inferred from the locations of the mains as shown on the plan.”

On the plan and copy the six-inch main to be abandoned on Allen street, West Forty-fourth street, West Forty-fifth.street and East Thirtieth street is indicated by a broken line and existing parallel mains on those same streets are indicated by a thin unbroken line. The new mains to be laid by the contractor on other streets covered by the contract are shown on the same plan and copy by a heavy straight line. The specifications, so far as applicable, read as follows:

Specifications for Lead Pipe for Extending House

Service Connections

“ Standard Water Main Specifications, Form No. IS

‘ Dated January 1, 1925

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lentilhon v. . City of New York
77 N.E. 1184 (New York Court of Appeals, 1906)
Borough Construction Co. v. City of New York
93 N.E. 480 (New York Court of Appeals, 1910)
Lentilhon v. City of New York
102 A.D. 548 (Appellate Division of the Supreme Court of New York, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
139 Misc. 751, 249 N.Y.S. 198, 1931 N.Y. Misc. LEXIS 1212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beaver-engineering-contracting-co-v-city-of-new-york-nysupct-1931.