Basin Electric Power Cooperative v. MPS Generation, Inc.

395 F. Supp. 2d 859, 2005 U.S. Dist. LEXIS 4466, 2005 WL 646213
CourtDistrict Court, D. North Dakota
DecidedMarch 21, 2005
DocketA1-05-29
StatusPublished

This text of 395 F. Supp. 2d 859 (Basin Electric Power Cooperative v. MPS Generation, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Basin Electric Power Cooperative v. MPS Generation, Inc., 395 F. Supp. 2d 859, 2005 U.S. Dist. LEXIS 4466, 2005 WL 646213 (D.N.D. 2005).

Opinion

ORDER GRANTING MOTION FOR PRELIMINARY INJUNCTION

HOVLAND, Chief Judge.

Before the Court is the plaintiff, Basin Electric Power Cooperative’s (“Basin Electric”) Motion for a Preliminary Injunction filed on February 14, 2005. Basin Electric also sought a temporary restraining order enjoining the Defendants from obtaining funds currently held in an escrow account pursuant to certain contracts described below, until a final determination of the merits is made in the above-entitled action. On February 25, 2005, the Court granted the Plaintiffs request for a temporary restraining order preventing the funds held in an escrow account at Wells Fargo Bank in Bismarck, North Dakota, from being disbursed until further Order of this Court.

A hearing on the motion for a preliminary injunction was held on Wednesday, March 16, 2005. Attorney John C. Kaps-ner appeared and represented the plaintiff, Basin Electric. Ron Rebenitsch testified on behalf of Basin Electric. Attorney Timothy Durick appeared and represented the Defendants. Lacy M. Henry testified on behalf of the Defendants.

I. BACKGROUND

The circumstances giving rise to this action have not changed since the Court issued its temporary restraining order. This action arises out of a contract dispute between Basin Electric and the Defendants. Basin Electric is a North Dakota cooperative principally located in Bis *861 marck, North Dakota, which provides electricity to its member cooperatives. Defendant MPS Generation, Inc., (“MPSG”) is a North Carolina corporation principally located in Wilmington, North Carolina, and is licensed to do business in the State of North Dakota. Defendants Mechanical Plant Services of North Carolina, Inc., (“MPS”) and Light Logix, Inc., are North Carolina corporations principally located in Wilmington. Defendant Lacy M. Henry is a resident of the State of North Carolina and is affiliated with MPSG, MPS, and Light Logix, Inc as either an owner or officer. Defendant Judy Henry, the wife of Lacy Henry, is a resident of the State of North Carolina, and purportedly an offi-eer/director of MPS, MPSG, and Light Logix, Inc. Defendant Keith D. Henry, a son of Lacy Henry, is a resident of the State of North Carolina and purportedly an officer/director of MPSG, MPS, and Light Logix, Inc.

Prior to the fall of 2003, Northern Border Natural Gas Pipeline approached MPSG regarding the possibility of recovering waste heat from the pipeline and converting it to electricity. MPSG then contacted Basin Electric to inquire as to whether it would be interested in the project. MPSG and Basin Electric then began negotiations. 1 During the negotiation process and at MPSG’s suggestion, MPSG and Basin Electric toured a facility in Canada that used equipment supplied by Or-mat Equipment. Both parties thought the equipment would suit their project. Thus, the negotiations continued with the expectation that technical equipment supplied by Ormat would be used.

On or about November 5, 2003, Basin Electric and MPSG entered into a series of contracts. In the Engineering, Procurement, and Construction Contract (“EPC Contract”), MPSG agreed to design and construct for the benefit of Basin Electric four waste heat recovery generation systems. Pursuant to the EPC Contract, Basin Electric agreed to pay MPSG a total of twenty-eight million, nine hundred thousand dollars ($28,900,000) in accordance with a “milestone payment schedule.” Basin and MPSG also entered into a contract (the “Operation and Maintenance Contract”) whereby MPSG agreed to operate and maintain the four waste heat recovery systems governed by the EPC Contract. Several other contracts were executed to facilitate the construction and operation of the waste recovery systems. Sometime after the contracts between Basin Electric and MPSG were executed, MPSG entered into a relationship with Ormat, to supply equipment capable of producing a specified amount of megawatts.

On November 13, 2003, Basin Electric, MPSG, and Wells Fargo Bank of North Dakota, entered into an escrow agreement. The escrow agreement provides for the release of the funds held in escrow to MPSG to the extent MPSG performed its obligations under the EPC Contract within the established deadlines. In the event MPSG failed to perform its obligations, the funds were to be returned to Basin Electric to enable it to ensure the waste heat recovery systems were constructed in accordance with the EPC Contract. To date, Basin Electric has deposited two million, fifty-two thousand dollars ($2,052,-000.00) into the escrow account at Wells *862 Fargo Bank as required by the EPC Contract.

Throughout the next several months, MPSG submitted invoices for work completed in accordance with the milestone payment schedule. Basin Electric reviewed the invoices and paid MPSG pursuant to the payment schedule. 2 Problems began during the performance of milestone five when it appeared MPSG was having difficulties meeting the specifications for the Waste Heat Oil Heater (WHOH). A July 29, 2004, letter from Basin Electric representative Ron Rebenitsch to Kip Waddell at MPSG detailed the problem:

As we have previously made you aware, Basin Electric Power Cooperative (Basin Electric) has had serious reservations about the design of the waste heat oil heater (WHOH). Therefore, to address these concerns, on July 27, 2004 engineers from Basin Electric and our subsidiary, Dakota Gasification Company (DGC), participated in two telephone conference calls with MPS Generation, Inc. (MPSG) and two WHOH vendors, ATS/Express LLC (ATS) and Heat Recovery Corp (HRC). MPSG has represented to us that ATS and HRC are experienced waste heat recovery heat exchanger manufacturers and Ormat had recommended both vendors for the Northern Border Cogeneration Projects. It is our understanding that the Ormat specifications provided to MPSG require a heat exchanger capable of transferring 99.3% of the available sensible heat in the Northern Border compressor/turbine exhaust gases to the oil loop. This level is unusually high. Basin Electric and MPSG agreed to consult ATS and HRC in an effort to clarify the safety, maintenance and engineering consideration involved.
To summarize the information provided by ATS and HRC, both stated the proposed design requirements far exceed normal heat exchanger design. The proposed approach temperatures are much smaller than normal, while the gas exit design temperatures in certain cases do not maintain a level sufficiently above dew point to prevent condensation and subsequent corrosion.
Neither manufacturer had ever designed a heat exchanger at these extreme conditions, not could they recall any heat exchangers designed to these conditions. Both manufacturers noted the design would result in the potential for the exhaust gases crossing the dew point, which in turn would lead to corrosion. Since these heat exchangers will operate in gas turbine exhaust temperature far above the auto-ignition temperatures of the oil, corrosion of the oil-filed heat exchanger piping would result in a significant risk of subsequent leaks, which, in turn, could cause a serious fire.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
395 F. Supp. 2d 859, 2005 U.S. Dist. LEXIS 4466, 2005 WL 646213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/basin-electric-power-cooperative-v-mps-generation-inc-ndd-2005.