Beard v. United States

67 F. Supp. 963, 110 Ct. Cl. 1, 1946 U.S. Ct. Cl. LEXIS 4
CourtUnited States Court of Claims
DecidedOctober 7, 1946
DocketNo. 45552
StatusPublished
Cited by2 cases

This text of 67 F. Supp. 963 (Beard v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beard v. United States, 67 F. Supp. 963, 110 Ct. Cl. 1, 1946 U.S. Ct. Cl. LEXIS 4 (cc 1946).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

Plaintiff is the receiver of the Becording and Computing Machines Company. He sues to recover amounts alleged to be due on contracts between defendant and the company of which he is receiver for the manufacture of munitions during World War I. The issue presented is whether or not a settlement contract entered into on August 27, 1919, bars recovery.

This contract was in final settlement of all of the company’s claims arising out of the termination of the contracts. In fact, all of the contracts which the company had entered into had been consolidated into one, numbered P-14408-1019-C. The contract of settlement was of this consolidated contract.

Under this consolidated contract the defendant had agreed to put up the money for working capital. To supervise its execution an Executive Committee was formed composed of Messrs. Ohmer, Carpenter, and Bippus. Ohmer was president of the company and its sole stockholder except for four directors’ shares; Carpenter was vice-president and general [15]*15manager of the company; and Bippus was the manager of the Dayton office of the Ordnance Production Division of the Army. Bippus was the chairman. This committee was in absolute charge of the affairs of the company.

It was provided that the contract could be terminated at any time the Chief of Ordnance thought the public interests so-required. Pursuant to this provision, after the Armistice on November 11, 1918, defendant ordered the company to suspend some operations under the contract and to reduce others, and all operations thereunder ceased about June 25, 1919, or shortly thereafter.

Upon termination defendant had agreed to pay the company all costs it had incurred in the carrying out of the contracts plus 10 .percent and less all sums that had been advanced for working capital. The basis for determining costs was set out in the contract.

Following the partial termination mentioned above the company submitted a plan for settlement, on February 5, 1919. Later, on June 12, 1919, the parties agreed on a plan which was incorporated into a contract bearing this date. Under this the defendant agreed to pay the company $500,000 in cash and such further sum as might be necessary to cover all costs, which were enumerated, plus 10 percent, less advances.

The company, acting through the Executive Comixiittee, then employed one Smethurst, a public accountant, and his firm to prepare a claim. Smethurst prepared the claim and certified it as correct on August 22, 1919. It was then approved by the Executive Committee and by the defendant. Five days later, on August 27, 1919, a final settlement contract was entered into under which defendant agreed to pay the company the amount of. its claim, to wit, $3,751,682.75, less the amount advanced by defendant of $3,443,064.96 plus interest thereon. When the interest was computed it was ascertained that there was a balance due the company of $4,479.63. Later the company, acting through H. J. Linltert, treasurer and a member of its board of directors, submitted a voucher for this amount, and this was paid.

Thus the matter rested until 1923 or 1924, when the defendant asserted a claim against the company for alleged over-payments under the settlement contract. This claim was [16]*16asserted under the following provision contract:

The United States reserves all its rights under the original contract to recover any payments improperly made and to enforce the liability of the Contractor and surety for defects existing at time of delivery to the United States in articles or work done which may hereafter appear.

When the company went into receivership in 1927 the defendant filed a claim for these alleged overpayments with the receiver. Thereupon the receiver had a reaudit made of the company’s books and as a result thereof he now alleges that the company was underpaid.

In order to assert his claim the receiver secured passage of an Act by Congress on September 24,1940 permitting the bringing of this suit. It was filed on September 19,1941, five days before the expiration of the time limit fixed in the Act.

The defendant filed a counterclaim on May 24, 1943, amended March 15, 1946, based, not on the alleged overpay-ments, but on a claim for taxes.

Defendant relies on the contract of settlement to defeat plaintiff’s claim. This contract contains this provision:

* * * The payment of the balance so ascertained shall be in full and final compensation for articles or work delivered, services rendered and expenditures incurred by the Contractor under the original contract and in full satisfaction of any and all claims or demands in law or in equity, which the contractor, his successors, representatives, agents or assigns, may have growing out of or incident to said original contract; and said contractor hereby expressly agrees that such settlement when made shall constitute a complete termination of every question or claim, legal or equitable, liquidated or unliquidated by or on behalf of the contractor, pertaining to or growing out of said original contract.

In order to avoid the bar of this provision, plaintiff alleges in his petition that this contract was executed by the secretary of the company while he was under the domination and control of the representatives of the United States and without authority of the board of directors of the company, or of its president and principal stockholder. It is further alleged that it was executed under the mistaken belief that [17]*17the original contract, P-14408-1019-C, had not been superseded by the partial settlement contract entered into on June 12, 1919.

On the taking of the testimony plaintiff insisted that Pierson, who executed the contract of August 27, 1919 on behalf of the company as its secretary, was not secretary at the time of the execution of the contract, having been previously discharged by the President, which action was confirmed by resolution of the board of directors on the same day the contract was executed. However, he makes no such claim in his brief nor does he otherwise insist upon the claim made in the petition that the contract was executed without authority.

He now claims in his brief, first, that the contract was executed under duress and, secondly, that it was executed under a mistake as to the proper interpretation of the terms of the contracts and as to the facts underlying the claim presented by the company.

In his brief plaintiff further insists that the Act of Congress conferring jurisdiction on this court to hear and determine the company’s claim waived the bar of the above-quoted provision of the contract of August 27, 1919.

This last proposition is manifestly incorrect. The Act conferring jurisdiction on this court reads as follows:

That jurisdiction is hereby conferred upon the Court of Claims of the United States to hear, determine, and render judgment upon the claim or claims of the Recording and Computing Machines Company, of Dayton, Ohio, arising out of a series of transactions, contracts, and provisional adjustments between said Recording and Computing Companies, of Dayton, Ohio, and the War Department for the manufacture of ordnance materials, equipment, instruments, and so forth, between the years 1916 and 1920, inclusive, and suit on such claims shall be instituted within one year from the date of approval of this Act.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beard v. United States
76 F. Supp. 715 (Court of Claims, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
67 F. Supp. 963, 110 Ct. Cl. 1, 1946 U.S. Ct. Cl. LEXIS 4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beard-v-united-states-cc-1946.