B.C. Construction Co., Inc. v. Johnson Roberts Associates, Inc.

CourtMassachusetts Appeals Court
DecidedOctober 3, 2025
Docket24-P-627
StatusPublished

This text of B.C. Construction Co., Inc. v. Johnson Roberts Associates, Inc. (B.C. Construction Co., Inc. v. Johnson Roberts Associates, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B.C. Construction Co., Inc. v. Johnson Roberts Associates, Inc., (Mass. Ct. App. 2025).

Opinion

APPEALS COURT

B.C. CONSTRUCTION CO., INC. vs. JOHNSON ROBERTS ASSOCIATES, INC.

Docket: 24-P-627
Dates: March 18, 2025 – October 3, 2025
Present: Massing, Neyman, & Wood, JJ.
County: Middlesex
Keywords: Contract, Interference with contractual relations, Bidding for contract, Construction contract. Municipal Corporations, Contracts. Evidence, Motive. Libel and Slander. Privileged Communication. Practice, Civil, Summary judgment.

      Civil action commenced in the Superior Court Department on June 7, 2021.

      The case was heard by Adam L. Sisitsky, J., on a motion for summary judgment.

      Kevin P. Polansky (Joseph P. Murphy also present) for the plaintiff.

      Stephen J. Orlando for the defendant.

      WOOD, J.  The plaintiff, B.C. Construction Co., Inc. (B.C.), brought this action against the defendant, Johnson Roberts Associates, Inc. (JRA), alleging intentional interference with advantageous business relations and defamation.  A Superior Court judge granted JRA's motion for summary judgment on both counts and entered a judgment dismissing the complaint.  B.C. appeals.  We affirm.

      Background.[1]  In 2013, the city of Everett (Everett) awarded B.C. a contract to renovate and construct an addition to Everett's library building and selected JRA as the project's architect.  At the end of the project, B.C. submitted change orders to Everett, increasing the total project cost.  Separately, JRA offered Everett a $20,000 credit for a dispute unrelated to the change orders.

      In 2019, the town of Dracut (Dracut) hired JRA as the architect for the construction of a new fire station and retained the Vertex Companies, Inc. (Vertex), as its owner's project manager (OPM).  Vertex and JRA worked together to evaluate bids for the fire station project, ultimately identifying B.C. as the lowest bidder.[2]  Vertex sent an e-mail message to the Attorney General's office (AGO),[3] explaining that it had information regarding JRA's problematic history with B.C. in connection with the Everett project, and that Dracut had been informed of other negative experiences with B.C.  In view of that information, Vertex asked whether Dracut had the right to reject B.C.'s bid.  The AGO advised that Dracut should independently gather client reviews of B.C.'s prior projects and, if it found negative reviews, then it should give B.C. the chance to respond.  The AGO confirmed that after taking these steps, Dracut would have the right "to reject a low bidder who is not responsible."  Philip O'Brien, a JRA principal, and Vertex prepared a report for Dracut's building committee summarizing B.C.'s municipal project references and the AGO's e-mail message and ultimately recommending a different bidder for the project.  Dracut's building committee then offered B.C.'s president, Michael Cresta, an opportunity to meet and address the negative project reviews.  Following that meeting, Dracut rejected B.C.'s bid.

      Because of budgeting issues, Dracut had to delay the project and conduct another round of bidding six months later.  After B.C. submitted a new bid for the project as the lowest bidder, JRA again reviewed B.C.'s references and summarized its findings in a report.[4]  JRA reported that it had contacted some of B.C.'s references from the first round of bidding and some new references, which generated a mix of negative and positive reviews.  JRA also identified a reference from an architect reporting that B.C. was "suing [the architect] and the [municipal client] for unpaid changes," and that the municipal client was countersuing B.C. for damages.  Once again, JRA did not recommend B.C. for the project, and Dracut again rejected B.C.'s bid, this time with no offer to discuss the negative reviews.

      In late 2019, as Dracut was completing its second round of bidding, the city of Cambridge (Cambridge) hired JRA as the architect for the construction of a fire station.  After B.C. submitted one of the lowest bids for the project, another JRA principal, Jeffrey Davis, sent an e-mail message to Cambridge's project manager apparently referencing JRA's experience working with B.C. on the Everett project.  Davis's message stated that, "[JRA] worked with [B.C.] in 2013/2014 -- if they weren't the worst, they were among the [two] worst [general contractors] that we have ever worked with.  As such, we really need to talk to current references to understand if they still suck."  Davis worked with a JRA associate, Michael Bellefeuille, to prepare a report summarizing JRA's bid review (Cambridge report), which included client reviews of B.C.'s prior work.  Davis also incorporated information obtained through reference checks and from JRA's previous reports on the Dracut project.  The Cambridge report stated that it appeared "that many of [B.C.'s] recently completed projects may have required formal dispute resolution (including mediation and litigation) in order to complete the project."  Cambridge rejected B.C.'s bid.

      Not all municipalities, however, reached the same conclusion with respect to B.C.  Around the same time as the Dracut and Cambridge projects, the town of Newbury (Newbury) sought bids to build a new police station.  B.C. was the lowest bidder.  Although JRA was not the architect for the Newbury project, Newbury's permanent building committee obtained a copy of one of JRA's reports from the Dracut project, which contained unfavorable information about B.C.  Vertex, which was the OPM on the project, nonetheless found that B.C. was a responsible bidder, and Newbury awarded the job to B.C.

      Discussion.  "The allowance of a motion for summary judgment is appropriate where there are no genuine issues of material fact in dispute and the moving party is entitled to judgment as a matter of law" (quotation and citation omitted).  Williams v. Board of Appeals of Norwell, 490 Mass. 684, 689 (2022).  When a party moves for summary judgment on claims that the opposing party will have the burden of proving at trial, the moving party must demonstrate "that the party opposing the motion has no reasonable expectation of proving an essential element of that party's case."  Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991).  We review a grant of summary judgment de novo.  See Casseus v. Eastern Bus Co., 478 Mass. 786, 792 (2018).

      a.  Intentional interference with advantageous business relations.  To prevail on a claim of intentional interference with advantageous business relations, B.C. must prove that (1) it had an advantageous business relationship with a third party, (2) JRA knowingly induced the third party to forgo the business relations, (3) JRA's interference was improper in motive or means, and (4) B.C. was harmed by the interference.  See Kelleher v. Lowell Gen. Hosp., 98 Mass. App. Ct. 49, 54 (2020), citing Psy-Ed Corp. v. Klein, 459 Mass. 697, 715-716 (2011).  The central question in this appeal is whether there is a genuine dispute of fact as to whether JRA's actions were motivated by an improper motive or means that harmed B.C.

      This turns on the application of Cutting Edge Homes, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Psy-Ed Corporation v. KLEIN HIRSCH
947 N.E.2d 520 (Massachusetts Supreme Judicial Court, 2011)
Downey v. Chutehall Construction Co.
19 N.E.3d 470 (Massachusetts Appeals Court, 2014)
Cavicchi v. Koski
855 N.E.2d 1137 (Massachusetts Appeals Court, 2006)
Casseus v. E. Bus Co.
89 N.E.3d 1184 (Massachusetts Supreme Judicial Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
B.C. Construction Co., Inc. v. Johnson Roberts Associates, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bc-construction-co-inc-v-johnson-roberts-associates-inc-massappct-2025.