Basin Paving, Inc. v. Port of Moses Lake

737 P.2d 1312, 48 Wash. App. 180
CourtCourt of Appeals of Washington
DecidedJune 9, 1987
Docket7611-3-III
StatusPublished
Cited by6 cases

This text of 737 P.2d 1312 (Basin Paving, Inc. v. Port of Moses Lake) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Basin Paving, Inc. v. Port of Moses Lake, 737 P.2d 1312, 48 Wash. App. 180 (Wash. Ct. App. 1987).

Opinion

McInturff, C.J.

Basin Paving, Inc. brought an action alleging the Port of Moses Lake owed it $70,000 on a contract. The Port counterclaimed for the return of that same amount of money, alleging it had overpaid Basin on a previous contract. In its answer, Basin stated the parties had agreed, in the settlement of a dispute arising out of the first *181 contract, that Basin should retain all payments made by the Port to Basin prior to that date. The Superior Court found, inter alia, the Port was not aware of the $70,000 overpayment at the time it entered into the settlement and this unilateral mistake was induced by inequitable conduct on the part of Basin. Thus, the court reformed a general release executed by the parties in their settlement to indicate that the $70,000 overpayment was not included in its terms. Basin's appeal assigns error to these and others of the court's findings and conclusions. We affirm.

In 1983, Basin entered into a contract with the Port of Moses Lake to repair one of the Port's runways. By mid-September 1983, it was apparent the work would require about 37,000 tons of asphalt instead of the 47,000 tons the Port had listed in the specifications. Basin notified the Port of the underrun and of its probable claim for damages on October 24, 1983, and in March 1984 it submitted a written claim for $89,885 to the Port and to CH2M Hill, the consulting engineer for the project. Witnesses for Basin testified this amount represented the incidental costs it had apportioned in its bid to the 10,000-ton underrun. These witnesses further stated lost profits were not included in this claim.

Meanwhile, Basin had performed work under the contract throughout the summer and fall of 1983. The Port paid Basin progress payments during the course of this work. Eric Cutbirth, the project engineer for CH2M Hill, and Larry McAtee, the project coordinator for Basin, initiated such payments by meeting and agreeing on the percentage of work performed to date and then submitting a payment application for a given amount to the Port's commissioners for their approval. Once approved, a voucher was issued.

The first payment application was for $180,886.41 and was approved and paid on October 12, 1983. The second application was for $922,333.68, and the commissioners approved that amount on October 21, 1983. However, in preparing the voucher for payment two, the Port's book *182 keeper made a typographical error. She made the voucher for $992,333.68 instead of $922,333.68. Basin accepted the check, and in its bookkeeping listed the entire amount as received "on account". Mr. Albert DeAtley, president of Basin, testified he was aware of the overpayment by late fall 1983, or early 1984, but Basin retained the money because more than that sum was still owing under the contract.

Subsequently, two other payment applications were approved and paid by the Port: $150,438.24 in February 1984, and $4,387.42 in April 1984. These applications and their vouchers reflected a $922,000, rather than $992,000, payment on the total-paid-to-date lines. Mr. McAtee, of Basin, Mr. Cutbirth, of CH2M Hill and David Bailey, a manager for the Port, testified they were not aware of the overpayment during this time.

Negotiations of Basin's underrun claim continued throughout the winter, spring and summer of 1984. Mr. Cutbirth testified that in May 1984, Basin offered to settle for $35,000, and the Port countered for $13,000. Basin's witnesses did not contradict these figures. However, testimony concerning who handled the negotiations varied. Eric Cutbirth stated that Lawrence McAtee was the one principally involved on behalf of Basin, but he also testified they reached an impasse in September 1984 and referred the matter to the parties' attorneys. Mr. DeAtley contended that in the final negotiations he and Basin's attorneys were the only people involved for Basin.

In October and November 1984, Alan DeAtley, of Basin, James Correll, of CH2M Hill, and Mr. Bailey, for the Port, signed a settlement and release disposing of Basin's claim. The release recited that a dispute existed concerning Basin's claim for damages in excess of $150,000. (The difference between the March 1984 claim for some $89,000 in damages and this $150,000 figure apparently is attributable to an added claim by Basin for lost profits.) The release then provided:

*183 Now, therefore, in consideration of all Port's past payments to Basin plus payment of $66,268.67 retainage and an extra payment by Port to Basin of $20,500.00 because of Basin's claim and other valuable consideration, Port accepts Basin's 1983 material supplied and work performed and Basin unconditionally forever releases and discharges the Port and CH2M-HÍ11 from all claims . . .
Further, the Port unconditionally forever releases and discharges Basin from all claims of every kind whatsoever, now known or unknown, . . .

(Italics ours.)

Mr. Bailey said that on November 29, 1984, in the course of a final audit of the job, the Port for the first time discovered the overpayment. When it contacted Basin, Mr. DeAtley advised that Basin considered the $70,000 to be part of the settlement on the underrun. On January 5, 1985, Basin's bookkeeping showed the $70,000 as applied to the settlement.

In 1984, Basin had entered into a second contract to perform other work for the Port. In its final payment on that contract, the Port withheld the $70,000, which it viewed as an overpayment on the first contract. As a result, Basin brought this action. The Port counterclaimed, alleging the overpayment and a right of setoff, and Basin replied, asserting the release as a defense.

Following a bench trial, the court issued a memorandum opinion which held that the parties' release should be reformed. The court found Mr. McAtee had negotiated the settlement on behalf of Basin, and since neither he nor the Port was aware of the overpayment at that time, a mutual mistake existed. In the alternative, the court held reformation was mandated by the Port's unilateral mistake coupled with Mr. DeAtley's failure to disclose. The court viewed Mr. DeAtley's conduct as (1) inequitable, (2) a breach of the contracting party's duty to deal in good faith, (3) unconscionable, and (4) a breach of a fiduciary duty flowing from Basin's position as a constructive trustee of the $70,000.

Basin's appeal assigns error to several of the findings and *184 conclusions formulated from the Superior Court's memorandum opinion.

First, did the court err when it relieved the Port of its obligation under the terms of the release? We note that a release which by its terms is clear and unambiguous will not be overturned short of "fraud, false representation, overreaching or a mutual mistake of which the evidence is clear and convincing." Metropolitan Life Ins. Co. v. Ritz, 70 Wn.2d 317, 321, 422 P.2d 780 (1967). Basin argues there was no such evidence in this case. We disagree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

G. Steven Hammond, M.d. v. The Everett Clinic, Pllc
Court of Appeals of Washington, 2021
Reynolds v. Farmers Ins. Co.
960 P.2d 432 (Court of Appeals of Washington, 1998)
Reynolds v. Farmers Insurance
960 P.2d 432 (Court of Appeals of Washington, 1998)
In Re Estate of Harford
936 P.2d 48 (Court of Appeals of Washington, 1997)
Gill v. Waggoner
828 P.2d 55 (Court of Appeals of Washington, 1992)
Parrish v. United Bank of Arizona
790 P.2d 304 (Court of Appeals of Arizona, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
737 P.2d 1312, 48 Wash. App. 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/basin-paving-inc-v-port-of-moses-lake-washctapp-1987.