Bauman & Garrity of Lakeville, Inc. v. George E. Emerson, Inc.

540 A.2d 710, 14 Conn. App. 261, 1988 Conn. App. LEXIS 145
CourtConnecticut Appellate Court
DecidedApril 26, 1988
Docket5507
StatusPublished
Cited by8 cases

This text of 540 A.2d 710 (Bauman & Garrity of Lakeville, Inc. v. George E. Emerson, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bauman & Garrity of Lakeville, Inc. v. George E. Emerson, Inc., 540 A.2d 710, 14 Conn. App. 261, 1988 Conn. App. LEXIS 145 (Colo. Ct. App. 1988).

Opinion

Borden, J.

The plaintiff, a plumbing and heating contractor, brought this action against the defendant, a general contractor, for breach of an alleged conditional oral agreement by the defendant to award the plaintiff the mechanical portion of a construction project. The plaintiff appeals from the judgment rendered in [262]*262favor of the defendant, after a jury trial, claiming that the trial court erred (1) in its instructions to the jury, and (2) in denying the plaintiffs motion to poll the jury after the verdict was announced. We find error.

The plaintiffs theory of recovery, as alleged in its complaint and supported by the evidence, was that the defendant contacted the plaintiff to solicit a bid for plumbing, heating and air conditioning work as a subcontractor on a proposed addition to the Salisbury Bank (bank). The bid was solicited by the defendant in conjunction with its proposed bid to the bank to perform the project as a general contractor. The defendant’s bid had to be submitted to the bank by 2 p.m. on September 1,1983. The plaintiff claimed that the defendant represented that, in order to meet the defendant’s bid submission deadline, the plaintiff had to submit its bid to the defendant by 12 noon on that day so that the defendant could timely submit its bid.

At 11:43 p.m. on September 1, the plaintiff submitted a bid to the defendant. The plaintiff claimed that the defendant’s agent represented to the plaintiff that its bid was the lowest, that the plaintiff would be designated as a subcontractor in the bid to the bank, and further that if the defendant was awarded the general contract, the plaintiff would be awarded the plumbing, heating and air conditioning subcontract. The defendant used the plaintiff’s bid in the bid to the bank. The defendant was awarded the general contract but refused to award the plaintiff the subcontract.

The defendant claimed that no acceptance of the plaintiff’s bid éver took place, and that any representations made by the defendant to the plaintiff regarding whether the plaintiff would be used on the project depended on whether the plaintiff’s bid turned out to be the lowest. Before 2 p.m. on September 1, and while the defendant’s president was en route to the [263]*263bank to submit the defendant’s bid on the project, the defendant received a lower bid from another subcontractor. After the defendant’s bid was accepted by the bank, the defendant employed that other subcontractor to do the mechanical portion of the project, and executed a formal written contract with that subcontractor after approval of the subcontractor by the owner and architect.

The plaintiff first claims that the court erred by charging the jury that, before it could find that the plaintiff’s bid was accepted by the defendant and a contract formed, the jury first had to conclude that the plaintiff submitted the lowest bid before the time that the defendant delivered its bid to the bank.1 We agree.2

[264]*264The court erred by instructing the jury that it must first find that the plaintiffs bid was the lowest at the time the defendant submitted its bid on the project to the bank. This fact, however, was not relevant to the plaintiffs theory of the case. The plaintiff’s case was based upon proof that the defendant accepted the plaintiff’s bid orally on September 1 and created a contract by indicating to the plaintiff that, if the defendant was awarded the contract on the project, the defendant would use the plaintiff as a subcontractor. The plaintiff’s legal claim was that its bid constituted an offer to which the defendant’s agent manifested an acceptance subject only to the condition precedent that the defendant be chosen as the general contractor on the project. See generally J. Calamari & J. Perillo, Contracts (3d Ed.) §§ 11-1, 11-2, 11-5.

[265]*265“A condition precedent is a fact or event which the parties intend must exist or take place before there is a right to performance. A condition is distinguished from a promise in that it creates no right or duty in and of itself but is merely a limiting or modifying factor. If the condition is not fulfilled, the right to enforce the contract does not come into existence. Whether a provision in a contract is a condition the nonfulfilment of which excuses performance depends upon the intent of the parties, to be ascertained from a fair and reasonable construction of the language used in the light of all the surrounding circumstances when they executed the contract.” (Citations omitted.)Lach v. Cahill, 138 Conn. 418, 421, 85 A.2d 481 (1951). The issue of whether or not the plaintiffs bid was the lowest simply was not an issue in this case. Instead, whether the plaintiffs bid was accepted by the defendant as alleged was the central factual and legal dispute for the jury to determine.3 The challenged instruction, therefore, [266]*266had the effect of charging the plaintiffs theory of recovery out of the case and, under the circumstances, was tantamount to improperly directing a verdict in the defendant’s favor.4

There is error, the judgment is set aside and the case is remanded for a new trial.

In this opinion the other judges concurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Connecticut Associated Builders & Contractors v. City of Hartford
740 A.2d 813 (Supreme Court of Connecticut, 1999)
Connecticut A. Bldrs. v. city/hartford, No. Cv-98-0584037-S (Dec. 17, 1998)
1998 Conn. Super. Ct. 14807 (Connecticut Superior Court, 1998)
Connecticut Assoc. Builders v. Anson, No. Cv-98-0579841-S (Oct. 26, 1998)
1998 Conn. Super. Ct. 12143 (Connecticut Superior Court, 1998)
Sicaras v. City of Hartford
692 A.2d 1290 (Connecticut Appellate Court, 1997)
Polverari v. Peatt
614 A.2d 484 (Connecticut Appellate Court, 1992)
Milward Corp. v. City of Hartford, No. 702290 (Dec. 6, 1991)
1991 Conn. Super. Ct. 10111 (Connecticut Superior Court, 1991)
Swenson v. Sawoska
559 A.2d 1153 (Connecticut Appellate Court, 1989)
Nisbet v. Olmeda
544 A.2d 642 (Connecticut Appellate Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
540 A.2d 710, 14 Conn. App. 261, 1988 Conn. App. LEXIS 145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bauman-garrity-of-lakeville-inc-v-george-e-emerson-inc-connappct-1988.