Bauer v. Cook

CourtMontana Supreme Court
DecidedJune 13, 1978
Docket13889
StatusPublished

This text of Bauer v. Cook (Bauer v. Cook) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bauer v. Cook, (Mo. 1978).

Opinion

No. 13889 IN THE SUPREMF: COURT OF THE STATE OF MONTANA

B. J. BAUER, JR., d/b/a BAUER CONSTRUCTION COMPANY, Plaintiff and Respondent,

JAMES DAVID COOK and DIETA MARIA COOK, husband and wife,

Defendants and Appellants.

Appeal from: District Court of the Fourth Judicial District, Honorable Jack L. Green, Judge presiding. Counsel of Record:

For Appellants: Tipp and Hoven, Missoula, Montana Thomas W. Frizzell argued, and Raymond P. Tipp argued, Missoula, Montana For Respondent: Skelton and Knight, Missoula, Montana Robert Skelton argued, Missoula, Montana

Submitted: February 2, 1979

Filed: JUN Mr. Justice John C. Sheehy delivered the Opinion of the Court.

This is an appeal from a judgment of the District Court, Missoula County, foreclosing a mechanic's lien on a dwelling house and directing defendants to pay the lien- holder's costs and attorney fees. In January 1975, James and Dieta Maria Cook contacted Blaisus J. Bauer, Jr., a building contractor, for the purpose of discussing the construction of a dwelling house on property located in Missoula County, Montana. Bauer, who had been in the construction business since 1971 and had built approximately thirty houses in that time, agreed to build the home. On February 19, 1975, the parties entered into a contract whereby Bauer agreed that the proposed house would be "turn-key" complete within ninety days after commence- ment of work. The Cooks agreed to pay Bauer in the following manner : "A. 2 0 % of cost upon completion of floor.

"B. 2 0 % of cost upon completion of framing, roofing and exterior windows & doors. "C. 2 0 % of cost upon completion of rough wiring, plumbing & heating. "D. 20% of cost upon completion of sheet rock and texturing. "E. 2 0 % of cost upon completion . . ." The contract plans and specifications were presented to

the Western Federal Savings and Loan Association of Missoula, Montana, for approval of a loan to finance the construction. The loan was approved and an account opened whereby the funds were to be disbursed in accordance with the contract and Western Federal's disbursement in- structions, which required that all disbursement requests be approved and signed by the Cooks and a loan officer. Bauer began construction immediately. Upon com- pletion of the floor, a building inspector for Western Federal inspected the work and approved a disbursement of $8,301.33 to Bauer. The Cooks also approved the dis-

bursement. Upon completion of the framing, roofing, and exterior windows and doors, a similar procedure took place.

Then, on April 1, 1975, after the building inspector had inspected the rough wiring, plumbing, and heating, and approved the disbursement, Dieta Cook refused to sign the disbursement request. Mrs. Cook refused to give her signature because she felt Bauer had not performed his part of the contract. A handwritten "Statement of Understanding" was given to Bauer by the Cooks, demanding that thirty-one

items be completed before the disbursement request would be signed. Bauer explained to the Cooks that he could not

continue construction without the funds, but Mrs. Cook refused to change her position. On April 4, 1975, Bauer ceased work and did not return to the construction site. Thereafter, four days later, he filed and perfected a mechanic's lien in the office of

the Clerk and Recorder, Missoula County, under the provisions

of section 45-501, et seq., R.C.M. 1947, now section 71-3-501, et seq. MCA. Bauer claimed the Cooks owed him $8,300 for labor and materials. This amount was reduced to $3,000 after the Cooks paid $5,300 to various materialmen. A suit to foreclose on the lien was filed April 22, 1975. Trial was commenced without a jury, in District Court, Missoula County on April 19, 1976. Three days later, due to calendar restrictions, the District Court ordered that the trial would be continued indefinitely. On December 9, 1976, the parties agreed to submit the case to the court without further testimony. The District Court entered -3- findings of fact, conclusions of law and judgment of foreclosure on March 24, 1977. Bauer was awarded $3,000 as foreclosure of the mechanic's lien and $1,000 as reasonable attorney fees.

On appeal, the Cooks have raised two issues: 1. Did Bauer abandon the project for which he had contracted, thereby rendering his filing of the mechanic's lien improper? 2. Did the District Court err in failing to reduce Bauer's recovery under the lien due to his defective performance of the contract? The general rule in Montana is that a mechanic's lien arises only upon completion (or substantial completion) of the contracted work. Western Plumbing of Bozeman v. Garrison (1976), 171 Mont. 85, 556 P.2d 520. However, the general rule does not apply if the laborer or material- man has been prevented from completing the work by the breach of the owner or a third party. Intermountain Electric, Inc. v. Berndt (1974), 164 Mont. 67, 518 P.2d 1168. In the case on appeal the alleged breach occurred when the Cooks refused to sign the disbursement request which had been presented to them by Bauer. The Cooks con- tend (1) under the circumstances, their refusal to sign did not constitute a breach of contract, and (2) if they did breach the contract, Bauer was nonetheless unjustified in abandoning the contract. In Gramrn v. Insurance Unlimited (1963), 141 Mont. 456, 378 P.2d 662, we said: "The rule is stated in Corbin on Contracts, § 946, as follows: "'The non-payment of an installment of money when due will always create a right of action for that money, but it will not always be a total breach.' "Thus, it depends upon the particular facts of each case whether or not non- payment of an installment is a total breach enabling the contractor to cease work, or whether it is merely a partial breach entitling the contractor to sue for the partial breach, but not permitting him to abandon the contract." The District Court concluded that Bauer completed

the rough wiring, plumbing and heating on or about April 1, 1975, and that the building inspector examined the work and approved the disbursement of $8,300 to Bauer, but Dieta

Cook refused to sign the disbursement request. In reviewing findings of fact in a civil action tried by the District Court without a jury, this Court is confined to determining whether there is substantial credible evidence to support those findings. Hornung v. Estate of Lagerquist (1970), 155 Mont. 412, 473 P.2d 541. Although conflicts may exist in the evidence presented, it is the duty and

function of the trial judge to resolve such conflicts. His findings will not be disturbed on appeal where they

are based on substantial though conflicting evidence. Fausett v. Blanchard (1969), 154 Mont. 301, 463 P.2d 319,

Finally, in determining whether the trial court's findings are supported by substantial evidence this Court must view the evidence in the light most favorable to the prevailing

party. Hellickson v. Barrett Mobile Home Transport, Inc. (1973), 161 Mont. 455, 507 P.2d 523. The record here contains the testimony of the sub- contractors who installed the rough wiring, plumbing, and heating prior to the inspection and approval of the work by the employee of the lending institution.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hellickson v. Barrett Mobile Home Transport, Inc.
507 P.2d 523 (Montana Supreme Court, 1973)
Intermountain Electric, Inc. v. Berndt
518 P.2d 1168 (Montana Supreme Court, 1974)
Western Plumbing of Bozeman v. Garrison
556 P.2d 520 (Montana Supreme Court, 1976)
Gramm v. Insurance Unlimited
378 P.2d 662 (Montana Supreme Court, 1963)
Fausett v. Blanchard
463 P.2d 319 (Montana Supreme Court, 1969)
Hornung v. Estate of Lagerquist
473 P.2d 541 (Montana Supreme Court, 1970)
Ballenger v. Tillman
324 P.2d 1045 (Montana Supreme Court, 1958)
Claver v. Rosenquist
499 P.2d 1235 (Montana Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
Bauer v. Cook, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bauer-v-cook-mont-1978.