Bayou Meto Drainage District No. 1 v. Kochtitzky

272 S.W. 840, 168 Ark. 1157, 1925 Ark. LEXIS 385
CourtSupreme Court of Arkansas
DecidedJune 15, 1925
StatusPublished

This text of 272 S.W. 840 (Bayou Meto Drainage District No. 1 v. Kochtitzky) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bayou Meto Drainage District No. 1 v. Kochtitzky, 272 S.W. 840, 168 Ark. 1157, 1925 Ark. LEXIS 385 (Ark. 1925).

Opinion

McCulloch, O. J.

Appellant is a -drainage district, organized for the purpose of 'constructing a drainage system in a large area in Lonoke County. The plans contemplated 69.8 miles of -ditches, including Bayou Meto for a distance- of twenty-five miles, the main ditch, 22 miles in length, and eleven lateral ditches, and a cut-off ditch, in addition to cleaning and dredging Bayou Meto for a distance of 25 miles to make it part of the system. Appellee was the successful bidder for the work, and entered into a written contract with appellant. The work was begun in the year 1920, and most of the work was completed in the year 1922, and there was a final completion, according to th^. finding-, by the chancery court, on May 1, 1923. This is an action instituted by appellee to recover the balance alleged to be due for work clone under the contract. Appellant answered denying the amount of earned compensation claimed by appellee, and also filed a counterclaim for damages on account of alleged defective work and for delay in completing the improvement.

Tiie contract called for payment for the work on estimates of the engineer, with the retention of twenty per cent, of each item, to 'be held back until completion of the contract. It is agreed by both parties that the aggregate retained percentage was $71,763.17, the controversy arising over additional items for which appellee made claim and over items of damage claimed by appellant in reduction of the amount due from retained percentage. There was a reference made to a master, who was to take testimony and state the account, which was done, and the court, on hearing the exceptions to the master’s report, rendered a decree in favor of appellee for the sum of $96,102.17, and dismissed appellant’s cross complaint for want of equity. There is a small item of $69.48 to be added to the retained percentage, about which there is no controversy except as to allowance of interest thereon. The interest item on that amount is very small, but we see no reason why appellee is not entitled to it.

The first item of any importance claimed by the appellee, in addition to the amount of retained percentage, and which was allowed by the chancery court, is the sum of $9,097.59 for work done on what is termed force account. Section 25 of the specifications reads as follows:

"Force Account. All -work not contemplated or set out in. these plans or specifications, which will be later found necessary to be done, will be done !by the contractor at the actual cost to him, as determined by the engineer, plus 15 per cent. Under this head would come such items as removing and replacing fences, bridges, removing houses, and all other work that cannot he foreseen at this time. Extra work will be paid for only on the written order from the engineer, and should not he undertaken without the engineer’s written order to do so.”

The claim is based on work done in clearing the right of way. The controversy relates to certain sections of the work along Bayou Meto, which is-a deep and wide stream of water with high hanks in some places and low banks in other places. The specifications in regard to clearing reads, originally, as follows:

“Right-of-Way Clearing. The right-of-way should be a minimum of eighty feet, and in general should be equal to the bottom width of the ditch, plus seventy feet. Widths above that at the discretion of the board and the engineer. Right-of-way for team ditches should not be less than enough to leave a clear ten-foot berm on each side and room for the waste banks.
“All trees and shrubs are to be cut off the entire right-of-way and burned or otherwise removed, to the end that the right-of-way may have a clean, neat appearance. Clearing will be paid for per acre per price bid.”

However, before the. contract was let to appellee, the last paragraph of § 24 was changed to read as follows:

“That all trees and shrubs are to be cut off the entire right-of-way and removed back or under the spoil-banks, to the end that the right-of-way have a clean, neat appearance. ’ ’

Other parts of the contract provided that the Bayou Meto excavation should be a width of fifty feet at the bottom, with sloping banks, and the evidence shows that the excavation work was intended to be done, and was done, with a large dredge boat fifty-four feet in width with a boom of sufficient length to deposit the waste seventy-five feet on each side from the center of the stream or ditch. The evidence also shows that it was the intention of appellant to cut the trees, and then remove the stumps and trunks and debris with the dipper of the dredge. All of the parties connected with the work, including- the commissioners, doubtless ha.d in mind that the clearing would be done in that way at the time the contract was made, but there is no specification in the contract with reference to that part of the work except those provisions quoted above. That method was pursued in doing- the clearing- from the beginning- of the work on Bayou Meto at station 3 up to station 429 when it was found that on account of the low banks and the depth of the stream there was not enough waste material to cover the logs, stumps and other debris so as to prevent it floating- back into the stream in times of high water and the same could not be handled and deposited by the dredge boat outside of the limits of the right-of-way; hence it was found necessary to clear the right-of-way by use of teams so that the debris could be hauled outside the limits of the right-of-way. Appellee claims that this constituted a change in the contract for which he is entitled to extra pay on force account, as provided in § 25 of the specifications. The chancery court took this view of the matter and allowed appellee the item of $9,097.59, which included the cost of clearing and the fifteen per cent, additional provided by the contract for payment on force account. Our conclusion is that the allowance was improper, and that the item did not fall within the clause providing for payment for extra work. Section 25 -was not intended to cover extra cost of different methods of doing the work unless it constituted a change in the plans and specifications. The intention of the parties, as gathered from a fair interpretation of the language used, is that it was to provide compensation for work which was not specified in the contract. There could be no claim on account of change in the method of doing the clearing, for there was no method specified. All that the contract provided on that subject was that the “ trees and shrubs are to be ■cut off the entire right-of-way and removed back or under the spoil-banks, to the end that the right-of-way may have a clean, neat appearance.” The effect of this provision was to require that all of the debris be placed either under the spoil-banks or removed from the right-of-way back of the spoil-banks; otherwisethe right-of-way could not “have a clean, neat appearance.” Under those terms of the contract, the debris could not be left exposed on the right-of-way, and if there was not sufficient deposit of waste dirt to constitute a spoil-bank to cover the debris, then, under the contract, it was appellee’s duty to remove it off of the right-of-way.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
272 S.W. 840, 168 Ark. 1157, 1925 Ark. LEXIS 385, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bayou-meto-drainage-district-no-1-v-kochtitzky-ark-1925.