Bayne v. United States

195 F. 236, 115 C.C.A. 188, 1912 U.S. App. LEXIS 1367
CourtCourt of Appeals for the Eighth Circuit
DecidedMarch 19, 1912
StatusPublished
Cited by8 cases

This text of 195 F. 236 (Bayne v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bayne v. United States, 195 F. 236, 115 C.C.A. 188, 1912 U.S. App. LEXIS 1367 (8th Cir. 1912).

Opinion

CARLAND, Circuit Judge.

Bayne & Hewett brought suit against the United States to recover the sum of $4,432.88, which they claimed was a balance due them on a contract and supplemental contract entered into between them and the United States on December 21, 1907, for the construction of a bridge across the Mississippi river at Ft. Snelling, Minn. The action was brought under the provisions of Act March 3, 1887, c. 359, 24 Slat. 505 (U. S. Comp. St 1901, p. 752), and was tried to the court. Findings of fact and conclusions of law were made upon which judgment was rendered in favor of Bayne & Hewett for $1,002.50. Finding of fact No. 7 is as follows:

“In const rue ting tlxe center pier the plaintiffs used 243 piles, 191 of which wore over 33 feet in length; but of these 191 only S9 were driven more than 33 feet, and it was deemed necessary l>y the engineer officer to drive no more than SO to a depth of more than 33 feet.'’

The sum for which judgment was rendered was the amount which the United States had withheld as a penalty for delay in performance of the contract. The trial court held that the delay was caused by the United States and not by Bayne & Hewett; therefore that no penalty accrued to the United States.

The actual cost of driving 191 piles more than 33 feet, less $9 for each 33-foot pile in place, was $4,750.60. This amount, less $1,320.22 paid by the United States before suit was brought for driving 89 piles more than 33 feet, plus the sum of $1,002.50 wrongfully withheld for delay in performance of the contract, is the sum for which judgment was asked by Bayne & Hewett, viz., $4,432.88.

In order that the real situation of the parties may be understood, it is necessary to set out in full paragraph No. 4 of the specifications attached to the original contract, and the supplemental agreement-referred to in the findings of fact:

“Fourth. Under the center pier shall be driven 200 piles, or more if required by the engineer in charge, spaced about 3 feet O. to 0. in each direction. Piles to be about 30' in length and spaced as shown on plan. The piles shall be of straight, sound, live timber, free from cracks, shakes and rotten knots, of a good quality of pine or oak. They must show an even gradual taper and must have a dimension of not less than 12", 3' from the butt and at least 6" at the small end. The bark must be removed from the piles. Piles shall be well and carefully driven so as to be plumb and true to line and distance. They shall be shod with cast-iron points, where required by the engineer in charge, and fitted with rings at the top while driv-. ing. or driven with a follower. They are to be driven full length, or to such depth that the pile will not penetrate 5" or more under ten successive blows, of a 3,000 pound hammer dropping 20 feet. After being driven, piles are to be sawed off below low water line, as directed by the engineer in charge*. Around the pier, outside of sheet piling, shall he driven a row of piling which are to be cut off at a higher elevation, to support the sheet piling.”
[238]*238“(1) This supplemental agreement entered into this fourth day of May, nineteen hundred eight, between Major Francis R. Shunk, Corps of Engineers, United States Army, of the first part, and Bayne & Hewett, a copartnership consisting of A. X. Bayne, W. S. Hewett and A. E. Hewett of Minneapolis, in the county of Hennepin, state of Minnesota, of the second part, witnesseth, that the said Major Francis R. Shunk for and in behalf of the United States of America, and the said Bayne & Hewett, do covenant and agree, to and with each other, as follows:
“That whereas the nature of the sub-soil at the center pier of the bridge across the Mississippi river now being constructed under contract. between the said Major Francis R. Shunk, corps of engineers, for and in behalf of the United States of America, and the said Bayne & Hewett, entered into December twenty-one (21) nineteen hundred and seven (1907), is such that longer piles are necessary than are provided for in the specifications forming part of said contract:
“Now, therefore, it is agreed that the party of the first part shall pay to the party of the second part, in addition to the sums provided for in the aforesaid contract, the actual cost, to be agreed upon between the party of the first part and the party of the second part, of furnishing and driving such number of piles as may be deemed necessary by the engineer officer to drive to a greater depth than -thirty-three (33) feet, less the sum of nine dollars ($9.00) for each such pile, the estimated cost of a thirty-three (33) foot pile in place, provided that it is distinctly understood and agreed that the additional payment to be made under this supplemental agreement shall in no case exceed the sum of five thousand dollars ($5,000) or he such as to increase the total cost of the bridge, including all expenses connected therewith, above the sum of two hundred and fifty thousand dollars ($250,000).
“It is hereby further understood and agreed that, except as herein specifically set forth, the contract dated December 21, 1907, shall remain in full force and effect.”

Subsequent to the making of the findings of fact and conclusions of law, counsel for Bayne & Hewett moved the court to amend finding of fact No. 7 by striking out the last two lines of said finding and adding thereto the following:

“All piles that were driven by plaintiffs were so driven under the direction and supervision of the defendant’s engineer officer in charge of the work.”

The motion i to amend was overruled. ■ This ruling is assigned as error, and, we think, correctly. There was no evidence that the engineer officer did not deem it necessary to drive more than 89 piles to a depth of more than 33 feet. On the contrary, there was no dispute in the testimony which established the fact that all piles driven by the plaintiffs were so driven under the direction and supervision of the defendant’s engineer in charge of the work. Capt. George W. Freeman, a witness called by the United States, testified as follows:

“Q. You are an assistant engineer? A. Yes, sir. * * *
“Q. Were you in immediate charge of the construction of the Ft. Sneiling bridge? A. I was. * * *
Q. From the beginning to the end? A. Yes, sir. * * *
“Q. What were your duties in charge of that bridge with respect to the driving of piles? A. To see that they conformed to the specifications.
“Q. That is, as to penetration? A. Yes, sir; and also the kind of piles, whether they were of proper quality and all that sort of thing.
“Q. Quality and penetration? A. Yes, sir.
“Q. You exacted of the contractors that the piles should be driven to the required point of resistance, did you? A. Yes, sir.”

[239]*239On cross-examination the witness also testified :

“Q. All the other piles were driven under your direction? A. All the piles were driven under my direction.
“Q. And you never at any time during the completion of the center pier ordered them to stop using long piles? A. I did not; no, sir.
“Q.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Southern Gulf Lumber Co.
106 F. Supp. 815 (S.D. Alabama, 1952)
Northern Pac. Ry. Co. v. United States
70 F. Supp. 836 (D. Minnesota, 1946)
Champlin v. Commissioner
71 F.2d 23 (Tenth Circuit, 1934)
Barnebey v. Barron G. Collier, Inc.
65 F.2d 864 (Eighth Circuit, 1933)
Burnett v. Hopwood
244 N.W. 254 (Supreme Court of Minnesota, 1932)
Indemnity Ins. Co. of North America v. Levering
59 F.2d 719 (Ninth Circuit, 1932)
C. C. Mengel & Bro. Co. v. Handy Chocolate Co.
10 F.2d 293 (First Circuit, 1926)
Ascension Red Cypress Co. v. New River Drainage Dist.
90 So. 165 (Supreme Court of Louisiana, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
195 F. 236, 115 C.C.A. 188, 1912 U.S. App. LEXIS 1367, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bayne-v-united-states-ca8-1912.