Bast Hatfield, Inc. v. Joseph R. Wunderlich, Inc.

78 A.D.3d 1270, 910 N.Y.S.2d 256
CourtAppellate Division of the Supreme Court of the State of New York
DecidedNovember 4, 2010
StatusPublished
Cited by4 cases

This text of 78 A.D.3d 1270 (Bast Hatfield, Inc. v. Joseph R. Wunderlich, Inc.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bast Hatfield, Inc. v. Joseph R. Wunderlich, Inc., 78 A.D.3d 1270, 910 N.Y.S.2d 256 (N.Y. Ct. App. 2010).

Opinion

Garry, J.

(l) Cross appeals (a) from an order of the Supreme Court (Hard, J.), entered April 21, 2009 in Albany County, upon a decision of the court in favor of, among others, defendant Joseph R. Wunderlich, Inc., and (b) from the judgment and amended judgment entered thereon, and (2) appeal from an order of said court, entered August 26, 2009 in Albany County, which denied a motion by Bast Hatfield, Inc. and defendant Western Surety Company to set aside the prior order.

In May 2003, Bast Hatfield, Inc. contracted with defendant Latham Circle, LLC to act as the general contractor for the construction of a Lowe’s Home Improvement Center on property owned by Latham Circle in the Town of Colonie, Albany County. Construction was set to begin in April 2003 and to be [1272]*1272substantially complete by October 31, 2003, with liquidated damages assessed against Bast thereafter. However, these dates were expressly conditioned on timely demolition by Latham Circle of several buildings occupying the construction site, including a Caldor’s store building. When the contract was signed, the demolition deadlines had already passed, and all of the buildings were still in place. Accordingly, two days before entering into the contract, Bast and Latham Circle executed an agreement (hereinafter the letter agreement) providing that no liquidated damages would be assessed against Bast until the later of 180 days after removal of the Caldor’s building or 165 days after completion of all demolition.

In July 2003, Bast executed a subcontract with defendant Joseph R. Wunderlich, Inc. (hereinafter Wunderlich) for site work including, among other things, removal of existing pavement, grading, and installation of storm drainage, sewer piping, and underground utilities. At the time the subcontract was signed, no demolition had yet occurred, and Bast had provided Wunderlich with a copy of the letter agreement tying the project completion dates to demolition of the buildings. The subcontract included a “time is of the essence” clause, providing for the “project” to be substantially complete no later than October 31, 2003, setting a final completion date of November 15, 2003, and further requiring Wunderlich to “coordinate its work so as to be completed by the date indicated on [Bast’s] progress schedule in support of the overall completion date.”

On August 1, 2003, Bast wrote to Latham Circle noting that the Caldor’s building had not been removed and proposing alternate dates for commencement and completion, contingent on completion of demolition by August 15, 2003. Demolition began in August 2003, but on August 15, 2003, Bast again wrote to Latham Circle expressing concern that it was not yet complete. On the same date, Bast and Latham Circle executed a change order altering Wunderlich’s scope of work and stating a substantial completion date for the Lowe’s project of January 31, 2004. After additional delays, the site demolition was eventually completed in late September 2003.

In addition to the demolition issues, Wunderlich encountered numerous other delays and obstacles after work began in August 2003; the parties disagree as to the reasons for these delays and the degree to which they impeded Wunderlich’s progress. On October 17, 2003, Bast sent Wunderlich a 48-hour written notice per the subcontract stating that its work was inadequate in several specified areas and that a failure to provide additional manpower and equipment by October 20, 2003 and to provide [1273]*1273Bast with a plan that would enable paving to begin by November 10, 2003 would result in its termination. Wunderlich’s principal, defendant Joseph R. Wunderlich, did not respond in writing, but did advise that his company would get the work done. There was no further correspondence until November 24, 2003, when Bast partially terminated Wunderlich. Thereafter Wunderlich completed the waterline and storm sewer system while Bast and other subcontractors carried out the other site work.

In April 2004, Wunderlich and plaintiff Gorman Brothers, Inc., a sub-subcontractor hired by Wunderlich to carry out certain work called for in the August 2003 change order, filed mechanics’ liens against the property; these were subsequently discharged pursuant to undertakings filed by Bast and defendant Western Surety Company under Lien Law § 19 (4). Bast commenced action No. 1 against Wunderlich and its principal seeking, among other things, damages for its alleged default under the subcontract. Wunderlich counterclaimed for damages for wrongful termination and commenced a third-party action against Bast1 and Western for payment pursuant to its mechanics’ lien. Gorman commenced action No. 2 against, among others, Bast, Wunderlich and Western, asserting that it had not been paid for its work under the sub-subcontract and seeking, among other things, to recover against the undertaking. After a lengthy nonjury trial on both actions, Supreme Court determined, among other things, that Bast had wrongfully terminated Wunderlich and that Wunderlich and Gorman were entitled to judgment on their breach of contract claims against Bast and Wunderlich, with damages to be collected against the undertakings.

Bast and Western moved to set aside this order, and Gorman and Wunderlich sought awards of counsel fees and costs. Supreme Court denied all of these applications. Bast and Western appeal from both orders and from the judgment and amended judgment entered upon the first order, and Gorman cross-appeals from the first order and the judgment and amended judgment entered thereon.

Bast contends that the October 31, 2003 substantial completion date in the subcontract was Wunderlich’s deadline and, thus, Supreme Court erred in finding that Wunderlich did not default by failing to complete its work by that date. In this regard, Bast claims that the court improperly relied on parol evidence in the form of the letter agreement between Bast and [1274]*1274Latham Circle that tied the project’s completion dates to the demolition schedule; in Bast’s view, the letter agreement was not part of the subcontract and did not affect Wunderlich’s contractual deadline. We find, to the contrary, that the court’s interpretation is supported by the unambiguous language of the subcontract, without reference to the letter agreement or other parol evidence.

“A written agreement that is complete, clear and unambiguous on its face must be enforced according to the plain meaning of its terms” (Science Applications Intl. Corp. v State of New York, 60 AD3d 1257, 1258 [2009] [internal quotation marks and brackets omitted]; see Greenfield v Philles Records, 98 NY2d 562, 569 [2002]). The subcontract provides that “the project” was to be substantially complete by October 31, 2003. The subcontract’s title page identified the “[p]roject” as “Lowe’s Colonie, NY” and, in accord therewith, the word “project” was used throughout the subcontract to refer to the Lowe’s construction as a whole. Wunderlich’s separate obligations were consistently referenced by the word “work.”2 Thus, under the plain language of the subcontract, the stated completion date for the “project” governed the construction as a whole and did not specifically pertain to Wunderlich’s scope of work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pizzarotti, LLC v. MDB Dev. Corp.
2025 NY Slip Op 05176 (Appellate Division of the Supreme Court of New York, 2025)
Mizenko v. Intertech Digital Entertainment, Inc.
166 N.Y.S.3d 366 (Appellate Division of the Supreme Court of New York, 2022)
Squire McBeasley, Inc. v. 36th Str, LLC
93 A.D.3d 1123 (Appellate Division of the Supreme Court of New York, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
78 A.D.3d 1270, 910 N.Y.S.2d 256, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bast-hatfield-inc-v-joseph-r-wunderlich-inc-nyappdiv-2010.