Beacon Castle Square Building Corporation v. National Labor Relations Board

406 F.2d 188, 70 L.R.R.M. (BNA) 2357, 1969 U.S. App. LEXIS 9199
CourtCourt of Appeals for the First Circuit
DecidedJanuary 24, 1969
Docket7150_1
StatusPublished
Cited by16 cases

This text of 406 F.2d 188 (Beacon Castle Square Building Corporation v. National Labor Relations Board) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beacon Castle Square Building Corporation v. National Labor Relations Board, 406 F.2d 188, 70 L.R.R.M. (BNA) 2357, 1969 U.S. App. LEXIS 9199 (1st Cir. 1969).

Opinion

McENTEE, Circuit Judge.

Beacon Castle Square Building Corporation (Beacon) petitions for review of an order of the National Labor Relations Board dismissing ,a complaint against the respondent union (Local 537). 1 The General Counsel issued a complaint charging Local 537 with violation of the secondary boycott provisions of the Act, § 8(b) (4) (i) and (ii) (B), alleging that this union directed its members to strike a subcontractor in order to force it to cease doing business with the general contractor.

Beacon, a general contractor engaged to build four “high rise” apartment buildings in Boston, 2 subcontracted the plumbing and heating work to the Frank Sullivan Company. On this project Sullivan employed plumbers from Local 12 and pipefitters from Local 537. 3 Sullivan was a party to a collective bargaining agreement with Local 537 which provides in part as follows:

Article VI
Temporary Heat
“1. Pipe fitters shall have jurisdiction over the operation and/or emergency maintenance of all temporary heat work whenever temporary heat is on a building, [sic] structure, or addition thereto, regardless of the source of heat supply.
******
6. It shall be the duty of Job Stewards to report to the Secretary of Local 537 all jobs on which it appears temporary heating will be required.
******
9. Any use of the heating system prior to its completion shall be considered temporary operation, until its formal acceptance by the owner.” 4

In January 1967 the project, and Building 23 in particular, neared completion. The Sullivan Company installed a temporary heating system to facilitate the work of the craftsmen but rather than using Local 537 (pipefitters) in accordance with the contract, it assigned this work to Local 12 (plumbers). When the work on the central heating unit of Building 23 was substantially complete, Beacon’s project manager, one Davis, notified the Sullivan Company and the owner’s architects that he wanted an inspection of the heating system with a view to acceptance by the owner on January 30. In preparation for this Sullivan inspected the system on January 26 and 27 and had it running on the 30th.

During the afternoon of the 30th Russell Campbell, the business agent for Local 537, came to the boiler room of Building 23 where those concerned with the inspection were gathering. Present were Edward Segal, Beacon’s job superintendent, John T. Sullivan, son of the president of the Sullivan Company, and Paul Richard, Sullivan’s pipefitter foreman, who was also a member of Local 537. When he arrived, Campbell asked where the temporary firemen were. Segal answered that since the heating system was substantially complete and was about to be accepted by the owner, there was no need of temporary firemen. Campbell remarked that the system was not complete and could not be accepted until it was 100 per cent complete. He then instructed Richard to drain the water from the hot water heating system and to have his men report at the union office the next morning rather than on the job. Richard did not, however, draw the heating system down and later the *190 same day the owner formally accepted the system.

On February 1, with the strike now in progress, Campbell met with Beacon project manager Davis and John Sullivan. Davis stated that the contract permitted acceptance whenever the heating system was “sufficiently complete and operating automatically,” and that it had in fact been accepted. Campbell refused to consider this, now taking the position that the Sullivan Company’s contract to install heating systems in four buildings was a single undertaking and that the acceptance in regard to Building 23 was an impermissible partial acceptance.

On February 3 there was another meeting at which Campbell, Smith, the union’s International Organizer, and Francis Sullivan were present. At this meeting Francis Sullivan informed Campbell for the first time that Local 12 plumbers had been employed to provide the temporary heat in Building 23. When Campbell confirmed this information, realized that the work remaining on the heating system in this building was very minor and that the tenants had been advised that they could move in, he relented and stated he would get the men back on the job the following Monday morning.

The issue is whether Local 537 was really striking against Sullivan or whether Sullivan was a neutral in a dispute .that actually was between Local 537 and the general contractor. This issue can be resolved by a consideration of two questions: (1) What was the union striking for? (2) Was Sullivan in a position to do anything about it?

The answer to the first question is complicated by the fact that Campbell espoused two different theories which he blandly mixed together. At one point he said that the condition of Building 23 was irrelevant, that the whole job must be considered as one for purposes of acceptance. 5 In the next breath he said that the buildings could be accepted one at a time and that temporary firemen were required only until the particular building was accepted. 6 Then later, exasperatingly, he went back to his orig *191 inal theory. 7 Nor does a reading of the testimony of the other parties to the dispute provide much illumination. 8

The trial examiner, considering this farrago of information, concluded that Campbell “clearly regarded the heating systems in Building 23 and the other three buildings of the project as incomplete both individually and collectively, and as thus requiring Sullivan to hire pipefitter temporary "firemen.” In our opinion there is substantial evidence in the record to support this finding as an overall interpretation and assessment.

The second question to be considered is whether the Sullivan Company could have done anything about Campbell’s demands at that point, i. e., whether the company had the right to control in these circumstances. See Local No. 5, United Association of Journeymen and Apprentices of Plumbing and Pipe Fitting Industry of United States & Canada v. N.L.R.B. (Venneri), 321 F.2d 366 (D.C. Cir.), enforcing 137 N.L.R.B. 828, cert. denied, 375 U.S. 921, 84 S.Ct. 266, 11 L.Ed.2d 165 (1963). We do not think that the Sullivan Company was powerless to act in this situation. It could have put firemen on in Building 23 for whatever time, long or short, they should have remained thereafter. 9 Fulcher, the Sullivan Company could have assured Campbell that firemen would be assigned promptly to the other buildings when they reached the appropriate stages of •completion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NLRB v. Pipefitters
429 U.S. 507 (Supreme Court, 1977)
Sachs v. Local Union No. 48
454 F.2d 879 (Fourth Circuit, 1972)
Danielson v. Painters District Council No. 20
305 F. Supp. 1108 (S.D. New York, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
406 F.2d 188, 70 L.R.R.M. (BNA) 2357, 1969 U.S. App. LEXIS 9199, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beacon-castle-square-building-corporation-v-national-labor-relations-board-ca1-1969.