Barton v. Mirich

273 N.E.2d 115, 149 Ind. App. 395, 1971 Ind. App. LEXIS 422
CourtIndiana Court of Appeals
DecidedSeptember 16, 1971
Docket670A100
StatusPublished
Cited by6 cases

This text of 273 N.E.2d 115 (Barton v. Mirich) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barton v. Mirich, 273 N.E.2d 115, 149 Ind. App. 395, 1971 Ind. App. LEXIS 422 (Ind. Ct. App. 1971).

Opinion

Lowdermilk, J.

Plaintiff-appellants entered into a lawsuit against defendant-appellee to recover $7,323.64 paid to defendant-appellee by appellants under a construction contract, plus $10,000 damages.

The defendant-appellee filed three pleading Paragraphs of answer. In the first Paragraph of answer the appellee admitted that plaintiff-appellants had made payments of $7,-323.64 to him; the second Paragraph alleged an affirmative defense, charging the appellants breached the construction contract; the third Paragraph alleged the contract was rescinded and abandoned by the plaintiffs, to which were filed replies in denial. Defendant also filed his counterclaim demanding judgment against the plaintiffs.

The case came to trial before a jury and before the commencement of the trial the appellants amended their complaint by striking out allegations of fraud. THEN THE PARTIES STIPULATED AND AGREED THAT THE QUESTION OF WHETHER OR NOT THE CONTRACT WAS RESCINDED WILL NOT BE SUBMITTED TO THE JURY.

At the conclusion of the trial the jury returned its verdict, finding for the defendant-appellee and against the plaintiff-appellants. The court then entered judgment accordingly.

Plaintiff-appellants entered into a contract with defendantappellee, a construction company, for the construction of a residence in Lake County. Much of the contract had already been written out on a typewriter and there were blank spaces left therein, which blank spaces were asterisked and filled in at the time the parties sat down to look at the contract. The last sheet of the contract was an addendum, which was written in longhand and the contract was agreed upon and executed by and between the parties. From the evidence in the *397 case it appears that all parties fully understood the contract, even though plaintiff-appellants did not write any of the terms of the contract and the handwritten portion was solely that of the defendant-appellee. The defendant-appellee testified that everything written into the contract was discussed and agreed upon before he wrote freehand in the contract, and also, that what he had put on the addendum sheet was discussed and agreed upon before he wrote it up.

On June 8, 1966, the date of the execution of the contract, plaintiff-appellants made a down payment of $100 and made further payments as they could, including the proceeds from the sale of their own house, the total payments being $7,323.64.

The appellee, in his answer to the statement of said payment stated: “That defendant admits the allegation contained in rhetorical paragraph six (6) of plaintiffs’ complaint” (which was the allegation of the amount paid.)

The contract provided for the builder to erect, build and completely finish a residence according to plans and specifications, and in a good and substantial workmanlike manner. Plaintiff-appellants allege the failure of the defendant-appellee to comply with the above contract provisions and the disagreement as to the builder’s charge for “extras” led the plaintiff-purchasers to cancel the contract.

The major alleged areas of alleged non-compliance with the contract were water seepage inside the house, sagging ceilings throughout the house, installation of the wrong color and type of trim within the house, and the installation of the wrong color paneling within the house. There were further allega^ tions of deficiencies in almost every room of the house, which included water leakage. The defendant-appellee testified the water damage occurred because of lack of gutters, occasioned by the plaintiffs’ failure to indicate what kind of gutters they wanted installed, and leakage around a plumber’s flue, occasioned by the plaintiffs’ failure to select the plumbing fixtures which were to be installed.

*398 Plaintiff-appellants alleged that the ceiling was sagging in a six foot diameter and could be pushed up three inches in places because there was nothing holding it. This was in the living room, dining room and kitchen. However, defendantappellee’s employee, agent and architect testified that he did not recall the ceiling of the living room and dining room ever coming loose.

Plaintiff-appellants further testified that the contract provided for all natural trim to be white pine, but instead they received a variation of finish trim. Defendant-appellee testified that the contract called for natural white pine and this was used in some places but was not in other places because the plaintiff-appellants-purchasers had changed the specifications. The record shows disputed evidence as to several changes claimed by each of the respective parties to this litigation as to trim and other matters. Further evidence on the dispute was given by office manager James R. Helsel for defendantappellee, who testified that he telephoned the plaintiff-appellant Mrs. Barton and informed her that there were two different tones of paneling and Mrs. Barton had said she wanted the lighter. This, however, Mrs. Barton later denied.

The appellants testified that on February 7 or 8 Mr. Barton was last in the house and took pictures for evidence. He had a key to the door, but three days later defendant-appellee changed the locks on the doors to keep the plaintiff-appellants out.

On February 15th plaintiff-appellants made a demand upon defendant-appellee for the return of the money they had previously paid. This demand was made by a letter, written by plaintiff-appellants’ attorney. This situation was followed by the commencement of this lawsuit, about the middle of 1968.

Defendant-appellee testified that prior to the lawsuit he did not attempt to sell the house, but he did finish the house and sold it afterward.

The appellants’ claim for relief was based on the rescission *399 of the contract for the appellee to construct the house for the appellants; that defendant-appellee had sold the house to another purchaser and retained the money paid to him by plaintiff-appellants and that the verdict is contrary to law for defendant-appellee’s refusal to repay the appellants the sum of $7,323.64.

Appellants timely filed their motion for a new trial, which was by the court overruled.

The causes in appellants’ motion for a new trial urged herein are:

3. The verdict of the jury is contrary to law.

5. Error of law occurring at the trial as follows:

A. ) The court erred in refusing to give to the jury at the request of the plaintiffs each of the written instructions tendered and requested by the plaintiffs and numbered 1 and 2.

B. ) The court erred in giving to the jury at the request of the defendant each of defendant’s instructions numbered 3, 4, and 9 and to the giving of each of which instructions the plaintiffs duly objected.

Plaintiff-appellants also stated “. . . that all two causes for a new trial raise substantially the same question, therefore, they are grouped together and supported by one argument.”

The plaintiff-appellants’ written tendered instruction number 1, which was refused by the court, is as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

King v. Pollard
311 N.E.2d 454 (Indiana Court of Appeals, 1974)
Nicholas v. Zimmerman
307 N.E.2d 900 (Indiana Court of Appeals, 1974)
Memorial Hospital of South Bend, Inc. v. Scott
290 N.E.2d 80 (Indiana Court of Appeals, 1972)
Murphy v. Indiana Harbor Belt Railroad Company
289 N.E.2d 167 (Indiana Court of Appeals, 1972)
Snider v. Lewis
276 N.E.2d 160 (Indiana Court of Appeals, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
273 N.E.2d 115, 149 Ind. App. 395, 1971 Ind. App. LEXIS 422, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barton-v-mirich-indctapp-1971.