Beane Plumbing & Heating Co. v. D-X Sunray Oil Co.

92 N.W.2d 638, 249 Iowa 1364, 2 A.F.T.R.2d (RIA) 5923, 1958 Iowa Sup. LEXIS 387
CourtSupreme Court of Iowa
DecidedOctober 14, 1958
Docket49515
StatusPublished
Cited by6 cases

This text of 92 N.W.2d 638 (Beane Plumbing & Heating Co. v. D-X Sunray Oil Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beane Plumbing & Heating Co. v. D-X Sunray Oil Co., 92 N.W.2d 638, 249 Iowa 1364, 2 A.F.T.R.2d (RIA) 5923, 1958 Iowa Sup. LEXIS 387 (iowa 1958).

Opinion

PetersoN, J.

On March 25, 1955, appellant’s predecessor in interest, Mid-Continent Petroleum Corporation, entered into a written agreement with Bride Construction Company of Sioux City for erection of a service station upon property in Sioux City, hereinafter described, and later acquired by appellant. Appellant assumed all obligations of the agreement. The con *1367 tract price was $22,904. The construction of the station was completed in October 1955.

Prior to January 1,1956, appellant paid Bride Construction Company $19,462 on the contract price, leaving unpaid the sum of $3442.

Bride Construction Company failed to pay several subcontractors. Most of them are appellees herein. The subcontractors filed liens, but not within sixty days from the completion of their work. Consequently, their liens would only attach as against appellant’s property to the extent of any unpaid balance under the contract. Sections 572,10 and 572.11, 1954 Iowa Code.

The liens were filed on the dates stated, and in following amounts: Charles Ellis Bourrett, March 30, 1956, $1231; Beane Plumbing & Heating Company, April 10, 1956, $646; Hooker Glass & Paint Manufacturing Company, May 3, 1956, $610; C. E. Hardy, May 17, 1956, as a subcontractor, $557; as a principal contractor for some extra work, $412.30. All above named” subcontractors gave written notice to appellant as to filing of the liens, as provided by statute.

September 4, 1956, plaintiff filed petition for foreclosure of its mechanic’s lien. September 24, 1956, C. E. Hardy filed petition for foreclosure of his mechanic’s lien. Charles Ellis Bourrett and Hooker Glass & Paint Manufacturing Company filed answers and cross-petitions in one or both of the cases for foreclosure of their mechanic’s liens. Appellant filed answer and cross-petition to quiet title against all adverse parties. Under Order of Court the two mechanic’s lien cases were consolidated for trial. The issues raised by the answering defendants and cross-petitioners were also consolidated for trial, in order that all issues as between the various mechanic’s lien holders and appellant could be, and were, tried in one case.

On February 15, 1956, the Internal Revenue Department of the United States made an assessment for social security, unemployment, etc., taxes against Bride Construction Company in the amount of $3361.33. May 4, 1956, the director served notice of levy on appellant to enforce payment of the assessment. Neither the United States of America nor the Revenue Department was served with notice in these cases. They never filed pleadings nor entered appearance.

*1368 On July 21, 1955, appellant entered into written contract with Bride Construction Company for the erection of a service station at Logan, Iowa. The contract price was $24,293. The construction company did not fully complete the contract and in November 1955 appellant expended the sum of $863.77 in completing the station. Prior to that time appellant had paid the contractor $18,090. Deducting- these two items from the contract price leaves $5339.23 that appellant still owed Bride Construction Company. However, within the sixty-day period for filing subcontractors’ liens three liens were filed totaling $10,284.59. If appellant will ultimately have to pay these liens, Bride Construction Company will owe $5345.36 to appellant. It is the theory of appellant that this item more than offsets the $3442 unpaid on the contract at Sioux City, and therefore there is no balance subject to appellees’ liens.

