Bates Fabrics Inc. v. Public Utilities Commission

447 A.2d 1211, 1982 Me. LEXIS 721
CourtSupreme Judicial Court of Maine
DecidedJuly 15, 1982
StatusPublished
Cited by4 cases

This text of 447 A.2d 1211 (Bates Fabrics Inc. v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bates Fabrics Inc. v. Public Utilities Commission, 447 A.2d 1211, 1982 Me. LEXIS 721 (Me. 1982).

Opinion

VIOLETTE, Justice.

Bates Fabrics, Inc. appeals pursuant to 35 M.R.S.A. § 303 (1978) and M.R.Civ.P. 73(b) from an order of the Public Utilities Commission denying Bates’ “Petition ... to Determine ... Status as a Qualifying Small Power Producer and to Establish Rate for Purchase of Electricity.” The Commission determined that under the Small Power Production Facilities and Cogeneration Facilities Act, 35 M.R.S.A. § 2321-2328 (Supp. 1981), [hereinafter referred to as the SPPFA] it did not have the authority to decide the dispute between Bates and Central Maine Power Company concerning the sale price of electricity by Bates to CMP where the parties had contractually agreed to a specified price. We deny the appeal and affirm the Commission’s decision.

[1212]*1212On June 1, 1977, Bates, CMP and Cumberland Securities Corp., a wholly owned subsidiary of CMP, entered into a contract which provided for the use and maintenance by Bates of various hydroelectric generating units owned by Cumberland. In addition, paragraph 2 of the contract detailed the financial relationship between Bates and CMP with respect to the hydroelectric units as follows:

Electricity from units not repaired or maintained by Bates but operated on behalf of CMP by Bates (hereinafter called “CMP Units”) will be delivered to CMP and not used by Bates. Bates will assume operating and rack cleaning costs only for these units. CMP will pay Bates three mills per kilowatt hour generated on CMP units operated by Bates.
Any excess power generated on the Bates units above Bates’ electric load will be delivered to CMP and paid for by CMP on a step-rate basis with the rate being three mills per kilowatt hour for the first 500,000 kilowatt hours delivered in each month and five mills per kilowatt hour for all kilowatt hours delivered in access [sic] of 500,000 kilowatt hours in each month. Said rates may be increased by mutual agreement of Bates and CMP to apportion extra costs imposed upon Bates by reason of non-routine repairs and maintenance and shorter amortization periods remaining under the term of this contract.

Within two years after the contract had been executed, federal and state legislation was enacted to encourage and, in some instances to regulate the purchase of hydroelectric electricity by public utilities from small power production facilities and cogen-eration facilities. See 16 U.S.C. § 824a-3 (Supp.1982); 35 M.R.S.A. § 2321-2328 (Supp.1981). Pursuant to the pertinent enabling statute, known as the Public Utility Regulatory Policies Act [hereinafter referred to as PURPA], the Federal Energy Regulatory Commission promulgated several rules to effectuate the purposes of the act, one of which states that purchases of electricity shall be at “just and reasonable” rates which are presumed to be the equivalent of the utility’s “avoided costs.” 18 CFR § 292.304(a)(1)(i) (1981). The Maine PUC has similarly provided that the “standard” rate of purchase “shall equal the purchasing utility’s avoided energy costs.” Me. Pub.Util. Comm’n Rules and Regulations, Chap. 36, § 4 B(3)(a).

On July 7, 1981, Bates petitioned the PUC, requesting that the Commission require CMP to pay an amount equal to avoided costs rather than the contract price for the electricity produced by Bates.1 A hearing before a Commission Examiner was held on August 18, 1981. The Commission granted CMP’s motion to dismiss the petition on September 30, 1981. The Commission ruled that the SPPFA authorized it to determine the purchase price of power only when the parties were “unable to mutually agree to a ... price for the electricity produced by the public utility.” 35 M.R. S.A. § 2326. Since the contract between Bates and CMP fixed the purchase price, the PUC ruled that Bates could not seek its intervention in the dispute, and in effect indicated that Bates’ complaint of unfair rates was simply not evidence of a lack of mutual agreement on a price.2

The Commission also rejected Bates’ argument that agency jurisdiction could alternatively be premised on a paragraph of the private contract which stated:

In addition to the other provisions contained in this contract, the parties hereby reserve the right to modify or amend the contract at any time to comply with the ruling or decision of any authority or [1213]*1213agency of the Federal Government or the State of Maine having jurisdiction hereof, but this contract shall only be modified under the provisions of this paragraph as to such part as the ruling or decision of such authority or agency will require.

The PUC pointed out that the provision did not

demonstrate that the parties are not mutually agreed on the price of electricity. Section 6 [of the contract] does not provide a vehicle for one of the parties to the contract to seek the intervention of a governmental agency for the express purpose of modifying the contract. It merely provides a mechanism for handling orders by governmental agencies once an agency has ruled.

Following the issuance of the Commission’s order, Bates petitioned the agency for a rehearing and reopening of its case. This petition was denied, and Bates has seasonably appealed to this court from the PUC order.

The question raised by its appeal is one of first impression in this jurisdiction which requires us to interpret the meaning and intent of the language of the SPPFA. Because Bates has also argued that the PUR-PA requires the Maine Public Utilities Commission to decide this case, we must also determine the import of the pertinent provisions of the federal regulatory scheme.

In 1978, Congress enacted the Public Utility Regulatory Policies Act (PURPA). Section 210 of the Act encourages the development of cogeneration and small power production facilities by authorizing the Federal Energy Regulatory Commission to set rates for the sale of electricity to electric utilities. The act provides in pertinent part:

(a) Cogeneration and small power production rules. Not later than 1 year after November 9, 1978, the Commission shall prescribe, and from time to time thereafter revise, such rules as it determines necessary to encourage cogeneration and small power production, and to encourage geothermal small power production facilities of not more than 80 megawatts capacity, which rules require electric utilities to offer to—
(1) sell electric energy to qualifying cogeneration facilities and qualifying small power production facilities and
(2) purchase electric energy from such facilities.
Such rules shall be prescribed, after consultation with representatives of Federal and State regulatory agencies having ratemaking authority for electric utilities, and after public notice and a reasonable opportunity for interested persons (including State and Federal agencies) to submit oral as well as written data, view, and arguments. ...

16 U.S.C. § 824a-3(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Public Utility Commission v. Gulf States Utilities Co.
809 S.W.2d 201 (Texas Supreme Court, 1991)
In Re Vicon Recovery Systems
572 A.2d 1355 (Supreme Court of Vermont, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
447 A.2d 1211, 1982 Me. LEXIS 721, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bates-fabrics-inc-v-public-utilities-commission-me-1982.