Basil B. Wells, Inc. v. County Court

96 F. Supp. 677, 1951 U.S. Dist. LEXIS 2504
CourtDistrict Court, S.D. West Virginia
DecidedMarch 30, 1951
DocketNo. 552
StatusPublished

This text of 96 F. Supp. 677 (Basil B. Wells, Inc. v. County Court) is published on Counsel Stack Legal Research, covering District Court, S.D. West Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Basil B. Wells, Inc. v. County Court, 96 F. Supp. 677, 1951 U.S. Dist. LEXIS 2504 (S.D.W. Va. 1951).

Opinion

WATKINS, District Judge.

" This action grows out of a contract between plaintiff and defendants under which the plaintiff corporation undertook to clean and paint a bridge crossing the Ohio River at Huntington, W. Va., for the Cabell County Bridge Commission, an agency of the County Court of Cabell County, West Virginia. Plaintiff claims that the contract required it to remove only “unserviceable” paint and not all the paint before applying new paint. When the Bridge Commission stated that it would require the removal of all paint, plaintiff walked off the job. Plaintiff claims breach of its contract and asks damages of $30,533.44. In the alternative, plaintiff asks that the contract' be cancelled, in which event it asks damages of $20,533.44. After plaintiff left the job, defendants re-advertised for bids and let the job to another contractor. Defendants contend that plaintiff breached the contract, and by way of counterclaim ask for damages against plaintiff of $52,119.63. The case was tried by the court without a jury.

Three questions are presented. (1) Was there a valid contract between the parties? (2) Did that contract require plaintiff to remove all the existing paint before applying new paint? Both of these questions must be answered in the affirmative. (3) Were the defendants guilty of any fraud or misrepresentation in procuring the contract? This question is answered in the negative..

Prior to the time the written contract was executed, a question was raised as to whether the contract required the removal [678]*678of all paint, or only the unserviceable paint, before the three new coats of paint were to be applied. The parties met together before the contract was signed to eliminate any possible misunderstanding about this matter. Plaintiff contends that it was assured by defendants or their representatives that only the unserviceable paint need be removed. Basil B. Wells and John Ernst testified directly to that effect. The defendants contend that plaintiff was told that all paint had to be removed, and that Wells or Ernst, president and vice-president, respectively, of the plaintiff company, agreed to undertake the job with this understanding. Six witnesses testified directly to that effect, including George H. Wright, Artie Holley, James Brady, Frank Heiner, members of the Cabell County Bridge Commission, and Benjamin W. LeSueur, and Harry M. Brown, engineers of the firm of J. E. Greiner Company, employed by the Commission to advise them as to the proper method of painting and otherwise maintaining the bridge. After hearing this conflicting testimony in open court, after weighing the evidence, and considering the credibility of the various witnesses, as disclosed by their interest in the outcome of the trial, the reasonableness of their testimony, their opportunity for knowing the facts about which they have testified, their prejudice or lack of prejudice, their demeanor on the witness stand, their experience and fairness, in the light of admitted facts, and all the surrounding circumstances, I make the following findings of fact and conclusions of law:

Findings of Fact.

1. The bridge in question was constructed by a private corporation and was opened to the public as a toll bridge in 1926. It is of steel construction and has a total length of 2124 feet between abutments. In 1940 it was purchased by Cabell County, West Virginia, by the issuance of bonds secured by a trust indenture. It was thereafter operated'and maintained by the Cabell County Bridge Commission under statutory authorization. At all times material to this action defendants George H. Wright, Artie Holley, James Brady,' Frank Heiner and Ezra Midkiff were members of that Commission.

2. Major Herschel H. Allen, an experienced engineer and a partner of J. E. Greiner Company of Baltimore, Md., one of the outstanding engineering firms of the country, designed the bridge. By the terms of the trust indenture securing the bonds, this firm was to be employed by the County Court to inspect the bridge periodically and to make recommendations as to its operation and maintenance. Accordingly, the bridge was inspected annually by the engineering firm, which made appropriate recommendations to the County Court or the Bridge Commission with reference to maintenance of the bridge for the protection of the owner of the bridge and the bondholders.

3. The 1940 and 1941 inspections showed that the paint on the bridge was in poor condition. It had not been completely painted since it was built in 1926. The engineering firm recommended that areas of paint which no longer served to protect the metal be cleaned down to bare metal, primed with a coat of red lead and then covered with a finishing coat. This method of cleaning only the areas of damaged paint is known in the bridge painting trade as spot cleaning. The entire process of both cleaning the areas of damaged paint, priming with red lead and applying a finishing coat is known as spot cleaning and painting. Pursuant to this recommendation the bridge was spot cleaned. Red lead (which is a primer coat) was applied to the areas cleaned down to bare metal, and the entire bridge was then covered with a coat of green, paint. The type of green paint recommended by the engineers could not be obtained due to wartime restrictions, with the result that an inferior substitute was purchased' by the Commission and applied to- the bridge.

4. In 1943 the engineers recommended that the bridge be spot cleaned again and that the spots so cleaned be primeé again with red lead and another covering coat applied. The inspection in 1943 revealed a general failure of the green coat applied' in 1942. Chemical analysis revealed; that [679]*679this green paint contained certain harmful silicates which had been used as a filler by the manufacturer. Pursuant to this recommendation the Commission spot cleaned and spot painted the bridge in 1944. Each subsequent inspection revealed a progressive failure of the paint film. The 1947 report to the Commission contained the following recommendation: “This inspection has disclosed that a general breakdown and failure of the paint applied in 1942 is occurring over the entire bridge. It has further disclosed that disintegration of this paint coat is taking place under spot painting that was done during the summer of 1944. This indicates that any application of paint over existing coats is not economical and that before adequate protection of the metal can be provided the existing paint must be completely removed * *

On May 1, 1948, the annual report made by the engineering firm to the Commission contained the following recommendation: “The present bridge paint has deteriorated to such an extent that it must be replaced. It would not be advisable to attempt to save such portions of the surface as appear to be in good condition. The paint applied some six years ago has weathered badly and is subject to progressive cracking. This cracking would continue under any finish coats of new paint and would result in re-exposure of the steel. It is strongly recommended that all the old paint be removed and the surfaces thoroughly cleaned before applying new paint.” (Emphasis supplied.)

The engineers who made this report are the same engineers who subsequently prepared the specifications for the painting contract. There can not be the slightest doubt as to the meaning of the words “old paint” in that recommendation. It is crystal clear that the words “old paint” were used to distinguish the existing paint from the “new” paint to be applied.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
96 F. Supp. 677, 1951 U.S. Dist. LEXIS 2504, Counsel Stack Legal Research, https://law.counselstack.com/opinion/basil-b-wells-inc-v-county-court-wvsd-1951.