The decree of the trial court held the Logan matter did not enter into the situation and that there was unpaid on the contract for erection of the Sioux City station the sum of $3442. The court established costs and mechanic’s liens as against the real estate of appellant in following order and amounts: First: Costs of the proceeding. Second: Claim of Charles Ellis Bour-rett for $1231. Third: Claim of Beane Plumbing & Heating Company for $646. Fourth: Claim or lien of the United States, if and when the same is established. Fifth: Claim of Hooker Glass & Paint Manufacturing Company for $610. Sixth: Claim of C. E. Hardy for $557 as a subcontractor. The court also held Hardy was a principal contractor as to $412.30, and foreclosed lien as to said amount directly against appellant.

Fullerton Lumber Company, The Haakinson & Beaty Company and Thermoflector Corporation also filed mechanic’s liens. Thermoflector Corporation was never served with a notice and never became a party to the action. Fullerton Lumber Company and The Haakinson & Beaty Company never gave written notice to appellant as to filing of their mechanic’s liens as provided by section 572.11. The trial court properly dismissed their claims, and these three parties are not involved in this appeal.

Appellant urges and relies upon three alleged errors for *1369 reversal: 1. In bolding that there was an unpaid balance of $3442 on the contract from appellant to the contractor. 2. If there was any amount unpaid on the contract to the contractor, which appellant does not concede, it- was covered by the liens of United States of America ; it also urges since Government was not a party, no lien should have been established against appellant’s property. 3. In holding that C. E. Hardy was a principal contractor to the extent of $412.30.

I. The property involved in this action, and as against which mechanic’s liens were established, is described as follows: “S.E. one half of Tax Lot 10 and the S.W. thirteen feet of the S.E. one half of Tax Lot 11, and the S.W. 150 feet of Tax Lot 15, all in Auditor’s Plat of Lots 7, 8 and 9 in Block 59, Block 60, and the South one half of Block 61 in Sioux City East Addition, and Blocks 51 and 52 in Sioux City, Iowa; also being described as the Southwesterly 63 feet of Lot 2, and the Southwesterly 150 feet of Lot 3, in Block 51, of the Original Plat of Sioux City, Iowa.”

With the exception of evidence as to the claim of C. E. Hardy, as a principal contractor, the parties stipulated as to the facts. In addition to $3442 stipulated as balance on Sioux City contract, there was a possible additional item of $220 not settled by the stipulation or any evidence in the case. The trial court reserved jurisdiction for supplemental decree as to this small item. It is not involved in the appeal. In supplemental decree to be entered after this decision has been filed, whatever the trial court holds as to this item shall be final.

There being no question about these figures, the first question in the case is whether or not the possible amount owing by Bride Construction Company to appellant as to the contract for erection of service station at Logan can offset as against the $3442 unpaid on the Sioux City contract.

In connection with the unpaid balance on the Sioux City contract of $3442 the trial court said: “Balance due on this particular contract [Sioux City] fixes the liability of the owner to the subcontractors.” We agree with this conclusion.

We hold the possible balance due from Bride to appellant at Logan cannot be used as an offset against the $3442 for two reasons: A. The record in this case does not establish the *1370

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coplay Cement Co. v. Willis & Paul Group
983 F.2d 1435 (Seventh Circuit, 1993)
Coplay Cement Company, Inc. v. Willis & Paul Group
983 F.2d 1435 (Seventh Circuit, 1993)
Diecke v. Lumber Supply, Inc.
149 N.W.2d 822 (Supreme Court of Iowa, 1967)
Pay-N-Taket, Inc. v. Crooks
145 N.W.2d 621 (Supreme Court of Iowa, 1966)
J. K. & W. H. Gilcrest Co. v. A. & R. Concrete Co.
112 N.W.2d 366 (Supreme Court of Iowa, 1961)
Randall v. Colby
190 F. Supp. 319 (N.D. Iowa, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
92 N.W.2d 638, 249 Iowa 1364, 2 A.F.T.R.2d (RIA) 5923, 1958 Iowa Sup. LEXIS 387, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beane-plumbing-heating-co-v-d-x-sunray-oil-co-iowa-1958.